Key Takeaways


Financial Performance

Panjwani: "We have time and again mentioned that we should be in some 15 kind of a range and we will always remain in double digits."

Competitive Position & Margin Defence

Panjwani: "We want to protect our margins and therefore we don't get into any speculative arrangement because modules remain the significant part of the procurement if the project is along with modules."

Order Book & Execution Pipeline


Technology & New Verticals

Panjwani: "We are not looking at this sector as solar sector... we are looking at renewable energy projects is the right terminology... You put any number, it will be an underestimate, you know."

Market Opportunity & Policy Backdrop


Capital Efficiency & Asset Strategy


Guidance & Commitments

CommitmentSpecificsTimeline
EBITDA marginRemain in double digits; ~15% stable modelling marginOngoing
Order book execution~2.1 GW unexecuted order book to be completed9-12 months from July 1
Full-year volumeEnd the year at ~1.8 GW to 2 GW of businessFY25
O&M portfolioReach ~2 GW, with revenue 2x to 2.5x current levelsBeginning of next year (FY26)
PowerSale revenueContinue at current run rate with 3-4% variationRest of FY25
5B Maverick deploymentDeployments to begin"Coming couple of months"
Green hydrogen pilotUpdate when progress occurs; awaiting land from government agencyNo timeline

Key Metrics

MetricQ1 FY25
Revenue₹236.35 cr, +83.31% YoY
EBITDA₹41.08 cr, +206.6% YoY
EBITDA margin>17%; management guides ~15% as stable, maintainable margin
Profit after tax₹28.16 cr, +208.51% YoY
Unexecuted order book2,191 MW
Order book at beginning of year2.3 GW
MW executed in quarter217 MW
Order wins in quarter58.19 MW peak
Current bid pipeline15.5 GW
IPP revenue~₹7.5 cr
O&M portfolio500 MW currently; expected to reach ~2 GW by beginning of next year
O&M revenue~₹2.5 cr in Q1; full year expected ~₹10 cr
Permanent employees~240
Employee cost~₹6 cr, up from ₹4 cr
Average realization per MW₹1 to ₹1.2 cr