Key Takeaways
- Revenue nearly doubled, but mix shift compressed margins: Revenue grew 99.28% YoY to INR 118.79 crores, yet the surge in lower-margin power distribution and solar EPC (9.5–10% PAT) versus CGD (15.3% PAT) squeezed overall profitability.
- Growth consumed cash, and management says that is the plan: Negative operating cash flow of INR 18–19 crores is attributed entirely to working capital deployed for project ramp-ups, not stress, with the cash-burn ratio improving 3–4.5 percentage points year-on-year.
- The order book is deep and CGD-heavy: INR 345 crores in hand, with INR 330–332 crores from CGD (18–24 month timelines) and the rest from power distribution (~1 year), providing multi-year visibility.
- A biogas pivot is underway, with near-term commissioning: The 2 TPD CBG plant is set for Q1 FY27, with a 5 TPD LOA already received and a target of 15–20 TPD capacity within 18 months, aiming for INR 170 crores in CBG revenue by FY2030.
- What to watch next quarter: Whether the CBG plant commissions on time, the pace of margin stabilization as the segment mix evolves, and any concrete progress on the stalled Ras Al Khaimah international expansion.
Revenue Growth & Seasonality
- H2 dominance is structural: In power distribution and solar EPC, municipal ROW/ROU permissions are unavailable during the monsoon, so 65% of revenue, and the maximum from Q4, lands in H2. This pattern will repeat annually.
- CGD remains the anchor: CGD contributed INR 83.24 crores, while power distribution and solar EPC added INR 35.37 crores. Management expects CGD to stay at 60–65% of revenue going forward, with the newer segments filling the remaining 30–35%.
- The 2030 ambition is built on penetration math: The INR 1,000 crore target rests on Ministry of Petroleum and Natural Gas Regulatory Board data showing only 6.5% of total volume has converted to piped natural gas, leaving 93% of the addressable market untouched.
Malhar Desai: "I can see the revenue growth by I think minimum 70% to 80% year-on-year... this is basically the conservative thing, like 70% to 80% will be the conservative thing."
Margin Profile & Sustainability
- The margin story is a mix story, not a deterioration story: CGD delivers 15.3% PAT margins, while power distribution and solar EPC sit at 9.5–10%. As the latter segments grew from zero in H1 to INR 35.37 crores in the full year, blended margins compressed, a dynamic management calls structurally improving, not one-off.
- A deliberate shift in profit philosophy: Management stated that as an unlisted company it previously chose not to show profits to avoid taxes, but after attending seminars on value creation, it changed its mindset to report true profits and share them with shareholders. The margin improvement from 8% to 20% reflects this shift.
- Selectivity is the promised safeguard: Management pledged it will not accept every LOA just to inflate the order book, committing to pursue only work with the greatest margins.
Malhar Desai: "Going forward your company is promising you that this margin will be sustainable and company to increase the order book they won't pick up any book and this is the promise from me to you."
Cash Flow & Working Capital
- Negative cash flow is growth-led, not stress-led: The INR 18–19 crore operating cash outflow stems from working capital deployed during project ramp-ups, with collections aligned to project cycles rather than structurally delayed.
- The cash-burn ratio is improving: Last year, negative cash flow was INR 12 crores on INR 60 crores of revenue; this year, INR 18–19 crores on INR 118 crores, an improvement of 3–4.5 percentage points.
- Path to positive: Management expects to report at par or slightly positive operating cash flow next year, with a firm commitment to positive operating cash flow within two years.
- Unbilled work in progress swelled other current assets: Other current assets rose to INR 56 crores from INR 26 crores last year, driven by work in progress (unbilled amounts) and GST receivables, per management clarification after an analyst query.
Malhar Desai: "I basically promised that the cash flow will see a good improvement in terms of absolute percentage against revenue... So we hereby see an improvement in the negative operating cash flow with almost 3% to 4.5%."
CBG & Green Energy Ventures
- Near-term commissioning with a small delay: The 2 TPD compressed biogas plant is now expected by end of May or June 2026, a 15–25 day delay caused by upgrading the target capacity from 1 to 2 TPD. A 5 TPD LOA has already been received.
- Aggressive scaling planned: Management targets 15–20 TPD of CBG capacity over the next 18 months, split across Gujarat (12 TPD) and Madhya Pradesh (4–5 TPD), with an MOU signed in South Gujarat and another expected in Dhar, MP within 30 days.
- CBG economics: Breakeven is expected within 18–20 months maximum, and the segment targets INR 170 crores in revenue by FY2030. CBG will be reported as a separate segment but falls under the city gas distribution channel.
- Green hydrogen is a placeholder, not a plan: Management described the venture as "very premature," with production currently too costly. Documentation is complete, and the company will blend green hydrogen into CGD gas when a fair opportunity arises, but no timeline exists.
- SGAEPL merger on the horizon: Shri Green Agro Energies Private Limited will merge into Desco Biogreen Private Limited once 5 TPD capacity is planned and commissioned.
International Expansion & Competitive Positioning
- Ras Al Khaimah entity stalled by geopolitics: Desco Global FZ-LLC was incorporated in the Dubai free zone to explore Middle East infrastructure and energy opportunities, but gas companies in Ras Al Khaimah have stopped operations due to the regional crisis. No investments have been made yet, and the company is waiting for policies to liberalize once the war ends.
- Surety bonds as a differentiator: Desco has started using surety bonds instead of bank guarantees, a practice management highlighted as distinguishing it from peers.
- Dismissive of Likhitha Infra as a peer: Management stated it does not view Likhitha as a competitor and believes Desco can match them by 10–25% in execution and operational capabilities.
Malhar Desai: "We are not looking Likhitha as our competitor to be very honest and to be very fair."
Balance Sheet & Capital Structure
- Debt-to-equity may rise modestly: Management expects the ratio to reach a maximum of 0.3 over the coming 1.5 years as the company uses structured debt and financial tools.
- NBFC loan repayment planned: After H1 of the current year, the company will structure its debt and plans to repay through internal accruals.
- CBG project financing: The company plans to raise funds through banks via greenfield project financing, with an expected cost of debt between 8.5% and 9.5%.
- Promoter holding to increase: Management stated it is "definitely looking to increase promoters holding," though no specifics were provided. On equity raising for CBG capex, management said "no comments on equity raising for now."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | Minimum 70–80% YoY (conservative) | Ongoing annual basis |
| Revenue target | INR 1,000 crores | By 2030, possibly 1 year earlier |
| Segment mix | CGD 60–65%, power distribution/solar EPC 30–35% | Going forward |
| Operating cash flow | Positive | Within 2 years; possibly as early as coming year |
| Debt-to-equity ceiling | Maximum 0.3 | Within 1.5 years |
| CBG plant commissioning (2 TPD) | Operational | End of May/June 2026 |
| CBG capacity expansion | 15–20 TPD | Over next 18 months |
| CBG revenue target | INR 170 crores | By FY2030 end |
| CBG breakeven | Achieved | Within 18–20 months maximum |
| Margin sustainability | Will not accept low-margin LOAs just to build order book | Ongoing |
| Promoter holding | Increase (quantum unspecified) | No timeline given |
Key Metrics
| Metric | FY26 |
|---|---|
| Revenue from operations | ₹118.79 cr, +99.28% YoY |
| EBIT | ₹23.43 cr, +76.30% YoY |
| Profit after tax | ₹16.38 cr, +80.87% YoY |
| EBITDA margin | 20%, vs 23% last year |
| EPS | ₹21.34, +33% YoY |
| Net worth growth | +20% YoY |
| Debt-to-equity ratio | 0.2x, vs 0.19x last year |
| Operating cash flow | ₹(18–19) cr negative, improved from ₹(12) cr negative last year |
| Revenue growth guidance (FY27) | 70–80% YoY minimum, conservative |
| Revenue target by 2030 | ₹1,000 cr |
| Order book | ₹345 cr |
| Order book, CGD | ₹330–332 cr, execution timeline 18–24 months for EPC, 24 months for O&M |
| Order book, O&M within CGD | ₹35–40 cr |
| Order pipeline | ₹650 cr, of which ₹470–480 cr CGD, ₹100 cr solar EPC and power distribution |
| CGD revenue | ₹83.24 cr, PAT margin 15.3% |
| Power distribution and solar EPC revenue | ₹35.37 cr, PAT margin 9.5–10% |
| CGD working capital days | 30–35 days |
| Power distribution and solar EPC working capital days | 10–15 days |
| Customer mix, public sector | 72% of CGD order book |
| CBG plant, 2 TPD capex | ₹3.5–4 cr, commissioning Q1 FY27 |
| CBG plant, 2 TPD annual revenue | ~₹5 cr, PAT margin 22–23% |
| CBG expansion capex | ~₹25 cr for 15–18 TPD combined capacity across Gujarat and Madhya Pradesh |
| CBG revenue target by FY2030 | ~₹170 cr |
| NBFC loan interest rate | 16–17% currently, expected to reduce to 8.5–9.5% after restructuring |
| India PNG penetration | 6.5% of households connected, 93% ungasified |