Key Takeaways
- 43% YoY growth despite headwinds: Revenue growth was moderated by prolonged monsoon and GST 2.0 rollout disruptions, yet the company still delivered strong expansion.
- Module manufacturing is the next leg: A 1 GW TOPCon plant is commissioning by mid-January, targeting 75% utilization within Q1 FY27 and a standalone revenue potential of INR1,000 crores+ at 85% utilization.
- Defense receivables created a one-off cash crunch: Finance costs doubled as trade receivables from BSF and MES projects were delayed by Operation Sindoor (India-Pakistan war) from May to August; INR20-25 crores recovered since October, with full clearance expected by December.
- Margins got a structural lift from the Saarthi franchisee initiative, but the full benefit will only be visible as the program scales and commission outgo stabilizes.
- What to watch next quarter: Whether the module plant commissions on time in January, the pace of defense receivable clearance, and the initial captive consumption rate for modules in Q4.
Module Manufacturing: The Big Bet
- Plant timeline: Machines shipping from China this week, arriving in India by mid-December, with 15-20 days for trial runs. Full operations expected by mid-January to end of January.
- Technology choice: TOPCon line installed now, upgradeable to HJT in 3-4 years. Capable of using both DCR and non-DCR cells, with initial production focused on non-DCR given the existing pipeline of pre-August 31st bids.
- Ramp-up plan: 40-50% utilization in the first couple of months, targeting 75-80% over the next couple of quarters, with an internal target of 75% within Q1 FY27.
- Revenue and margin math: At 85% utilization, the standalone unit can generate INR1,000 crores+ in revenue with a 12-13% standalone EBITDA margin. Captive consumption is expected to improve gross margins by 5-7% on those modules.
- Captive consumption target: Management is confident of consuming 40-50% of output in-house within the first 6-9 months, with the balance sold B2B, where revenue is expected to appear in Q4.
- Sales team pre-deployed: Sandeep Banodiya (ex-Krannich Global) and other industry veterans were hired months before the plant goes live to build a B2B order book and enable cross-sell.
- Cost advantage not yet quantified: Management has not estimated the per-watt cost advantage from backward integration, but emphasized that supply assurance is the bigger prize in a market where module availability remains tight despite 100-130 GW of nominal capacity.
Ankit Garg: "we have not estimated the cost advantage till now. But the supply advantage will be very big for us."
The Defense Receivables Shock
- The trigger: Receivables from BSF and MES defense-linked projects were frozen for roughly four months because personnel were unreachable during Operation Sindoor, the India-Pakistan military engagement from approximately May to August.
- The financial impact: Finance costs doubled as working capital requirements swelled, and trade receivables stretched. This was a one-off specific to defense projects; no delays were experienced from other government entities like NTPC or Vyapar.
- Recovery underway: INR20-25 crores were collected between August and September, with another tranche received in October. Management expects to clear the remaining defense-linked receivables by December.
- Q3 will still carry the bloat: Finance costs will remain elevated in Q3 specifically because of the lag in normalization, before settling within the quarter.
- Residential business insulated: The residential segment carries negligible credit risk: customers pay a token advance of INR10,000-20,000, then nearly 100% before dispatch, and subsidy disbursement is gated behind Solarium's approval on the government portal.
Himanshu Garg: "both the agencies were stuck from somewhere about May to almost like August because of Operation Sindoor. We experienced the India-Pakistan war there. So most of the people were not reachable during that time."
EPC & Execution: The Core Engine
- Growth trajectory intact: The EPC segment grew 4x over two years (FY23-FY25), doubling every year, and management is targeting a continuation of that pace, citing visible traction in the order pipeline.
- Unexecuted order book: The majority of the backlog comes from NTPC, HPPL and other non-defense entities. Management aims to execute most of it within this fiscal year, with any spillover completed no later than Q1 next year.
- L1 execution cycle: From the date LOAs are received, projects typically take 9-12 months to execute.
- Government contribution split: Orders remain intact and the priority is rapid execution. The defense segment is a minority contributor relative to other government and utility-scale clients.
- Structure manufacturing commissioned: A 1,200 MTPA structure manufacturing facility went live in July 2025, adding another layer of backward integration ahead of the module plant.
Residential & Channel Expansion
- Geographic expansion: The residential footprint was extended to an additional 25 cities during the quarter.
- Solarium Saarthi initiative: Approximately 450 new franchisee channel partners were onboarded, driving margin expansion. As the initiative scales, commission outgo will stabilize and the margin benefit will sustain.
- B2C app under development: An application for residential customers will offer real-time order tracking and payment updates, aimed at improving retention and conversion rates rather than generating new revenue directly.
- End-to-end control: Solarium manages the entire residential journey from initial consultation through to final subsidy disbursement, a moat that local electrician competitors cannot replicate.
- Competitive reality: Larger players like Adani, Waaree and Tata supply products or kits but do not execute rooftop installations. Very few organized players operate in the execution layer where Solarium competes.
Himanshu Garg: "But in actual, nobody is doing the rooftop, including Tata. So, they are only supplying the products. Nobody is there in terms of executing. There are very, very few organized players who are there doing the execution part."
Distribution & Working Capital Dynamics
- Distribution is a negative working capital business: The pure trading segment, which accounts for roughly 70% of sales, imports modules from companies like Trina and operates on a negative working capital cycle.
- IPO proceeds deliberately not used for working capital: Management chose to use credit lines instead, building a credit history with lenders at no additional cost to the company. IPO funds are expected to be deployed into working capital once the module plant becomes operational in Q4.
- Module pricing volatility is familiar territory: Management noted that the solar industry has weathered such cycles before. Despite talk of 100-130 GW of domestic capacity, actual utilization runs at 70-75% while demand continues to grow aggressively, keeping supply timelines challenging.
- Chinese supplier relationships: The company is leveraging relationships from its earlier manufacturing facility. Once the new plant goes live, these will convert into long-term supply agreements for cells.
Himanshu Garg: "This is not the first time the module industry is seeing such sort of volatility."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Module plant commissioning | Machines arrive mid-December; trial runs 15-20 days; fully operational | Mid-January to end of January |
| Module plant utilization | 40-50% initial, ramping to 75-80% | 75% within Q1 FY27 |
| Module plant standalone EBITDA margin | 12% to 13% | At steady-state utilization |
| Module plant revenue potential | INR1,000 crores+ | At 85% utilization |
| Captive module consumption | 40-50% of output consumed in-house | First 6-9 months post-commissioning |
| B2B module sales revenue | Revenue to appear in financials | Q4 FY26 |
| Defense receivables clearance | Full clearance of delayed defense-linked receivables | By December |
| Finance cost normalization | Elevated finance costs to settle | Within Q3 FY26 |
| Unexecuted order book execution | Majority of backlog executed | Within this fiscal year; spillover by Q1 next year |
| IPO working capital deployment | IPO proceeds deployed into working capital | Q4 FY26, once plant is operational |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue | 43% YoY increase in H1 FY26 |
| Gross margin | 65% rise in H1 FY26 |
| EBITDA | 36% improvement in H1 FY26 |
| Profit after tax | 22% expansion in H1 FY26 |
| Employee cost | ~80% YoY increase in H1 FY26; flat from H2 FY25 to H1 FY26 |
| Finance cost | Doubled YoY, driven by delayed defense-linked receivables; expected to normalize as INR20–25 cr recovered Oct–Dec |
| Residential segment revenue share | 32% of H1 FY26 revenue |
| Government segment revenue share | 36% of H1 FY26 revenue |
| Distribution sales revenue share | ~70% of revenue split |
| Unexecuted order book | INR229 cr as of H1 FY26 |
| L1 orders | INR209 cr |
| Bidding pipeline | Over INR900 cr |
| Residential channel partners onboarded | ~450 new partners via Solarium Saarthi Initiative in H1 FY26 |
| Residential footprint expansion | 25 additional cities in H1 FY26 |
| Structure manufacturing cost advantage | 4–5% on structure cost, adding 0.3–0.5% to EPC margins |
| Module manufacturing plant capacity | 1,000 MW automated plant in Ahmedabad, commissioning mid-Jan to end-Jan 2026 |
| Module plant standalone EBITDA margin target | 12–13% |
| Module plant initial utilization | 40–50% for first couple of months, targeting 75% within Q1 FY27 |
| Module plant revenue potential at 85% utilization | INR1,000 cr+ as a standalone unit |
| Gross margin improvement from captive module consumption | 5–7% improvement foreseen |
| Working capital required for manufacturing plant | INR80–100 cr; Q4 FY26 requirement of INR60–70 cr |
| Win ratio (by number of orders) | 25–30% |