Key Takeaways
- Explosive revenue growth, margin peak unsustainable: Revenue surged ~339% YoY to INR324 crores, but the Q3 EBITDA margin of 27%+ is a high-water mark; management guided sustainable margins at 15–20%.
- Order book provides near-term visibility: An unexecuted order book of 749+ MWp and a 9 GW bidding pipeline support the FY24 execution target of 900–950 MW, though conversion rates are lumpy and undisclosed.
- PSU shift is a volume-for-margin trade: PSU orders, currently under 10% of the book, are set to rise significantly, compressing margins but scaling volumes without requiring additional capital.
- Pure-play EPC, agnostic to supply chain shocks: The company is a pure EPC player with no manufacturing exposure, insulating it from module price volatility and China Plus One dynamics.
- What to watch next quarter: Whether the guided 375–420 MW Q4 execution materializes, the pace of PSU order conversion from the 9 GW pipeline, and the trajectory of blended margins as the mix shifts toward module-supply contracts.
Financial Performance
- Revenue trajectory: Q3 FY24 revenue of INR324.19 crores grew ~338.78% YoY from INR73.88 crores, driven by strong execution of the order book.
- Margin reality check: Q3 EBITDA margin of 27%+ is not sustainable; EPC contracts span 3–6 quarters and margins in entirety hover between 15%–20%. Q1 was 12.4%, Q2 was 18.7%.
- Power revenue contribution: INR10.89 crores generated from 44 MW of power assets in 9M FY24, a small but steady contributor.
- Revenue per megawatt range: Overall range is INR1.1–1.2 crores per megawatt; nine-month average was INR1.27 crores despite some module contracts; some contracts can be as low as 90 lakhs per megawatt depending on scope.
- Working capital efficiency: Most projects come from utility IPP and C&I segments with favorable payment terms: 10% mobilization advance, payments within 15–20 days of material supply, and LC credit periods available. PSUs pay fast but 10%–15% of capital gets held up.
Order Book & Pipeline
- Current backlog: Un-executed order book stands at 749+ MWp; 473+ MWp executed in 9M FY24.
- FY24 execution target: Planning to execute 900 to 950 MW in total for FY24; Q4 expected range of 375–400 MW, possibly up to 420 MW, though this could change due to variables outside control.
- Bidding pipeline scale: 9 GW pipeline under discussion with potential customers, increasing by the day. Management gave a thumb rule conversion rate of 30–40% when pressed, but declined to give a specific percentage, citing that orders are too large for a relevant percentage.
- Order book composition shift: Bulk of the 750 MW order book is still from utility IPP; pipeline shows movement towards PSUs, which were under 10% but will see significant increase as bids happen every couple of weeks in the PSU segment.
- New wins in Q3: Received one rooftop solar project and one ground-mounted solar project, already announced on stock exchanges.
Panjwani: "when private sector, when you go to utility IPP and other segments, people choose you not because of competitive intensity, people choose you because you are set apart from others, in terms of your capability and vintage heritage experience, whatever inverted commas you want to put."
Margin Structure & Competitive Dynamics
- Module vs non-module mix: 25%–30% of orders come with modules; margins on modules shrink overall margins. Company uses blended margins and does not differentiate externally.
- PSU margin-volume tradeoff: PSU orders may compress margins but volume substantially increases; economies of scale on the operating side would play out; no additional capital needed to deliver large volumes.
- Competitive moat in private sector: In utility IPP and C&I segments, clients choose based on vintage, experience, design capability and optimization, not just price. In PSU and government sectors, L1 bidding applies.
- Module price tailwind: Lower module prices due to Chinese oversupply are favorable for new project starts, expected to bring more opportunities for EPC companies.
- China Plus One insulation: As a pure EPC player, the company is agnostic to whether clients use imported or domestic material, so it is not impacted by China Plus One dynamics.
Panjwani: "even if it's like a platform, what happens in a platform is that, once you get big orders, from PSUs, let's say you get 500 megawatts, 700 megawatts, if you get two, three orders, you are already 2.5 gigawatt and your economies of scale on the operating side will also play out, though your margins will come out, but you don't need additional capital to deliver them at the end of the day."
Strategic Positioning & New Initiatives
- Pure-play EPC identity: Waaree Renewable Technologies is a pure EPC player, not a manufacturing company; modules are procured from anywhere including Waaree Energies Limited with no captive arrangement.
- Energy transition scope: Company will participate in solar, battery, and pump storage projects as they arise; planning to do all kinds of projects in the renewable space.
- Green hydrogen pilot: Contract won on a pilot basis from a PSU; land yet to be provided by the PSU. Company will execute hydrogen projects that come up in future.
- Maverick collaboration: Collaboration agreement with Maverick Services Private Limited; they need to set up manufacturing in India and start client discussions; planning to invite them in first quarter to adhere to terms and set up a unit for showcasing. Client acceptance could take anywhere between one quarter and a couple of quarters.
- Suryodaya scheme caution: Company is treading the scheme but normally deals in big megawatt projects (50–100 MW, even 290 MW); rooftop kilowatt projects are scattered and may not be remunerative for EPC. No plan formed yet on how to approach.
- O&M as tail business: Company tries to get O&M contracts as tail business but there is no compulsion; big utility scale providers generally do not give O&M; smaller contracts (200–300 MW) normally give O&M to the company.
Panjwani: "the sector is at such a good growth point that there is no antithesis, you know, it's just you have to seize the moment and every company has to work in getting the business on its right side."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| EBITDA margin range | Sustainable EBITDA margins expected at 15% to 20% | Ongoing (contract-level, 3–6 quarter cycles) |
| FY24 execution | Execute 900 to 950 MW total | FY24 (473 MW done in 9M) |
| Q4 FY24 execution | 375–400 MW, possibly up to 420 MW | Q4 FY24 (subject to variables outside control) |
| PSU segment mix | Significant increase from under 10% of order book | Imminent (bids every couple of weeks) |
Key Metrics
| Metric | Q3 FY24 |
|---|---|
| Revenue | ₹324.19 cr, up ~338.78% YoY from ₹73.88 cr |
| Revenue from operations & O&M (9M FY24) | ₹7.19 cr |
| Revenue from power (9M FY24) | ₹10.89 cr |
| EBITDA margin | 27%+, vs 18.7% in Q2 FY24 and 12.4% in Q1 FY24 |
| Sustainable EBITDA margin guidance | 15% to 20% |
| Profit after tax | ~₹60 cr |
| Unexecuted order book | 749+ MWp |
| Orders executed (9M FY24) | 473+ MWp |
| FY24 execution target | 900 to 950 MW, of which 473 MW executed in 9M |
| Q4 FY24 execution expectation | 375 to 420 MW (internal target range) |
| Bidding pipeline | 9 GW as of January 31, 2024 |
| Bid conversion rate benchmark | 30% to 40% |
| Power assets owned | 44 MW |
| Revenue per MW (overall) | ₹1.1 cr to ₹1.2 cr |
| 9M FY24 average revenue per MW | ₹1.27 cr (per an analyst's math) |