Key Takeaways
- Capacity doubled, now the ramp-up must deliver: The new 0.1 crore ton kiln was commissioned in Q4 and reached 77% utilization, with rated capacity expected by end of Q1 FY26. The entire investment case now hinges on filling this capacity profitably.
- Price, not volume, destroyed FY25 profits: Dispatches rose 10-11% but the company lost ₹16-17 crores of EBITDA solely because cement realizations fell ~11.5% and solar realizations fell ~12%.
- FY26 EBITDA target of ₹70+ crores is a bet on price stability: Management projects a 50-50 split between cement and solar, but the target holds only if the price recovery seen since March sustains and improves.
- Government projects are the new growth lever: The larger plant now qualifies the company for state government tenders it was previously too small to bid for, and a breakthrough is expected to book by end of Q1 or early Q2.
- What to watch next quarter: Whether the kiln hits rated capacity on schedule, whether the government project breakthrough materializes on the books, and whether the Q1 price recovery holds through the monsoon.
The FY25 Damage: Price Overwhelmed Volume
- Stable top line, squeezed bottom line: Total income held at ₹124.6 crores and EBITDA at ₹25.17 crores (20.73% margin), but this stability masks a brutal price environment that erased the benefit of higher dispatches.
- Realization collapse: Cement prices dropped nearly 11.5% in Q4 and renewable power prices fell about 12%, producing a net realization decline of roughly ₹425 per ton for the full year.
- Volume gains were real but insufficient: Capacity utilization jumped from 79.5% in Q4 FY24 to 92% in Q4 FY25, and dispatches increased 10-11%, yet the company still lost an estimated ₹16-17 crores of EBITDA purely from price decline.
- PAT turned negative on a non-cash item: The bottom-line loss was squarely attributable to a deferred tax liability, not operating weakness; the company generated healthy cash profits despite heavy capex and depreciation.
- Debtor days stretched on weak demand: The increase in debtor days last year reflected poor market demand rather than any deliberate loosening of credit terms, and management expects improvement as cement consumption picks up.
Venkatesh Katwa: "We lost around Rs. 16 crore to Rs. 17 crores EBITDA only because of the decrease in the price."
The New Kiln: Ramp-Up Progress and Economics
- Commissioning and current state: The 0.1 crore ton kiln was commissioned at end-March, started at 30-40% of rated capacity, and had reached 77% as of the call date. Management expects to hit rated capacity by end of Q1 FY26, with full operational stabilization possibly taking another month or two.
- FY26 utilization target: The company aims for 50% capacity utilization on an overall basis in FY26, even with a slow ramp-up trajectory. Q1 utilization is already much better than the prior year.
- Payback timeline: Typical payback on the kiln modernization is seven to eight years.
- Cement becomes the mainstay: With the larger plant and higher captive power consumption, management expects 95-96% of sales to eventually come from cement, with the balance from solar. That mix shift begins this year.
- Future expansion deferred: Any further capacity increase beyond the current 0.1 crore tons is at least two years away; management called it too early to discuss projections and said the focus is entirely on stabilizing the new plant and sales.
The FY26 Earnings Bridge: How ₹70 Crores of EBITDA Gets Built
- The target: Management projects EBITDA of around ₹70 crores for FY26, translating to PBT of roughly ₹30-35 crores, and expects to achieve positive PAT definitively.
- The split: The ₹70+ crores is expected to divide roughly 50-50 between solar (₹30-35 crores) and cement (the remainder).
- The price assumption: The entire target is conditional on cement prices continuing at the levels seen from May onward. Q1 FY26 realizations are already better because prices have generally increased in the south, and early monsoon disruption to dispatches is expected to be short-lived.
- The volume assumption: April and May dispatches were in line with targets, and management sees a general uptick in cement consumption supported by government spending on rural housing, highways, and infrastructure.
- Fuel cost tailwind potential: Petcoke prices were stable throughout FY25 and are expected to remain so, but management is hoping for some reduction as alternative fuels emerge globally.
- Tax shield: The MAT rate will run around 15-16% for the next couple of years due to carry-forward depreciation losses, protecting cash flows.
- Debt repayment priority: The first call on excess cash as profits materialize will be debt reduction. New debt from the capex cycle is now on the books, and its benefits are expected to accrue this year.
Venkatesh Katwa: "As we speak, we are almost reached 77% of its rated capacity, expect to reach the rated capacity by the end of this quarter. So, with that, I am still hopeful that this year, hoping that the price continue to remain as it is, we should be able to comfortably achieve the EBITDA figures."
Solar: From Merchant Sales to Captive Engine
- Capacity and captive shift: Total renewable capacity now stands at 40 MW after a 3 MW addition. Captive consumption was 40-45% last year; with the new cement capacity, management targets 60-65% captive utilization this year, rising to 95% once the cement plant reaches 80-85% utilization.
- Merchant sales will shrink: As captive consumption rises, the portion of power sold to third parties will reduce sharply. The existing 12-13 solar customers will see supply diminish, and management acknowledged this without offering a specific retention plan, noting that solar sales will be extremely reduced until another solar plant is added.
- 30 MW expansion under evaluation: A 30 MW solar addition is on the cards this financial year but not yet finalized. If it proceeds, the timeline from approach to commissioning is roughly 9-12 months, and funding would come entirely from banks. Management expects to have clarity on the project's shape by the end of next quarter.
- Long-term ambition: The company plans to grow renewable capacity beyond 100 MW over the next three to five years.
- Solar realizations: Management expects to reasonably get around ₹6 per unit for solar power this financial year. Solar payback periods run six to seven years based on current regulatory costs and pricing.
- Waste heat recovery deferred: Not considered urgent because renewable power costs less than ₹1.70-1.80 per unit; the possibility exists for the future but has no timeline.
Market Position: Closing the Pricing Gap
- The discount to larger brands: The company's cement trades at a discount of ₹600-700 per ton versus Tier-2 brands and roughly ₹1,000 per ton versus Tier-1 brands, despite what management says is comparable quality.
- The closing mechanism: Management believes this gap will narrow as higher capacity lets the company reach bigger institutional buyers and government projects, which value quality and consistency over brand perception.
- Government qualification as catalyst: The 0.1 crore ton plant now meets the size threshold for state government tenders that were previously inaccessible. The company is actively pursuing state-level projects and has already achieved some breakthrough, which may appear on the books by end of Q1 or early Q2 FY26.
- Dealer network intact: The company retained nearly 100% of its dealers, losing only a few extremely price-sensitive ones. With the expansion, it is building out a bigger network and has significantly increased its sales and marketing headcount across all regions.
- Digital loyalty program launched: A new incentive point system now reaches end customers (engineers, masons) directly, not just dealers and retailers. Management says these activities are already contributing to the sales increase seen this quarter.
- Geographic expansion on the horizon: Once the plant stabilizes and production increases, the company will look at new areas bordering its existing territory, extending its radius by another 50-100 kilometers and potentially reaching Pune and Bangalore.
Venkatesh Katwa: "I believe right now, the pricing difference is almost like Rs. 600 per ton, Rs. 600 to Rs. 700 per ton between ours and Tier-2 brands. And maybe almost around Rs. 1,000 from Tier-1 to our brand. But that gap will start reducing as we go with higher capacity and start reaching out to bigger institutional buyers because we are able to produce the same quality and everything."
Capital Structure & Credit Profile
- Rating upgrade: Long-term bank facilities were upgraded from IVR BB positive to IVR BBB minus with stable outlook; short-term facilities received an IVR A3 rating.
- Debt and repayment: New capex-related debt is now on the books. Management stated that debt reduction is the first priority as profits begin, with excess cash directed to repayment.
- Equity dilution question left open: When asked about equity dilution versus debt for future projects, management gave a general answer about improving shareholder wealth but made no specific commitment to any funding strategy.
- RMC diversification under study: The company is considering ready-mix concrete as a next step, which would consume cement internally and reach end customers directly, increasing the top line. Consultants are working on the next course of action, but no conclusion has been reached.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Kiln rated capacity | Reach 100% of rated capacity | End of Q1 FY26 |
| Kiln full operational stabilization | Optimum performance level achieved | Mid-Q2 FY26 (one to two months beyond rated capacity) |
| Overall capacity utilization | 50% utilization on expanded base | FY26 |
| EBITDA target | ~₹70 crores, implying PBT of ₹30-35 crores | FY26, conditional on price stability |
| Positive PAT | Achieve positive profit after tax definitively | FY26 |
| Captive power consumption | 60-65% of renewable power used captively | FY26 |
| Government project revenue | Breakthrough showing on books | End of Q1 or beginning of Q2 FY26 |
| 30 MW solar project decision | Clarity on project shape and go/no-go | By end of Q2 FY26 |
| 30 MW solar project completion | Commissioning, if project proceeds | 9-12 months from start |
| MAT tax rate | 15-16% | Next couple of years |
| Cement-solar sales mix | 95-96% of sales from cement | When cement plant reaches 80-85% utilization |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Total income (FY25) | ₹124.6 cr, stable YoY |
| EBITDA (FY25) | ₹25.17 cr, margin of 20.73% |
| EBITDA guidance (FY26) | ₹70 cr plus, with roughly 50-50 split between solar and cement |
| PBT foresight (FY26) | ₹30 to 35 cr, based on current pricing and EBITDA of around ₹70 cr |
| PAT outlook (FY26) | Positive PAT expected, after negative PAT in FY25 due to deferred tax liability |
| Cement capacity utilization | 92% in Q4 FY25, up from 79.5% in Q4 FY24 |
| Cement price change (Q4) | Reduced by almost 11.5% YoY |
| Renewable power price change (Q4) | Reduced by about 12% YoY |
| Naked cement realization (FY25) | ₹3,350, similar in Q4; decreased by around ₹425 vs FY24 |
| New kiln capacity ramp-up | 77% of rated capacity reached as of call date, expect rated capacity by end of Q1 FY26 or mid Q2 FY26 |
| Capacity utilization target (FY26) | 50% on overall basis for the expanded plant |
| Breakeven capacity utilization | 37% to 40% for the newly expanded cement plant |
| Captive renewable power consumption | 40%-45% in FY25, expected to reach 60%-65% in FY26 within existing 40 MW |
| Renewable power production cost | Less than ₹1.70 or ₹1.80 per unit |
| Average solar power realization (FY25) | Around ₹5.90 |
| Solar power realization (early FY26) | Around ₹6 |
| Cement dispatches (FY25) | 2,57,000 tons, up around 10%-11% from 2,46,000 tons in FY24 |
| EBITDA impact from price decline (FY25) | Lost around ₹16 to 17 cr EBITDA due to cement price decrease |
| Debt repaid (FY25) | Around ₹26 cr |
| Long-term borrowings | ₹169 cr, up from ₹165 cr, an increase of just ₹4 cr |
| Debt-to-equity ratio | Less than 2 |
| Interest cost (FY26) | Around ₹25 cr with new loan addition |
| Depreciation (FY26) | Around ₹18 to 20 cr |
| MAT tax rate | 15% to 16% for next couple of years |
| Debtor days | Around 16 days |
| Pricing gap vs Tier-2 brands | ₹600 to ₹700 per ton lower |
| Pricing gap vs Tier-1 brands | Around ₹1,000 per ton lower |
| Solar plant project cost (30 MW) | Around ₹130 to 135 cr |
| Distribution network | Over 350 cement distributors and 600 retail touchpoints |
| Solar power consumers | Over 14 |
| Credit rating (long-term) | IVR BBB minus with stable outlook, upgraded from IVR BB positive |
| Credit rating (short-term) | IVR A3 |