Energy Infrastructure Trust Guidance Report - SOIC x StockScans Report

as of Nov 2026

  1. UCG/coal gasification - syngas from Eluru project expected from 2030 Pending - At the Q2 FY27 call, management expected huge gas quantities from coal blocks in 3-4 years, with the Eluru UCG project guiding Phase 1 exploration (₹3,000 cr) by Q4 2027 and synthetic natural gas from 2030. Draft guidelines issued October 2025, first UCG auction held April 2026 with 2 developers selected.
  2. CBG tie-in - gas to flow in next 6-8 months from Q2 FY27 On track - At the Q2 FY27 call, management said the signed CBG tie-in agreement should deliver gas "in next 6 months, 8 months", volumes initially 0.05-0.1 MMSCMD. One compressed biogas tie-in agreement is signed and regulatory discussions for CBG injection are underway; no gas flow yet reported as of Q2 FY27.
  3. Distribution payout - ₹15-16 per unit in the near future On track - At the Q2 FY27 call, management guided payouts to continue at Rs 15-16 per unit in the near future, keeping the current return-on-capital/return-of-capital mix. H1 FY27 distribution was ₹7.76 per unit, 100% of NDCF, and FY26 distribution was ₹15.25 per unit.
  4. Trust conversion to public InvIT - put on hold Delivered - At the Q4 FY26 call, management said there were no plans to convert to a public trust; by the Q2 FY27 call, the conversion approved at the October 25 EGM was put on hold, citing improved post-stake-sale liquidity. No conversion has been executed as of Q2 FY27.
  5. Net debt-to-AUM ratio - maintain within regulatory compliance limits and stable credit rating Delivered - At the Q4 FY26 call, management committed refinancing would keep the net debt-to-AUM ratio within regulatory compliance limits and a stable credit rating, reiterated at the Q2 FY27 call. Debt-to-AUM was 44.2% as on 30 September 2026 vs 45.1% at end FY26, with CRISIL and CARE AAA/Stable ratings intact.
  6. Series 1 NCD refinancing - ₹1,000 crore maturing 11 March 2027 On track - At the Q4 FY26 call, management said "we are definitely refinancing that" on the ₹1,000 crore Series 1 NCD due 11 March 2027. At Q2 FY27, they were working with banks, evaluating a December 2026 market move via the pre-maturity call option, with 20-30 basis points of possible hardening; the ₹6,452 crore debt stack remains at 7.96%.
  7. Crown LNG Kakinada terminal - 7.2 MMTPA (\~25 mmscmd) offshore regasification, commissioning \~3.5 years from FY26 On track - At the Q4 FY26 call, management confirmed the Crown LNG commissioning date of 3.5 years from then, with 100% offtake committed to PIL and an MOU signed at Kakinada. As of Q2 FY27 PPT, the 7.2 mmtpa Kakinada terminal is yet to be operationalized.
  8. FY27 volume guidance - \~34-35 MMSCMD full-year FY27 On track - At the Q4 FY26 call, management guided flat volumes for 2 years; at Q2 FY27 they reiterated \~34-35 MMSCMD for full-year FY27, "at par if not higher". H1 FY27 volumes averaged 37.48 MMSCMD vs 34.49 in H1 FY26, with a 46.91 MMSCMD single-day record in July 2026 before softer August-September.
  9. Ennore LNG Terminal pipeline connection - commissioning expected by FY30 On track - The Q4 FY26 PPT guided the 10 mmscmd pipeline to Ennore LNG Terminal for commissioning by FY30, reiterated in the Q2 FY27 PPT. As of Q2 FY27, Ennore (5 mmtpa, IOCL) is operational but not yet connected, with the new Ennore-CS3 pipeline under development.
  10. New asset additions - value-accretive opportunities only Delivered - At the Q4 FY26 call, management saw no near-term opportunities to add assets; at Q2 FY27 they committed any additions would be value-accretive, noting current market valuations are not very accretive. No new assets have been added as of Q2 FY27.
  11. CGD connectivity project - Haryana City Gas at M&R66 planned for FY 2024-25 Partial - The FY24 annual report planned completion of the M/s. Haryana City Gas connectivity at M&R66 for FY 2024-25. The connectivity was completed in FY26, enabling 0.085 MMSCMD via hot tapping on the 48" mainline - the first in-house executed greenfield project, a year after the planned year.
  12. CGD connectivity projects - AGP at M&R63 and Bhilosa at M&R65 planned for FY 2023-24 Delivered - The FY23 annual report planned completion of 2 CGD connectivity projects, M/s. AGP at M&R63 and M/s. Bhilosa Industries at M&R65, for FY 2023-24. During FY24, PIL achieved mechanical completion of both AGP and Bhilosa connectivity projects, both listed at M&R65, and Bhilosa gas supply commenced in FY25.
  13. HCA mitigation - concrete slab installation/soil filling at 13 identified locations and PIDS implementation Delivered - The FY23 annual report planned concrete slab installation/soil filling at 13 identified High Consequence Area locations and phased PIDS implementation. Slab installation/soil filling was completed at all 13 locations against the target of 13, and PIDS was commissioned for MLV 26 to MLV 28 (52.750 km) and MLV 26 to CS 07 (48.338 km).
  14. SUG target - 1.25% for FY23 Delivered - The FY23 annual report set an HSSE score card SUG target of 1.25% for FY23. FY23 SUG came in at 1.23% against the 1.25% target.
  15. CGD connectivity projects - 2 completions planned for FY 2022-23 Delivered - The FY22 annual report planned 2 CGD connectivity project completions for FY 2022-23. In FY23, 5 projects were completed, with gas supplies commencing to Meghа Engineering at M&R54, M&R61 and M&R63, and mechanical completion of ONGC at M&R60 and Silvassa at M&R62.
  16. Additional Scrubber at CS01 - installation under progress Delivered - The FY22 annual report stated installation of an additional scrubber at CS01, for gas received at RIL-high and GAIL-medium pressures, was under progress. The FY23 annual report lists the additional scrubber at CS01 among upgrades completed in FY23.
  17. PIL connectivity with ONGC and other customers - pursuing completion Delivered - The FY22 annual report stated PIL was pursuing further connectivity projects, including with ONGC as a gas source point, and other customers. ONGC gas receipt from the KG-DWN 98/2 block commenced, and the pipeline commenced supplies to 3 CGD connectivity projects with 4 more ready for commissioning.
  18. CGD connectivity projects - 2 completions planned for FY 2021-22 Delivered - The FY21 annual report planned 2 CGD connectivity project completions for FY 2021-22. In FY22, PIL completed 7 connectivity projects ahead of customers' readiness, with 3 flowing gas and mechanical completion of 4 CGD connections.
  19. CGD connectivity projects - 2 completions planned for FY 2020-21 Delivered - The FY20 annual report planned 2 CGD connectivity project completions for FY 2020-21, after 9 completions in FY 2019-20. In FY21, PIL completed 9 CGD/industrial connectivity projects ahead of customers' readiness, with 4 of the 9 starting gas flow.
  20. SUG target - 1.58% for FY20 Delivered - The FY20 annual report set a PIL SUG target of 1.58% for FY20. FY20 SUG was reported at 1.11% against the 1.58% target.