Key Takeaways
- Two mines finally entering production: Jonnagiri trial runs completed successfully and Altyn Tor trial production has started, ending a multi-year wait for first gold.
- ₹315 Cr rights issue to clear a painful debt overhang: The raise would repay ~₹200 Cr of high-cost debt, making the company debt-free, with the balance funding drilling across four projects.
- Jonnagiri stake dilution is permanent: Deccan’s stake fell from 42% to 27% because it prioritized Kyrgyzstan; management sees no path to increase it and may monetize in two to three years.
- The project pipeline is real but timelines keep slipping: Mozambique lithium is delayed by a year, Finland’s trial mine pushed to 2026, and full-scale Altyn Tor production waits on a post-winter ramp-up.
- What to watch next quarter: Whether the rights issue terms are finalized, Altyn Tor’s trial production transitions to commercial output, and if Jonnagiri’s refinery delivers first bullion.
The Production Inflection
- Jonnagiri is now operational: Trial runs completed successfully; the processing plant is fully working at its approved 1,000 tons per day capacity with no glitches, and test work predictions are reconciling well.
- Refinery adds value capture: A refinery has been built alongside the plant, so Jonnagiri will produce refined gold bullion rather than Dore bar, a first for an Indian gold mine.
- Altyn Tor trial production has begun: Final preparations completed and trial production started; commissioning during winter may be slow, but post-February the plant will be full on.
- Production ramp-up is back-end loaded: Jonnagiri is projected at ~500 kg in FY2027, rising to 750 kg the following year and eventually peaking at ~1 ton annually with underground operations. Altyn Tor starts at 350 kg next year, potentially reaching 700 kg by 2028.
- Community license to operate is hard-won: 600-700 people employed at Jonnagiri in a backward area with no other opportunities; about 200 employed in Kyrgyzstan where two villages sustain on the project. Building this took five to six years.
Hanuma Prasad: "Till yesterday, I was there on the project. I think shareholders are very keen to know when it is going to start. We have completed the final preparations for the trial production. Within the next couple of weeks, you will come to know once the trial production starts."
The Rights Issue: Debt, Dilution, and Discontent
- Primary purpose is debt repayment: ~₹200 Cr of debt, secured by pledged Geomysore shares, has become very difficult to service. Even with Kyrgyzstan revenues next year, if all cash goes to debt, growth funding disappears.
- Balance funds four drilling programs: Remaining proceeds target exploration at Altyn Tor, Finland, Mozambique, and Bhalukona to build resources and increase company value.
- Debt-free target is near-term: If the rights issue proceeds, the company will pay all debts and become debt-free by end of this year.
- Management pushes back on timing criticism: An analyst called the timing "100,000% wrong," arguing it should have been done after production announcements. Management counters that existing shareholders benefit from growth and the company needs to clear debt now.
- Backdoor entry denied explicitly: Management stated there is no intent to bring in a big investor at a discount; if that were the goal, they would have done a larger ₹600-700 Cr issue. Even if 99% of rights are renounced, an incoming investor gets only 15% maximum.
Imran Ghani: "the timing of the right issue is 100% wrong. It is 100,000% wrong."
Jonnagiri: A Shrinking Stake in a Growing Asset
- Stake fell from 42% to 27% by choice: Deccan prioritized investing ₹140-150 Cr in Kyrgyzstan over Jonnagiri, where it put only ~₹40 Cr. Management believes having two operating mines, even as a minority in one, is better than being a minority shareholder in a single operating mine.
- Deccan does not manage Jonnagiri: Geomysore manages the project; Deccan only gets information from Geomysore board meetings. The Managing Director was personally involved as MD of Geomysore until August, but the Deccan team is not involved in the project's growth.
- No path to increase stake: Going forward, Jonnagiri may not require any money, so further stake increase seems doubtful. Management believes growth of other projects will bring more value than remaining a secondary shareholder.
- Monetization possible in two to three years: Management is not thinking of monetizing the 27% stake now, but may consider it when the resource is known to be increasing. There is also a chance Geomysore could get listed.
- Resource growth trajectory is significant: Jonnagiri sits at 12 tons as a first step, around 20 tons of resource currently, and in another couple of years could reach 42 tons.
Management: "I personally believe from the management perspective, we are in a better position with two operating mines rather than a minority shareholder in one operating mine. But that is how we see it."
Exploration Pipeline: Promise and Slippage
- Mozambique copper-gold is a fresh, fast-moving target: Strong evidence of copper-gold mineralization found in Tete province in the last 15 days to one month; multiple zones identified with ready-made drill targets. Deccan holds 90% and will drill immediately.
- Mozambique lithium is delayed by a year: The plan to commission a 110 ton per day processing plant this year was pushed out due to test work and further drilling requirements. A revised 100 TBD plant is targeted for next year.
- Finland needs one year of drilling to unlock value: A small open pit is planned next summer subject to environmental clearance and fund availability, targeting ~276 kg per annum by FY2029. The next year aims to prove ~4 tons of gold resource.
- Bhalukona drilling starts January: First-phase drilling on the nickel-copper-PGE license begins then; management needs 6-8 months before taking a development call. The intent is to move it into a 100% subsidiary for easier fundraising, but this has not been done yet.
- Tanzania not written off: First-stage exploration received; surface values look mixed. No drilling done yet; planning to drill as part of the overall program in January or February.
- Acquisition appetite remains: The company is looking at one or two projects to acquire, subject to due diligence, in both gold and critical minerals. Criteria: gold projects that can reach production within two years; critical minerals greenfields with good geological potential.
Critical Minerals and the Long Game
- 2021 pivot to critical minerals is paying off: The company has spread across lithium, nickel, tungsten, rare elements, copper-gold, and platinum groups, building a diversified resource base beyond gold.
- 2030 ambition is a mid-tier producer: Deccan wants to become a mid-tier gold producer and begin supplying critical minerals by 2030, with Jonnagiri reaching ~1 ton and Altyn Tor exceeding 800 kg, potentially a ton depending on underground grades.
- Majority ownership is now non-negotiable: The company will only enter projects with majority ownership or a clear path to it within two to three years, a lesson drawn from the Jonnagiri experience.
- Gold price tailwind is material: Management cites predictions of $4,500 to $5,000 per ounce in the next one to two years, positioning the company's production ramp-up as well-timed.
- Ganeshwar & Hathid hinge on policy reversal: These projects are linked to the 10A(2)(b) policy which the government removed; management is working with state authorities and the Mines Minister to bring it back, arguing the company is now in a stronger position as a producing group.
Shareholder Relations and Governance
- Long-term shareholders are restless: One analyst stated shareholders who have stuck with the company for 15 years "are being sidelined," reflecting frustration with delays, dilution, and communication gaps.
- Management acknowledges the wait: The MD thanked shareholders who have been invested since 2005 or 2011-2012, saying "you believed our story and now it is coming to reality."
- IR practices are being upgraded: Regular quarterly calls are now scheduled through BSE for the next year; a clear policy for handling shareholder responses will be communicated within days; physical AGMs are promised from next year onwards.
- Minority shareholder director process underway: A list of shareholders is being sent and the process is being followed; management is cooperating with shareholders who sought this.
- Several direct questions went unanswered: Management did not answer questions on why the 5-ton gold equivalent target was reduced to 2 tons, whether to subscribe to the rights issue given no earnings, legal strategy on Ganajur and Hatti, and the PAT impact from Jonnagiri’s production.
Hanuma Prasad: "Many of you have been the shareholder since like 2005 and some of them came in around 2011-2012. It is a long time and you believed our story and now it is coming to reality. We are getting into the production now. So, all from my heart, I thank you and we will do our best to deliver the value to you."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Debt-free status | Repay all debts (~₹200 Cr) using rights issue proceeds | By end of this year (whenever rights issue closes) |
| Altyn Tor trial production | Trial production to start | Within next couple of weeks from call date |
| Altyn Tor full-scale production | Plant to be "full on" | Post-February |
| Altyn Tor FY2027 production | ~350 kg | FY2027 |
| Altyn Tor FY2028 production | Potentially up to 700 kg | FY2028 |
| Jonnagiri FY2027 production | ~500 kg | FY2027 |
| Jonnagiri production increase | 750 kg | From FY2028 onwards |
| Jonnagiri peak production | ~1 ton per year (with underground) | By 2030 |
| Finland open pit production | ~276 kg per annum | FY2029, subject to environmental clearance and funds |
| Finland resource drilling | Prove ~4 tons of gold resource | Next one year |
| Mozambique copper-gold drilling | Start drilling operations | Beginning of next year |
| Mozambique lithium plant | 100 TBD processing plant | Next year |
| Bhalukona drilling | First phase drilling | From January |
| Tanzania drilling | Drill as part of overall program | January or February |
| Kalevala stake increase | Exercise rights to go up to 75% | No date; intent stated |
| Physical AGM | 100% physical AGMs | From next year onwards |
| FY2027 financial projections | Provide topline and net profit table | In a day or two from call date |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Market capitalisation | ~₹2,000 cr |
| Total debt | ~₹200 cr |
| Rights issue size planned | ₹315 cr, primarily for debt repayment and exploration drilling |
| Revenue sharing with Kyrgyzstan govt | 17% of revenue; India is 5.28% |
| Altyn Tor (Kyrgyzstan) proven resource | 5.6 tons of gold, expected to increase to more than 8 tons |
| Altyn Tor all-in sustaining cost | $1,045 per ounce |
| Altyn Tor FY2027 annual production target | 350 kilos, peak potential ~800 kilos after 3–4 years with underground ops |
| Altyn Tor trial production estimate (winter) | 20–25 kilos of gold |
| Jonnagiri (India) proven resource | ~12 tons of gold, potential to go beyond 20 tons |
| Jonnagiri FY2027 projected production | ~500 kilos, increasing to 750 kilos next year, peak ~1 ton per year |
| Jonnagiri initial production forecast | ~400 kilos per year, eventually 800 kilos plus to a ton |
| Jonnagiri plant approved capacity | ~1,000 tons per day |
| Jonnagiri EBITDA margin | ~75% |
| Kalevala (Finland) resource | ~4 tons of gold; grades up to 30 g/t, average 5–6 g/t |
| Kalevala targeted annual production | ~276 kilos, expected in FY2029 |
| Deccan stake in Geomysore (Jonnagiri) | 27%, down from 42% originally; maximum cap 49% |
| Deccan stake in Avelum Partners (Altyn Tor) | 60% |
| Deccan stake in Kalevala (Finland) | 32%, with rights to go up to 75% |
| Deccan ownership in Mozambique Tete tenements | 95% |
| Mozambique lithium plant capacity planned | 100 tons per day processing facility; potential to scale to 1,000 tpd with 0.3 cr tons ore |
| Deccan share of gold production target | ~2 tons (gold only); ~5 tons including gold equivalents from other commodities |
| Gold price assumption (current) | Close to $4,000 per ounce; forecasts of $4,500–$5,000 in 1–2 years |
| Jonnagiri feasibility study gold price | ₹2,800 per gram |
| Kyrgyzstan feasibility study gold price | $1,200–$1,300 per ounce |
| Hira Group total exposure (equity + debt) | ~₹400 cr |
| Loan to Kyrgyzstan entity | ~₹140–150 cr at 15% interest |
| Investment in Jonnagiri project | ~₹40 cr |
| Investment in Kyrgyzstan project | ~₹140–150 cr |
| People employed at Jonnagiri | 600–700 |
| People employed at Kyrgyzstan mine site | ~200 |
| Ganajur discovered gold | 9 tons in 2017 |