Key Takeaways
- Highest-ever quarterly revenue and PAT: Execution in H1 FY26 alone (1,621 MWp) surpassed all of FY25, driving a sharp EBITDA margin jump to 20.39% from 13.65% YoY.
- Order book swells to 3.48 GWp: The company booked 1.8 GWp in H1, and the current backlog is expected to convert to revenue over the next 12 to 15 months.
- Margin floor is 15%, not a ceiling: Management is comfortable guiding to >15% EBITDA margin for FY26, but operational efficiency and procurement capabilities can push realized margins toward 20%.
- New vectors are early but deliberate: The board approved 51 MWp of new IPP assets, a small BESS order sits in the backlog, and a senior hire is exploring data center EPC, though none of these are material yet.
- What to watch next quarter: Whether the H2 execution run rate sustains the upward trajectory, the pace of new order booking to replenish the 12-15 month backlog, and any concrete data center or international EPC win.
Financial Performance
- Revenue surge driven by volume: Revenue rose to ₹1,377 crores in H1 FY26, powered by execution of 1,621 MWp, which already exceeds the ~1.5 GWp executed in all of FY25.
- Margin expansion from operating leverage: EBITDA margin improved to 20.39% from 13.65% YoY, attributed to operational efficiency, tight budgeting control, and real-time project monitoring.
- Realization per MW is a range, not a point: Per-MW revenue varies from ₹0.8 crore to ₹1.3 crore depending on whether the scope is pure EPC (modules supplied by client) or turnkey (modules under scope), making a single blended realization figure misleading.
- Margin consistency across contract types: Margins are not inherently lower for pure EPC versus turnkey work; the company evaluates each order on its own risk-reward metric and does not bid below a threshold limit.
- IPP revenue sits in operating revenue: Income from the IPP portfolio is classified under revenue from operations alongside EPC and O&M, not as other income. Other income consists of bank FD returns and returns on spare cash.
- Cash flow expected to improve: With more orders slated for execution in H2, the operating cash flow position is expected to strengthen.
Manmohan Sharma: "The margin where we are comfortable is around 15%. But with the operational efficiency, tight budgeting control, monitoring all projects in real-time basis, we are able to get this kind of margin."
Order Book & Demand Pipeline
- Backlog stands at 3.48 GWp: After executing roughly 900 MWp in the quarter, the order book grew from 3.15 GWp last quarter, with H1 booking of 1.8 GWp. The current backlog is likely to be executed over the next 12 to 15 months.
- All current orders are domestic EPC: The entire 3.48 GWp order book is domestic, though the company is actively looking at international opportunities.
- Order flow seen as continuous: Management expects order flow to continue over the next few years, citing the country's green energy targets.
- No pricing pressure from competition: While competition exists, the company remains selective, only booking orders that meet its internal risk-reward metric after evaluating budget and margin.
- Order book churn is continuous: As orders are executed, new ones are rebooked; the company can handle projects ranging from 100 MWp to 2 GWp in size.
- BESS is a small but present opportunity: A 40 MWh BESS order is part of the current order book, executed on a pure EPC basis with no battery capex for the company. The company is actively participating in all possible BESS bids, though it is difficult to estimate the pipeline size.
- Data center exploration is nascent: A senior-level hire has been made to explore data center EPC opportunities, but no formal bidding is underway, only bilateral discussions. Management estimates the current Indian data center market at 250-300 MW, with at least 1 GW more expected over the next 4-5 years.
- No softness expected beyond FY27: Management sees opportunity beyond the 500 GW target, noting that 21 GW was added in H1 alone, suggesting the target may be reached earlier than expected.
Manmohan Sharma: "We are not going any kind of like below to the threshold limit to have the order in our kitty. So, accordingly, after analyzing the every order which suits our risk-reward metric, then only we go ahead with booking the order."
Margin Mechanics & Sustainability
- Internal mandate starts at 15%: Every contract is signed with a mandate of at least 15% margin internally. During execution, design and procurement capabilities push realized margins to 16%-20%.
- Ground-mounted projects drive scale and margin: The majority of revenue comes from ground-mounted projects, which can scale up to 1-2 GWp and deliver maximum margin through operational efficiency.
- No regional margin differentiation observed: The company has not seen projects in northeast or eastern states commanding better margins than other regions; execution spans Rajasthan, Gujarat, MP, Andhra, Maharashtra and others.
- Procurement is arms-length: When modules are procured, quotations are taken from Waaree Energies but always on an arms-length basis with minimum comparable quotations.
- Parent company revenue is not significant: Some projects are executed for Waaree Energies, but the portion was not significant in H1 execution; one order from the parent was received in H2.
Abhishek Pareek: "When we take up a project or whenever we sign up for a contract with a customer, we start with a mandate of at least 15% margin internally... bare minimum that we look at is around 15% when we started the project, but our endeavor is always to take it up to a..."
IPP & Adjacent Bets
- IPP portfolio is growing slowly: The board approved an additional 14 MWp in Maharashtra and 37 MWp in Rajasthan, in line with the existing 54 MWp IPP project. Execution is expected in H2 or slightly later.
- IPP provides long-duration revenue: IPP assets generate revenue for 20-25 years, but the core business remains EPC and O&M. Management did not confirm a target revenue mix, pushing back on a 70:30 EPC-to-IPP split suggestion.
- O&M portfolio is expanding: A 412 MWp project completed this quarter is likely to add to the O&M book going forward, and the year-on-year O&M portfolio is increasing.
- Cooling business stake is a synergy play: The company acquired a ~3% stake in a cooling solutions provider for large offices and factories, seeing synergy for solar installation EPC opportunities.
- Asset-light model preserved: The company carries only ~₹20 crores in term loans for the IPP business and has no plans for foreign investment or promoter stake increases.
Policy & External Factors
- GST reduction is a tailwind: The GST rate on solar modules was reduced from 12% to 5%, which is expected to decrease capital expenditure.
- ALMM List 2 delay has no impact: The extension of ALMM List 2 implementation does not affect the company because most contracts were already signed and PPAs were in place. Management declined to comment on whether further delays are expected.
- Evacuation and connectivity risks sit with the customer: Any such issues fall within the customer's scope, not the company's EPC work, and have not affected execution.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| EBITDA margin floor | More than 15% for the full financial year | FY26 |
| Order book execution | Current 3.48 GWp backlog to be executed | Next 12 to 15 months |
| IPP project execution | Approved 14 MWp (Maharashtra) and 37 MWp (Rajasthan) projects to be built | H2 FY26 or slightly later |
| Cash flow improvement | Operating cash flow position to improve as more orders are executed in H2 | H2 FY26 |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue from operations | ₹774.78 cr, +47.73% YoY |
| EBITDA | ₹157.94 cr, +120.69% YoY |
| EBITDA margin | 20.39%, vs 13.65% in Q2 FY25 |
| PAT | ₹116.34 cr, +117.40% YoY |
| H1 FY26 revenue from operations | ₹1,377.97 cr, +81.12% YoY |
| H1 FY26 EBITDA | ₹275.48 cr, +144.56% YoY |
| H1 FY26 PAT | ₹202.73 cr, +148.21% YoY |
| Unexecuted order book | 3.48 GWp, to be executed over next 12–15 months |
| H1 FY26 order inflow | 1.8 GWp |
| H1 FY26 EPC execution | 1,621 MWp, exceeding full-year FY25 execution |
| FY25 full-year EPC execution | ~1.5 GWp |
| Order book per MW range | ₹0.8 cr to ₹1.3 cr per MW, depending on scope |
| Bidding pipeline tracked | ~27 GWp (government tenders 6–7 GW, private C&I and IPP ~20 GW) |
| India solar capacity addition pace | 21 GW added in last six months, 40–50 GW expected annually |
| IPP assets approved for addition | 14 MWp in Maharashtra, 37 MWp in Rajasthan |
| BESS order in current order book | 40 MWh |