Deccan Gold Mines Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/c2j9p0rqdaxug4ualf6eweiq.pdf

Key Takeaways


Transition to Producer

Dr. Hanuma P Modali: "As a snapshot, it has established us as clearly as producers. All the time we have been explorers and last so many years we have been exploring in this country, but in the March quarter we have shown some production and June quarter has clearly established us as the producer."

Jonnagiri: Sales Timing and Cash Flow

Dr. Hanuma P Modali: "Actually there is a significant improvement in the gold price. So I am really holding that gold in the stock. I think it will benefit us in this quarter when we sell the gold at the higher price."

Altyn Tor and Kyrgyzstan

Dr. Hanuma P Modali: "Previously the government could not actually get the permission for the leaching circuit there. So that shows our commitment, our capability to take the community along with us."

Finland and Ganajur: The Next Gold Projects

Dr. Hanuma P Modali: "I do not see any other project, which is more closer to the production than the Ganajur project in this country. So it makes all the sense for the government to actually give us helping hand so that we can start producing."

Critical Minerals: Drilling and Validation


Funding and Capital Structure

Dr. Hanuma P Modali: "We are not going to have any off-take arrangement because the gold pricing and the off-take arrangements sometimes work well, but sometimes may not work very well in the gold industry."

Guidance & Commitments

CommitmentSpecificsTimeline
Jonnagiri FY27 production500–600 kg; clarity on whether 600 kg achievableEnd of next quarter
Jonnagiri FY28 production750–800 kgFY28
Jonnagiri EBITDAStabilize at 65–70%Within another quarter or two
Jonnagiri expansionProcessing facility from 1,010 to 2,500 tons per day; ~2 tons per annum maximumAround FY29–FY30
Jonnagiri resource growthTarget 40 tons of gold for more than 25 years of mine life; independent sign-off to be announcedNo date
Altyn Tor FY27 production150–160 kg, starting September with ~180 days available through MarchFY27
Altyn Tor FY28 production300–350 kgFY28
Altyn Tor resource estimateRevised resource estimate within the mine; first phase revised mine design and life-of-mine planOctober 2026
Altyn Tor underground capex₹150–200 crore for decline development below the 170-meter open pit; funded from internal accrualsIn 3–4 years
Jonnagiri underground capexUpwards of ₹400 crore for 500–600 meter deep shafts; funded from internal accrualsIn 4–5 years
Finland drilling1,500 meters planned; results in next 3–6 monthsStarting September 15
Finland stake$1 million investment to take Deccan to 51%Coming quarter
Finland feasibility studyNeed at least 4 tons of resourceYear 2027
Logrosán resultsFull Dehesa results; preliminary resource modeling announced to marketMid-September; early October
Chhattisgarh mining leaseApply for mining lease; process flow sheet completedNext year; mid next year
Mozambique processing plant200 ton per day plant for concentrate productionEnd of 2027 or Q1 2028
New gold acquisitionsThree assets under due diligence; could come into productionEnd of 2027 or 2028
Ganajur productionAbout 1 ton of gold production if mining lease grantedIn 2–3 years
Clear FY27/FY28 production guidanceTo be givenEnd of next quarter

Key Metrics

MetricQ1 FY27
Revenue from gold sales (Jonnagiri)₹87 crores from sale of 59 kilos of gold
Profit after tax (Jonnagiri)₹25 crores, Deccan's share ₹6.35 crores booked into accounts
Geomysore Services profit contribution₹6.35 crores PAT booked into Deccan's accounts
Gold sold (Jonnagiri)59 kilos of bullion sold in Q1
Gold production (Jonnagiri)112 kilos of dore bar, yielding about 90 kilos of bullion
Production strike rate (Jonnagiri)1 kilo per day, at least 30 kilos per month
Gold in stock at quarter end (Jonnagiri)80 kilos equivalent, comprising 40 kilos of gold plus 60 kilos of dore bar
Jonnagiri FY27 production guidance500 to 600 kilos, management reaffirmed prior guidance
Jonnagiri FY28 production guidance750 to 800 kilos
Jonnagiri target EBITDA margin65% to 70%, expected to stabilize in another quarter or two
Altyn Tor (Kyrgyzstan) FY27 production guidance150 to 160 kilos, starting September with roughly 180 days available through March
Altyn Tor (Kyrgyzstan) FY28 production guidance300 to 350 kilos
Altyn Tor investment to dateMore than ₹300 crores
Altyn Tor tailings resource780 kilos of gold in 0.06 crore tons of old tailings at 1.3 grams per ton
Altyn Tor low-grade stockpileAbout 0.1 crore tons, supporting 4 to 5 years of production along with tailings
Board approved capital raise₹137 crores through CCDs, equity shares and equity warrants, subject to shareholder approval
Jonnagiri processing facility approvals1,010 tons per day, planned increase to 2,500 tons per day
Jonnagiri maximum anticipated productionUp to 2 tons of gold per annum, expected around FY29 or FY30
Jonnagiri target resource40 tons of gold, supporting more than 25 years of mine life
Jonnagiri employment createdAbout 1,000 on site plus a similar number outside the company
Finland (Kalevala) licensed area27.36 square kilometers, about 2,735 hectares
Finland Kuikka depositAbout 1 ton of gold at average grade more than 5 grams per ton; drilling target to increase to almost 4 tons
Finland Pahkalampi prospectAbout 2 tons of gold historical resources at about 3.5 grams per ton
Finland combined targetMore than 5 to 6 tons of gold, at least 4 tons needed for feasibility
Finland investment to reach 51%About $1 million, of a $1 to $2 million total, planned for the coming quarter
Chhattisgarh nickel-copper-platinum drilling2,500 meters completed, 15th drill hole ongoing; 1.3 km mineralized zone identified
Chhattisgarh processing plantAbout 3,000 tons per day tentatively planned, bigger than Jonnagiri plant
Logrosán tungsten project (Spain) drilling3,000 meters completed; every hole intersected tungsten or tungsten-tin mineralization
Logrosán highest drill results0.88% and 1.21% tungsten, the 1.21% intersected at 535 meters depth
Logrosán processing facility guesstimate1,000 tons processing facility, about 300,000 tons input per year
Mozambique lithium-cesium-tantalum licensesAbout 150 square kilometers covered by three broadly contiguous licenses
Mozambique drilling plan1,500 to 2,000 meters starting September onwards
Mozambique processing plant target200 tons per day to concentrate lithium and tantalum by end of 2027 or Q1 FY28
Critical mineral price increase, tungsten622% in last one year
Critical mineral price increase, tantalum196% in last one year
Critical mineral price increase, lithium108% in last one year
Altyn Tor underground mining capex estimate₹150 crores, up to a maximum of ₹200 crores, required in 3 to 4 years
Jonnagiri underground block capexUpwards of ₹400 crores, required in another 4 to 5 years
Total capital requirement across remaining projectsAbout ₹2,000 crores, more than ₹1,000 crores if at least two of four projects reach feasibility