Key Takeaways
- Topline momentum, margin squeeze: Revenue grew over 20% YoY and the company took a ~5% price hike, but EBITDA margin contracted ~300 bps as fuel costs surged after the forced switch to pet coke.
- The expansion bet is now funded: The INR 125 Cr fund raise (INR 80 Cr debt, INR 45 Cr equity) is finalized, clearing the path to triple cement capacity to 0.1 crore tons by March-April 2024.
- Solar is the margin bridge: Nine-month solar EBITDA nearly doubled to INR 25 Cr, and management insists this contribution will remain visible even as 90% of power shifts to captive use, because cement EBITDA is calculated at market power prices.
- Efficiency fix is the near-term catalyst: A dynamic separator retrofit, due by March-April 2023, targets a 4-5% production cost reduction, offering a small but concrete margin lift before the big expansion arrives.
- What to watch next quarter: Whether the fund raise actually closes in the promised couple of weeks, the pace of the separator commissioning, and any stabilization in pet coke costs that could ease the margin pressure.
The Expansion Plan: From 0.03 to 0.1 Crore Tons
- Rationale: Management is investing to bring the plant’s technology to par with major players, replacing old, inefficient equipment that drives power consumption ~80% above industry standards and keeps EBITDA per ton at INR 245-250 vs an industry INR 1,000-1,400.
- Scope: The expansion adds balanced equipment focused on reducing power and fuel consumption and increasing bunker production, all within the existing factory premises with no additional land required.
- Timeline: Full work starts by end of March 2023; target completion is March-April 2024, with one or two months for teething issues, so full capacity is expected to show in FY25.
- Post-expansion economics: At 60% utilization in the first year, revenue expectation is INR 350-400 Cr with better EBITDA margins because the project is based on fuel and power efficiency. The EBITDA per ton target is INR 1,000, assuming power cost at the sell price of ~INR 7/unit; if power cost is excluded, EBITDA per ton reaches almost INR 2,000.
- Market strategy shift: Post-expansion, the company will target institutional buyers and government contracts, segments currently unserviceable due to limited EBITDA and capacity. It will continue to hold ~80% of sales in the local area, with ~20% potentially going to larger markets like Pune and Bangalore.
- Competitive moat preserved: Management estimates major plants would incur INR 1,800-2,000 per ton in freight to supply its market area, vs the INR 600-800 its customers pay, a delta the company captures.
Venkatesh Katwa: "All that we're doing is investing in the same technology and coming at par with most of the major plans."
Solar: The Hidden Margin Engine
- Revenue doubling: Nine-month solar revenue nearly doubled to ~INR 15 Cr from INR 7.86 Cr, driven by the 12 MW capacity commissioned in December 2021, a ~50% addition.
- EBITDA contribution: Nine-month solar EBITDA was ~INR 25 Cr; full-year FY23 is expected at INR 32-35 Cr.
- Post-expansion accounting: As cement capacity triples, 90% of solar power will be consumed internally and only 10% sold outside. Management insists the INR 30-35 Cr solar EBITDA will continue to show because cement EBITDA is calculated assuming power cost at the external sell price, so captive consumption is valued at market rates.
- Overcapacity buffer: The company remains over capacity in solar even for the 0.1 crore ton cement target, meaning no incremental solar capex is needed to support the expansion.
Venkatesh Katwa: "Solar EBITDA of INR 30 crores to INR 35 crores will continue even if you're utilizing 90% power inside. The cement EBITDA I'm calculating assuming the power cost of my sell price."
Fuel Cost & Margin Pressure
- The pet coke pivot: The company completed plant modifications about two quarters back to enable 100% pet coke use, and switched entirely this quarter because buying coal at current prices was not feasible.
- The cost sting: Last quarter’s average coal price was INR 8,000/ton; this quarter’s average pet coke price was INR 16,000/ton. Even though pet coke is 20-30% cheaper on a per-kilo-calorie basis, the absolute cost still rose compared to Q3 FY22, driving the EBITDA margin contraction from 32.9% to 29.88%.
- Logistics insulation: Almost 80% of cement is sold on an ex-plant basis, so logistics cost fluctuations are passed on to customers, limiting one source of margin volatility.
- The efficiency handicap: Cement EBITDA per ton languishes at INR 245-250 because the plant is very old: actual consumption is 30-40% higher than industry standards, and power consumption is almost 80% higher. The dynamic separator retrofit and the larger expansion both target this gap.
Venkatesh Katwa: "That is because I'm driving old, very old ambassadors with a very, very bad average, which is what we are trying to fix in this model machine now."
Fund Raise & Balance Sheet
- Structure finalized: The entire fund raise was concluded just last week. Canara Bank, the sole banker, agreed to fund INR 80 Cr via debt; INR 45 Cr will come via a preferential equity issue. Soft commitments are in place and closure is expected in the next couple of weeks.
- Debt terms: An 8-year repayment schedule was negotiated, down from the initially asked 10 years; the bank had wanted only 5 years based on a high DSCR. The interest rate on existing debt is planned to be reduced from 9.55% to 9.1%.
- Promoter equity conversion: All promoters’ unsecured debt on the books is being converted into equity as part of the fresh equity raise.
- Finance cost drag: Q3 PAT declined from ~INR 1.6 Cr to INR 1.4 Cr YoY mainly because of increased finance cost, as overdraft limit utilization rose from under 50% in Q2 to 80% in Q3. Internal accruals parked in overdraft limits had to be used for internal work on equipment.
- Post-expansion deleveraging: Repayment capacity is expected to increase by nearly three times post-expansion. Management will look at using surplus cash flows to close loans from FY25 onwards, unless pursuing another expansion or additional capacity.
Venkatesh Katwa: “History of not a single day default, not a single rupee delayed since inception till date and our bankers know about it.”
Demand & Pricing
- Volume growth: Q3 production and sales volume increased to 65,400 tons from 51,550 tons YoY; nine-month volume grew ~10% from 158,000 to 172,000 tons.
- Price realization: The company took a price hike of around 4.6% QoQ, or ~INR 170 per ton on books compared to Q2, enabled by robust demand.
- Macro tailwind: Management cites increasing spend on housing and infrastructure, and the 33% increase in capital investment outlay to INR 10 lakh crores in the 2023 budget, as positive for building materials.
- Capacity utilization: Q3 utilization was ~73%, improving from FY22’s ~63%. The drop from FY18’s 88% is solely because rated capacity expanded nearly three times; there is no drop in quantity or sales.
Near-Term Catalysts & Optionality
- Dynamic separator retrofit: Work has begun using internal resources; expected to commission by March-April 2023, reducing cost of production by around 4-5%.
- RMC opportunity: Management sees ready-mix concrete as a great new opportunity and will definitely look into it once the expansion takes shape, but current focus is only on the capacity expansion.
- Railway adjacency: A railway line passing adjacent to the boundary will be laid down in the next couple of years, which could serve as freight infrastructure for the cement plant; management expects this to increase the plant’s valuation when it materializes.
- Land bank: Existing land can accommodate another two million tons in capacity beyond the current expansion.
- M&A openness: Management stated that at a very good price, it would consider selling the cement division if it adds to shareholder wealth, but the current focus is entirely on expanding capacity.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Fund raise closure | INR 80 Cr debt + INR 45 Cr equity; soft commitments in place | Next couple of weeks |
| Dynamic separator commissioning | Reduce production cost by 4-5% | March-April 2023 |
| Full expansion work start | Capacity increase from 0.03 to 0.1 crore tons | End of March 2023 |
| Expansion completion | Full capacity operational after teething issues | March-April 2024; full showing in FY25 |
| Post-expansion revenue | INR 350-400 Cr at 60% utilization in first year | FY25 |
| Post-expansion EBITDA per ton | INR 1,000/ton (cement), assuming power at INR 7/unit | Post-expansion |
| Solar EBITDA | INR 32-35 Cr full-year FY23 | FY23 |
| Interest rate reduction | Existing debt rate from 9.55% to 9.1% | Not specified |
| Debt repayment capacity | Increase by nearly 3x post-expansion | Post-expansion |
| Surplus cash deployment | Debt reduction first, unless productive asset investment | FY25 onwards |
Key Metrics
| Metric | Q3 FY23 |
|---|---|
| Revenue | 34.81%, +20% YoY |
| EBITDA | 10.44%, up 9.36% |
| EBITDA margin | 29.88%, down from 32.9% in Q3 FY22 |
| PAT | ₹1.39 cr, down from ~₹1.6 cr in Q3 FY22 |
| EPS | ₹1.16 |
| 9M FY23 revenue | ~₹93 cr, +17.2% YoY |
| 9M FY23 PAT | ₹29 cr, +315% YoY |
| 9M FY23 EPS | ~₹24.18 |
| Cement sales volume | ~65,400 tons, vs 51,550 tons in Q3 FY22 |
| Cement EBITDA per ton | ~₹245, vs industry ₹1,000–₹1,400 |
| Capacity utilization | 73%, vs 63% in FY22 |
| Price hike (QoQ) | ~4.6%, ~₹170 per ton vs Q2 |
| Solar revenue (9M FY23) | ~₹15 cr, nearly doubled from ₹7.86 cr in 9M FY22 |
| Solar EBITDA (9M FY23) | ~₹25 cr; full-year FY23 expected ₹32–35 cr |
| Total debt (post-expansion) | ~₹230 cr, up from ~₹154 cr currently |