Key Takeaways
- Revenue nearly doubled, outpacing the sector: Revenue grew 82% YoY to INR1,598 crores, well ahead of India's solar capacity addition rate, while PAT rose 58% YoY on strong execution and cost discipline.
- Order book deepened to 3.2 GW: The unexecuted order book grew from 2.3 GW to 3.2 GW over the year, with 2.5 GW+ of new orders won, providing 12 to 15 months of revenue visibility.
- Margins are over-delivering against a 14–15% range: Management guided to a 14–15% EBITDA margin band but noted teams have been generating "even more" each passing quarter, with large-scale projects holding that range and C&I rooftop adding 200–300 bps above it.
- BESS and data centres are the next adjacency: A 40 MWh standalone BESS order is underway as battery pack prices collapsed from $200 to $60–$70 per MW hour, and the company is now actively bidding for data centre EPC work.
- What to watch next quarter: Whether the 3.2 GW order book execution pace holds, any margin uplift from the growing C&I mix, and the first data centre contract win.
Financial Performance
- Top-line surge: Revenue of INR1,597.75 crores grew 82.29% YoY, significantly surpassing the growth rate of India's solar sector during the same period.
- Profitability kept pace: EBITDA grew 50.06% YoY and PAT grew 57.64% YoY, attributed to operational efficiency, cost management, and the ability to scale the business efficiently.
- Execution velocity: The company executed 1,524 MWp of EPC orders in FY2025, with around 500 MWp executed in Q4 alone.
- Working capital stretched by scale: The shift from small C&I projects to GW-scale single-location contracts (9 to 12 months duration) has changed the cash flow profile, with capital deployed upfront and retention money of 10–15% arriving only at the rear end of projects.
- No equity raise planned: Management stated there is no immediate plan for fund-based capital fundraising and will continue to depend on non-fund-based working capital limits.
- IPP capex underway: INR101 crores of capex was accounted for IPP assets being created by WRTL, marking a move into asset ownership alongside the EPC business.
Sharma: "The margin, we are not giving any kind of guidance as far as the margins are concerned, but it should be in the range of 14% to 15% going forward."
Order Book & Pipeline
- Year-end position: The unexecuted order book stood at 3.2 GWp as of the reporting date, up from 2.3 GW at the start of the year, with 1.5 GW executed and over 2.5 GW of new orders won during FY2025.
- Execution timeline: The 3.2 GW order book is likely to be executed in the next 9 to 15 months, giving visibility through FY2026.
- Q4 inflow: The company received orders of around 500 MW during the last quarter.
- Jindal Renewables progressing: The 2 GW order from Jindal Renewables started execution and was partially executed during FY2025; it will be completed in FY2026.
- Land and connectivity scope: Around 15–20% of orders come with land and connectivity requirements; the rest have customer infrastructure already in place.
- Bidding pipeline scale: The company is tracking a bidding pipeline of 30 GW, which management says means it is tracking almost every large order in the country.
- Market share ambition: Management stated its ability to have a larger share of the pipeline "cannot be denied," though it declined to provide a hit-rate estimate or the total tendered market size to calculate current share.
- Realization range: Broader realization should be in the range of INR80 lakhs per MW to INR1.2 crore per MW.
Pareek: "Mathematically, we have runway of 40 GW to 50 GW installations minimum level each passing year. As we say that we have an order pipeline or bidding pipeline of 30 GW, it means we are tracking almost every large order in this country."
Margin Dynamics & Mix
- Large-scale baseline: Large-scale projects maintain margins in the 14–15% range and even more, with teams over-performing every passing quarter.
- C&I premium: Small rooftop C&I projects carry 200–300 bps better margins than utility-scale work due to smaller size and cash spending patterns.
- PSU orders with land: An analyst asked whether more PSU orders bundled with land could inch margins to 18–20%, but management declined to comment directly on the margin impact.
- No formal margin guidance: The company normally does not give future guidance as a policy matter, though the CFO offered 14–15% as a directional range.
- C&I capability build: The company is building capabilities to replicate its utility-scale success in the rooftop and C&I segment, which would lift the blended margin if the mix shifts.
New Adjacencies: BESS & Data Centres
- BESS price collapse opens the market: The price of storage packs dropped from $200 per MW hour last year to $60–$70 per MW hour this year, a move management described as "a different level of price action" that it never thought would materialize.
- First BESS order in hand: The company has a 40 MWh standalone BESS EPC project where it is retrofitting storage into an ongoing power project.
- Data centre entry: The company announced it is building EPC capabilities for data centre projects and is already bidding for them, citing the power-intensity gap between traditional and AI-driven infrastructure as a structural demand driver.
- Energy transition portfolio broadening: The EPC portfolio has expanded from solar-only to FDRE and RTC projects including battery energy storage, and management stated it has "never shied away from enhancing" its offering.
Pareek: "If you compare a typical Google data centre versus an AI data centre, the power requirement is at least 10x higher in AI-driven infrastructure. Hence, this becomes of eminent importance for us as a group that we keep on hunting on opportunities in data centre."
Industry Context & Enablers
- Sector tailwind: India's solar power sector added 23.83 GW in FY2025, a significant increase over 15.03 GW in the previous year, driven by expansion across ground-mounted (81.01 GW), rooftop (17.02 GW), and other segments (7.61 GW).
- Government scheme momentum: PM-KUSUM saw a 4.2-fold increase to 4.4 lakh solar pumps installed in FY2025; PM Surya Ghar Muft Bijli Yojana benefited over 11 lakh households as of March 31, 2025.
- Tendering volume: Government tendering of 30–35 GW for ground-mount projects is expected this year.
- Transmission bottleneck easing: Transmission has had bottlenecks in the past but equal support in investments by government and private players means the order book of transmission companies now justifies expectations of installations going higher.
- Long runway: India has a clear runway of around 170–180 GW worth of solar over the next five years, requiring 40–50 GW of installations minimum each year.
Disclosure & Engagement
- Limited contract detail: An analyst requested more detailed press releases on new agreements including tenure and project specifics. Management responded "We'll look into it" but noted they already make disclosures as required under LODR regulation, a deflection rather than a commitment.
- No segment bifurcation: Management declined to provide a bifurcation of utility versus C&I revenue or order book, stating "We don't give this kind of bifurcation detail as far as the customer base are concerned."
- Competitor silence: When asked whether a competitor's regulatory mishap would open up a bigger bid pipeline, management said "We refrain from commenting on anything that's happening in market."
- Dividend non-answer: On dividend payout increases, management deflected with "As and when the Board approves it, I think we should get back to you."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Order book execution | 3.2 GW unexecuted order book to be completed | 9 to 15 months |
| Jindal Renewables order | 2 GW order fully executed | FY2026 |
| EBITDA margin range | 14% to 15% going forward | Ongoing |
| Working capital funding | No fund-based capital raise planned; continue with non-fund-based limits | No immediate plan |
| Data centre EPC | Building capabilities and actively bidding | Underway |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Revenue | ₹476.58 cr, +74.37% YoY |
| EBITDA | ₹126.33 cr |
| PAT | ₹93.77 cr |
| FY25 Revenue | ₹1,597.75 cr, +82.29% YoY |
| FY25 EBITDA | ₹310.90 cr, +50.06% YoY |
| FY25 PAT | ₹228.92 cr, +57.64% YoY |
| EBITDA margin guidance | 14% to 15% going forward |
| Unexecuted order book | 3.2 GWp, to be executed in 9 to 12 months |
| Q4 execution | ~500 MWp |
| FY25 execution | 1,524 MWp |
| FY25 order inflow | ~2.5 GW+ (per an analyst's math) |
| Order book with land and connectivity scope | 15% to 20% of orders |
| Realization per MW | ~₹1 cr in Q4, broader range ₹80 lakh to ₹1.2 cr per MW |
| BESS order book | 40 MWh standalone BESS EPC project |
| Capex on IPP assets | ₹101 cr |