Key Takeaways
- Producer status achieved: Q1 FY27 established Deccan as a producer, with Jonnagiri producing 112 kilos of dore bar from which about 90 kilos of bullion was produced, and Altyn Tor producing its first dore bar in Kyrgyzstan.
- Sales deliberately lagged production: Only 59 kg sold in Q1 versus ~90 kg produced, as management held ~80 kg of gold inventory to capture higher prices; this depressed EBITDA/PAT and should reverse in Q2.
- Two-mine revenue starts next quarter: Altyn Tor revenue and profits are expected to be booked in the September quarter, adding to Jonnagiri's contribution for the first time.
- ₹137 crore raise funds the next leg: The board-approved capital raise, with HNA and management participation, is earmarked largely for drilling across Finland, Spain, Mozambique and Chhattisgarh.
- What to watch next quarter: Whether ~170 kg of Jonnagiri gold in stock by end-Q2 converts into sales, whether Altyn Tor books its first revenue, and whether management delivers the promised clarity on FY27/FY28 production guidance.
Transition to Producer
- Two operating mines now: Jonnagiri in India and Altyn Tor in Kyrgyzstan are both producing, marking the shift from explorer to producer that management calls a "significant milestone."
- Jonnagiri ramp-up: Q1 production of 112 kg dore / 90 kg bullion reflects a strike rate of about 1 kg per day, the first quarterly ramp-up target; production is being stabilized and increased.
- Plant performance: Management stated the Jonnagiri processing plant is "running fully well"; upcoming production improvement will come from grade, not plant issues.
- Altyn Tor derisking: Dore bar produced from the Merrill-Crowe system via a smelting test, demonstrating operational viability of the process flow sheet; gravity circuit commissioned and leaching circuit added, moving close to full-scale production.
- Altyn Tor production source: First 4 to 5 years of production will come primarily from existing tailings (0.06 crore tons at 1.3 g/t) and about a million tons of low-grade stockpile already on the ground.
Dr. Hanuma P Modali: "As a snapshot, it has established us as clearly as producers. All the time we have been explorers and last so many years we have been exploring in this country, but in the March quarter we have shown some production and June quarter has clearly established us as the producer."
Jonnagiri: Sales Timing and Cash Flow
- Low Q1 sales: Only 59 kg of gold was sold in Q1, making EBITDA/PAT numbers look "significantly on the lower side"; this was partly because the official inauguration happened on 24th June, near quarter-end, leaving little time to sell.
- Inventory build: ~80 kg of gold (40 kg refined gold + 60 kg dore bar equivalent to ~40–42 kg gold) remained unsold in stock at end of June quarter.
- Gold price timing: Management deliberately held gold in stock because gold prices improved significantly; they expect to benefit by selling at higher prices in the coming quarter.
- Q2 stock position: With ~80 kg carried inventory plus ~90 kg production, ~170 kg of gold will be in stock by end of Q2; next quarter "should clearly give us a kind of guidance" on production and PAT margins for the year.
- EBITDA stabilization: Expected to stabilize at 65–70% within another quarter or two.
- Cash flow constraint: Profits are booked in Deccan's accounts, but cash can only come as dividends from Geomysore; management doubts dividends will arrive this financial year because expansion, land acquisition, and processing plant costs are consuming cash; dividends might happen next year but cannot be guaranteed.
Dr. Hanuma P Modali: "Actually there is a significant improvement in the gold price. So I am really holding that gold in the stock. I think it will benefit us in this quarter when we sell the gold at the higher price."
Altyn Tor and Kyrgyzstan
- Commissioning path: Larger leach circuit and tailings facility to be completed and commissioned; Dr. Modali visiting site next week to review final arrangements; production commencement and inauguration date to be decided during that visit.
- Tailings dam: New tailings dam being built to sustain next 10 years; must be completed before commissioning the entire project.
- Resource expansion: Mining activities to start this month (August/September) to enhance resources; revised resource estimate within the mine expected by October 2026; first phase revised mine design and life-of-mine plan to be delivered by October 2026; underground resources expected to exceed 5 tons, adding 6–7 years of project life.
- Recruitment: Another 100-odd people to be recruited with enhanced capacity; recruitment process already on; about 30 engineers from India, some already at site.
- Government offer: Kyrgyzstan government offering Deccan one more gold project of roughly 10 tons; team currently doing due diligence; intention is to take the project if due diligence passes.
- Community engagement: Management says the government offered a new project because Deccan convinced the local community to allow a leaching circuit, which the government previously could not get permission for; this demonstrated commitment and capability to take the community along.
Dr. Hanuma P Modali: "Previously the government could not actually get the permission for the leaching circuit there. So that shows our commitment, our capability to take the community along with us."
Finland and Ganajur: The Next Gold Projects
- Finland grade advantage: Kuikka average grade above 5 g/t and Pahkalampi about 3.5 g/t, versus Jonnagiri's 1.4–1.5 g/t; higher grades support a centrally located plant for the two deposits 25 km apart.
- Finland drilling: Drilling operations targeted to start September 15; 1,500 meters planned; results in next 3–6 months; target to increase Kuikka resource to almost 4 tons; combined projects to have more than 5–6 tons of gold.
- Finland stake: About $1 million investment to take Deccan to 51% planned in the coming quarter; money to be used for drilling.
- Finland feasibility: Planned for year 2027; need at least 4 tons of resource, to be achieved very soon.
- Finland processing concept: Centrally located flotation circuit plant for higher-grade ore; possibility of bringing concentrates to India to refine and produce gold for price advantage; underground mines planned at both deposits, considered better given Finland's environmental restrictions.
- Ganajur status: Awaiting court decision; after two years of delay, hearings started before the court's summer vacation in May; hearings were expected in July but have not come up for regular hearing so far; management remains hopeful.
- Ganajur legal position: Recent judgments (e.g., Gadchiroli iron ore case restoring pre-2015 rights) give strong legal position; government may consider leeway under recent Mining Act developments; if mining lease granted, about 1 ton of gold production in 2–3 years.
Dr. Hanuma P Modali: "I do not see any other project, which is more closer to the production than the Ganajur project in this country. So it makes all the sense for the government to actually give us helping hand so that we can start producing."
Critical Minerals: Drilling and Validation
- Logrosán tungsten (Spain): Every hole intersected tungsten or tungsten-tin mineralization; mineralization continues from surface to depth; widths up to 7.5 meters help underground mining maneuverability.
- Logrosán timeline: Full Dehesa results expected by mid-September; preliminary resource modeling by early October to be announced to market; additional 1,000–2,000 meters resource definition drilling in Dehesa; beneficiation test work simultaneously; by mid next year expect a lot of information.
- Logrosán scale: Preliminary guesstimate of 1,000 tons processing facility (about 300,000 tons input per year); if 10-year project, around 0.3 crore tons overall resource.
- Chhattisgarh drilling: 15th drill hole ongoing; about 2,500 meters drilled; 1.3 km mineralized zone identified; around 700 meters more or less proved; most drilling concentrated in northern side where red patches are concentrated.
- Chhattisgarh timeline: First phase resource estimation planned very soon once all results come out; plan to apply for mining lease by next year; process flow sheet to be completed by mid next year; tentative 3,000 tons per day processing plant; significant capex expected.
- Mozambique: Drilling to start mid-September or end of September; 1,500–2,000 meters in both areas; aim to set up 200 ton per day processing plant by end of 2027; if not 2027, at least first quarter of 2028 for concentrate production; first critical mineral project to produce and show revenues maybe in 2028.
- Price validation: Tungsten up 622% in last year due to uses and scarcity, majority controlled by Chinese; tantalum up 196%; lithium up 108%; natural graphite up 5% despite synthetic graphite production, validating the strategy.
- Battery metals strategy: Primary focus on battery industry because energy storage in India to increase significantly; want to look for more assets to strengthen battery metal strategy; graphite project in Africa under review; every battery has at least 50% graphite in anode.
Funding and Capital Structure
- Current raise: ₹137 crores via CCDs, equity shares and equity warrants; HNAs have shown interest and management (including Dr. Modali and Jade Devenish) are contributing; subject to shareholder approval.
- Raise purpose: Expected to accelerate Deccan's transition into a production-oriented mining company; large part going into drilling operations.
- Larger QIP planned: Current Rs.137 crore fundraise is short-term/intermediate funding; larger QIP placement still planned; in next 3–4 months there is a commitment to drill; drilling now will give clear idea of how much to raise in larger funding and which projects require large funding.
- Total funding need: ~₹2,000 crore total required; management expects critical mineral projects to be funded via off-take arrangements (citing graphite/lithium examples where end-users fund projects in exchange for discounted 10-year supply agreements).
- Gold project funding: Will be raised through equity and debt (50-50% or 40% equity / 60% debt); no off-take arrangements for gold because they "sometimes may not work very well in the gold industry."
- Debt availability: Banks and lending institutions expected to lend once good numbers arrive in the next two to three quarters.
- Strategic partnerships: Not yet decided whether to bring in a large promoter or remain professionally run; management prefers current professional team model with promoter/Hira Group support; leaves open possibility of a strategic partner if drill results are good.
- Government support: Management "very confident" of government funding support for critical mineral projects via the National Critical Mineral Mission; National Mineral Exploration Trust (~₹16,000 crore corpus) will fund some overseas exploration by private companies, with a cap of "million dollars or something" for drilling projects; availing funds requires bringing critical minerals back to India.
Dr. Hanuma P Modali: "We are not going to have any off-take arrangement because the gold pricing and the off-take arrangements sometimes work well, but sometimes may not work very well in the gold industry."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Jonnagiri FY27 production | 500–600 kg; clarity on whether 600 kg achievable | End of next quarter |
| Jonnagiri FY28 production | 750–800 kg | FY28 |
| Jonnagiri EBITDA | Stabilize at 65–70% | Within another quarter or two |
| Jonnagiri expansion | Processing facility from 1,010 to 2,500 tons per day; ~2 tons per annum maximum | Around FY29–FY30 |
| Jonnagiri resource growth | Target 40 tons of gold for more than 25 years of mine life; independent sign-off to be announced | No date |
| Altyn Tor FY27 production | 150–160 kg, starting September with ~180 days available through March | FY27 |
| Altyn Tor FY28 production | 300–350 kg | FY28 |
| Altyn Tor resource estimate | Revised resource estimate within the mine; first phase revised mine design and life-of-mine plan | October 2026 |
| Altyn Tor underground capex | ₹150–200 crore for decline development below the 170-meter open pit; funded from internal accruals | In 3–4 years |
| Jonnagiri underground capex | Upwards of ₹400 crore for 500–600 meter deep shafts; funded from internal accruals | In 4–5 years |
| Finland drilling | 1,500 meters planned; results in next 3–6 months | Starting September 15 |
| Finland stake | $1 million investment to take Deccan to 51% | Coming quarter |
| Finland feasibility study | Need at least 4 tons of resource | Year 2027 |
| Logrosán results | Full Dehesa results; preliminary resource modeling announced to market | Mid-September; early October |
| Chhattisgarh mining lease | Apply for mining lease; process flow sheet completed | Next year; mid next year |
| Mozambique processing plant | 200 ton per day plant for concentrate production | End of 2027 or Q1 2028 |
| New gold acquisitions | Three assets under due diligence; could come into production | End of 2027 or 2028 |
| Ganajur production | About 1 ton of gold production if mining lease granted | In 2–3 years |
| Clear FY27/FY28 production guidance | To be given | End of next quarter |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Revenue from gold sales (Jonnagiri) | ₹87 crores from sale of 59 kilos of gold |
| Profit after tax (Jonnagiri) | ₹25 crores, Deccan's share ₹6.35 crores booked into accounts |
| Geomysore Services profit contribution | ₹6.35 crores PAT booked into Deccan's accounts |
| Gold sold (Jonnagiri) | 59 kilos of bullion sold in Q1 |
| Gold production (Jonnagiri) | 112 kilos of dore bar, yielding about 90 kilos of bullion |
| Production strike rate (Jonnagiri) | 1 kilo per day, at least 30 kilos per month |
| Gold in stock at quarter end (Jonnagiri) | 80 kilos equivalent, comprising 40 kilos of gold plus 60 kilos of dore bar |
| Jonnagiri FY27 production guidance | 500 to 600 kilos, management reaffirmed prior guidance |
| Jonnagiri FY28 production guidance | 750 to 800 kilos |
| Jonnagiri target EBITDA margin | 65% to 70%, expected to stabilize in another quarter or two |
| Altyn Tor (Kyrgyzstan) FY27 production guidance | 150 to 160 kilos, starting September with roughly 180 days available through March |
| Altyn Tor (Kyrgyzstan) FY28 production guidance | 300 to 350 kilos |
| Altyn Tor investment to date | More than ₹300 crores |
| Altyn Tor tailings resource | 780 kilos of gold in 0.06 crore tons of old tailings at 1.3 grams per ton |
| Altyn Tor low-grade stockpile | About 0.1 crore tons, supporting 4 to 5 years of production along with tailings |
| Board approved capital raise | ₹137 crores through CCDs, equity shares and equity warrants, subject to shareholder approval |
| Jonnagiri processing facility approvals | 1,010 tons per day, planned increase to 2,500 tons per day |
| Jonnagiri maximum anticipated production | Up to 2 tons of gold per annum, expected around FY29 or FY30 |
| Jonnagiri target resource | 40 tons of gold, supporting more than 25 years of mine life |
| Jonnagiri employment created | About 1,000 on site plus a similar number outside the company |
| Finland (Kalevala) licensed area | 27.36 square kilometers, about 2,735 hectares |
| Finland Kuikka deposit | About 1 ton of gold at average grade more than 5 grams per ton; drilling target to increase to almost 4 tons |
| Finland Pahkalampi prospect | About 2 tons of gold historical resources at about 3.5 grams per ton |
| Finland combined target | More than 5 to 6 tons of gold, at least 4 tons needed for feasibility |
| Finland investment to reach 51% | About $1 million, of a $1 to $2 million total, planned for the coming quarter |
| Chhattisgarh nickel-copper-platinum drilling | 2,500 meters completed, 15th drill hole ongoing; 1.3 km mineralized zone identified |
| Chhattisgarh processing plant | About 3,000 tons per day tentatively planned, bigger than Jonnagiri plant |
| Logrosán tungsten project (Spain) drilling | 3,000 meters completed; every hole intersected tungsten or tungsten-tin mineralization |
| Logrosán highest drill results | 0.88% and 1.21% tungsten, the 1.21% intersected at 535 meters depth |
| Logrosán processing facility guesstimate | 1,000 tons processing facility, about 300,000 tons input per year |
| Mozambique lithium-cesium-tantalum licenses | About 150 square kilometers covered by three broadly contiguous licenses |
| Mozambique drilling plan | 1,500 to 2,000 meters starting September onwards |
| Mozambique processing plant target | 200 tons per day to concentrate lithium and tantalum by end of 2027 or Q1 FY28 |
| Critical mineral price increase, tungsten | 622% in last one year |
| Critical mineral price increase, tantalum | 196% in last one year |
| Critical mineral price increase, lithium | 108% in last one year |
| Altyn Tor underground mining capex estimate | ₹150 crores, up to a maximum of ₹200 crores, required in 3 to 4 years |
| Jonnagiri underground block capex | Upwards of ₹400 crores, required in another 4 to 5 years |
| Total capital requirement across remaining projects | About ₹2,000 crores, more than ₹1,000 crores if at least two of four projects reach feasibility |