Key Takeaways
- Revenue nearly doubled, margins surged: H1 FY27 revenue grew 90.9% YoY to ₹52.68 crores, while EBITDA margin expanded 345 bps to 11.72% as fixed overheads barely moved against the volume jump.
- Order book provides near-term visibility: The ₹173 crores order book, plus ~₹200 crores under discussion, sets up H2 execution; all current orders are expected delivered by March.
- EHV entry is the structural re-rating story: A new 220 kV plant (capex ₹35–40 crores, 15,000 MVA capacity) targets a segment where single transformers sell for ₹6–70 crores, competition is thin, and existing customers want a single-vendor relationship.
- Customer approvals are unlocking new segments: The 17.6 MVA type test opens the solar generation market beyond wind, while UGVCL, GETCO and multiple private-sector vendor approvals widen the tender pipeline.
- What to watch next quarter: Whether the ~₹200 crores of orders under discussion convert within FY27, the pace of EHV plant commissioning (target: ~6 months), and any update on the ROCE math management declined to share on the call.
EHV Expansion: The Multiplier Bet
- Plant underway: Bhoomi Pujan held Oct 30, 2026 on 20,300 sq. meters at Bhiwadi, Rajasthan; PEB order placed with SML, delivery starting December, commercial production targeted in ~6 months from now.
- Capex and funding: Total outlay ₹35–40 crores, split between internal accruals plus IPO funds (~₹20 crores) and debt, with the ₹20 crores from internal accruals and IPO funds.
- Revenue math: 220 kV transformers start at ₹6–7 crores per unit and go up to ₹70 crores; management expects revenue to "multiply" upon entry.
- Margin path: EHV transformers carry higher engineering cost and lower relative material cost versus distribution transformers; initial PAT targeted at ~10%, with improvement expected once depreciation and interest are absorbed.
- Customer pull, not push: Existing buyers of Accord's ≤20 MVA transformers (JSW, Birla Group, ReNew Power, Inox Wind, Torrent Power, Adani Group) currently source 220 kV units elsewhere but prefer a single manufacturer for control and delivery pipeline, a dynamic management calls the reason it is "very hurried to start this 220 kV class."
- Power Grid approval path: Already approved up to 33 kV class; only a plant facility visit and upgradation approval needed for EHV, expected within 30 days once the plant is ready.
- Market backdrop: Delivery times for EHV transformers currently run 6–8 months to over a year; management believes even 100 new plants would not fulfill India's requirement, with imports still coming from China and Italy.
- ROCE undisclosed: When asked what return on capital employed the EHV expansion is expected to generate, management declined to answer on the call, saying "I will get back to you on this, right after this call."
Verma: "Because 220 kV transformer starts from INR6 crores, INR7 crores onwards per transformer, okay? And it goes up to INR70 crores value, single transformer. So, that is the reason if we enter into HV, whenever we enter into HV, the -- our revenue will multiply."
Order Book & Demand Visibility
- H1 order intake: Secured ~₹77 crores in new orders across EV infrastructure, renewable energy, and other segments, taking the order book to ₹173 crores as of September 30, 2026.
- Near-term pipeline: ~₹200 crores of orders under discussion, expected to close within FY27.
- Execution cadence: Transformers deliver within 6–8 weeks of order; all current orders expected delivered by end of March (H2 FY27), making the order book a reliable H2 revenue proxy.
- Deferred revenue booked: ~₹20 crores from a single customer that was deferred earlier was recognized in H1; management clarified the previously discussed figure of ₹31 crores was incorrect.
- Customer advances vary by segment: Government projects carry no advance; corporates (Adani, Reliance, Torrent Power) operate on confirmation LC or manufacturing LC without advance; distribution and one-time purchasers pay 20–30% advance with the balance before dispatch.
- Working capital: Currently 4–5 months, in line with industry, because large orders require immediate raw-material procurement (copper, oil) to hedge against price volatility; target is 3–4 months once raw material prices stabilize.
Margin Structure & Operating Leverage
- The leverage engine: Revenue nearly doubled YoY while major expenses (existing facility, manpower, top management) stayed largely fixed, reducing per-MVA overhead absorption and driving the 345 bps EBITDA margin expansion to 11.72%.
- Net profit followed: Net profit grew 237% YoY to ₹4.23 crores; net profit margin expanded 347 bps to 7.97%.
- Scale economies on larger orders: Material cost is universal across order sizes, but overheads (R&D, quality, marketing teams) do not rise proportionally as orders grow bigger; operational ground-cost impact is only 1–2%.
- Aspiration path: Management is targeting 12–13% margins; when asked if ~100 bps per year is the pace, the response was "Definitely, we are trying to make our commitment."
- EHV margin nuance: In distribution transformers, buyers compare material cost; in EHV, material cost is lower and engineering cost is higher, a mix shift that supports margin expansion once the plant is operational.
Management: "So, profit in the transformer industry from 3% to up to 20% is in-between play."
Customer Approvals & Market Access
- Vendor approvals won in H1: Aditya Birla Renewables, UGVCL, Sterling & Wilson, Megha Engineering, BluePine, KEC International, and SMC Construction, expanding the addressable tender universe.
- 17.6 MVA type test at CPRI: The highest rating in the renewable segment transformer category; report submitted to Adani (under review), ReNew Power, and JSW, expected to unlock the solar generation segment (10–20 MVA transformers) beyond the existing wind turbine transformer supply to Adani.
- UGVCL 5-year approval: Received for manufacturing and supplying 500 kVA distribution transformers; other ratings under process with prototype testing, approval expected within 15 days.
- GETCO shunt reactor: Dispatch clearance received for a prototype shunt reactor at a transmission substation; successful commissioning and performance expected to drive significant future order inflows.
- NHEV EV charging project: LOI/LOR received; 20 of 450 substation land acquisitions completed by the government; compact substations being bought by Megha Engineering and PMI from Accord.
- Export ambition flagged: Management stated "you will see in the coming days that we are going to deliver these products in our overseas market also," though no timeline or specifics were provided.
Operations & Capacity
- H1 production: ~300–400 MVA delivered against existing plant capacity of 1,500 MVA, with 400 MVA already delivered, leaving significant headroom before the EHV plant comes online.
- Delivery time stable: 6–8 weeks from order to delivery, unchanged from earlier periods.
- CEO hiring: An operational head/CEO is joining next month to oversee factory operations across the two existing facilities and the upcoming larger plant, a move timed to the H2 delivery focus and EHV ramp.
- Vendor ecosystem: Copper supplier (Ram Ratna) located 1 km from the factory; CRGO, radiator, and sheet metal vendors developed 3–4 km away; backward integration work ongoing to reduce transportation cost and timeline.
- Product claims: Management stated Accord was first to make 16-pulse and 24-pulse transformers in India, and that its GETCO shunt reactor is first-of-its-kind.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Order book delivery | All current orders (₹173 crores order book) delivered | By end of March |
| Orders under discussion | ~₹200 crores value expected to close | Within FY27 |
| EHV plant commercial production | 220 kV class plant operational | Minimum 6 months from now (i.e., ~May 2027) |
| EHV plant capex | ₹35–40 crores total; ~₹20 cr from internal accruals + IPO funds, rest via debt | During plant build phase |
| Power Grid EHV approval | Facility visit and upgradation approval | Within 30 days once plant is ready |
| Revenue growth rate | ~60–80% growth rate sustained | Next 2–3 years |
| Margin expansion | Aspiring to 12–13% margins; ~100 bps per year | Ongoing |
| EHV initial PAT | ~10% initially, improving after depreciation and interest absorption | Once EHV segment begins |
| Working capital target | 3–4 months | Once raw material prices stabilize |
Key Metrics
| Metric | H1 FY27 |
|---|---|
| Revenue from operations | ₹52.68 crores, +90.90% YoY |
| Total income | ₹52.53 crores vs ₹27.76 crores in H1 FY26 |
| EBITDA | ₹6.21 crores, +170% YoY |
| EBITDA margin | 11.72%, expanded 345 bps YoY from 8.28% |
| Net profit | ₹4.23 crores, +237% YoY |
| Net profit margin | 7.97%, expanded 347 bps YoY from 4.51% |
| EPS | ₹2.05 vs ₹0.87 in H1 FY26 |
| Orders received (H1) | ~₹77 crores across solar, wind, and other transformer segments |
| Order book (as of Sep 30, 2026) | ₹173 crores |
| Orders under discussion | ~₹200 crores, expected to close in FY27 |
| Production volume delivered (H1) | ~300–400 MVA (delivered; capacity is 1,500 MVA) |
| Existing installed capacity | 1,500 MVA per annum |
| New EHV plant capacity | 15,000 MVA per annum, 10x increase |
| New EHV plant capex | ₹35–40 crores, funded via internal accruals, IPO proceeds, and debt |
| Working capital cycle | 4–5 months, in line with industry standard; targeting 3–4 months |