- IPO proceeds - solar plant generation of \~2 crore kWh/year
Pending - The DRHP stated the 7.20 MW (AC) / 9.99 MW (DC) ground-mounted solar project would generate \~2 crore kWh/year. The project was commissioned and generation commenced from May 27, 2026; no actual generation figures are disclosed in our record.
- IPO proceeds - General Corporate Purposes within SEBI ICDR limit
Delivered - In the announcement dated 25th May 2026, the Company committed that post-variation General Corporate Purposes allocation remains within the SEBI ICDR limit of the lower of 15% of gross IPO proceeds or ₹10 crore. The GCP allocation was revised from ₹364.50 lakhs to ₹570.63 lakhs; against gross proceeds of ₹39.56 crore, the 15% ceiling is ₹593.40 lakhs, so ₹570.63 lakhs is within the limit.
- IPO proceeds - issue expenses at ₹433.59 lakhs
Delivered - The DRHP estimated IPO issue expenses at ₹433.59 lakhs. Actual expenses came in at ₹400.36 lakhs, leaving a surplus of ₹33.23 lakhs to be utilised for the solar project capex and reclassified into the unutilised solar capex balance.
- 100 MWp cumulative solar installations milestone
Delivered - The company announced it crossed 100 MWp of cumulative solar installations on July 16, 2026, with the FY26 Annual Report noting the milestone was achieved post March 31, 2026. The crossing occurred in June 2026, and the Q2 FY27 PPT reports a 197+ MW solar portfolio as of October 2026.
- Indrap solar project - subsidiary GRE Green Energy Private Limited
Delivered - The Q4 FY26 PPT included subsidiary GRE Green Assets of 2,016 KWp in the FY27 RESCO cumulative asset portfolio projection. GRE Green Energy Private Limited commissioned a 1.500 MW (AC) / 2.016 MW (DC) project at Indrap, Becharaji, Mehsana, Gujarat, with generation from May 30, 2026, listed at \~₹4.00/kWh.
- Rashtrapati Bhavan rooftop solar project - 1 MW (AC)
Pending - The company was awarded the 1 MW (AC) Rooftop Solar Project at Rashtrapati Bhavan, New Delhi in 2025. A new term loan of ₹2.58 crore was secured for the project during H1 FY27; no commissioning date is disclosed in our record.
- Scaling utility-scale solar development via GRE Green Energy Private Limited
On track - In the Q2 FY27 PPT, management stated it is scaling utility-scale solar development using GRE Green Energy Private Limited to accelerate large-scale greenfield solar projects and solar parks across India. The subsidiary commissioned a 1.500 MW (AC) / 2.016 MW (DC) project at Indrap, Gujarat, with generation from May 30, 2026.
- Geographic expansion beyond Gujarat into high-growth solar markets
Delivered - In the Q2 FY27 PPT, management stated geographic expansion beyond Gujarat into high-growth solar markets across multiple states. Operations now span Rajasthan, Delhi and Maharashtra, with the 50 MW AC / 65 MW DC project in Maharashtra and the Rashtrapati Bhavan project in New Delhi.
- Strategic diversification into Hybrid Energy Systems and BESS
Pending - In the Q2 FY27 PPT, management stated strategic diversification into Hybrid Energy Systems and Battery Energy Storage Systems (BESS) to address rising demand for round-the-clock renewable energy. No specific progress on Hybrid Energy Systems or BESS is disclosed in our record beyond the strategic statement.
- 50 MW AC / 65 MW DC back-to-back EPC project to strengthen track record
Delivered - In the Q2 FY27 PPT, management stated successful commissioning of the 50 MW AC (65 MW DC) back-to-back EPC project would strengthen the execution track record, enabling bids for larger-scale projects and government tenders. The project, secured as a ₹175 crore turnkey order from Solarium Green Energy, accounted for approximately 48% of H1 FY27 revenue and was executed at a lower margin to establish utility-scale credentials.
- Order book - \~₹248 crore to be executed over 6-18 months
On track - In the announcement dated 1st August 2026, the company stated the order book of \~Rs 248 crore as on July 16, 2026, is to be executed over the next 6-18 months. As of October 31, 2026, the order book stood at 220.3 crore (including GST) with a 97.2+ MW pipeline, while H1 FY27 revenue was 138.7 crore.
- IPO proceeds - automated Solar Panel Dry Cleaning System
Missed - The DRHP proposed a 7.20 MW (AC)/9.99 MW (DC) ground-mounted plant including an automated Solar Panel Dry Cleaning System, allocated ₹3,158.31 lakh of IPO proceeds. The company replaced it with manual and semi-mechanised cleaning based on its evaluation of site conditions and sought shareholder approval to reallocate ₹2,06,12,830 to General Corporate Purposes; the automated system was not implemented, though the plant itself was commissioned in May 2026.
- IPO - listing on BSE SME Platform
Delivered - The DRHP proposed the IPO and listing of equity shares on the BSE SME Platform. Equity shares were listed on the BSE SME Platform on January 21, 2026, raising gross proceeds of ₹39.56 crore via a fresh issue of 37,68,000 equity shares at ₹105 per share.
- IPO proceeds utilisation - General Corporate Purposes before 31.03.2027
Pending - In the FY26 Annual Report, the target utilisation timeline for IPO proceeds under General Corporate Purposes was "Before 31.03.2027", with ₹364.50 lakh allocated. A variation revised the allocation to ₹570.63 lakhs, to be utilised on or before 31 March 2027, subject to shareholder approval; as at 31.03.2026, ₹114.38 lakhs of ₹364.50 lakhs (31.38%) was utilised.
- IPO proceeds utilisation - solar plant capex before Q2 FY27
Delivered - In the FY26 Annual Report, the target utilisation timeline for IPO-funded Capital Expenditure (Solar Projects) was "Before Q-2 of 2026-27", with ₹3,260.83 lakhs of Net Proceeds scheduled for the 7.20 MW (AC) / 9.99 MW (DC) plant. Capacity was varied to 7.20 MW (AC) / 9.67 MW (DC) and the solar object revised to ₹2,952.18 lakhs; the Himmatnagar solar project (9,676.80 KWp) was commissioned on 27-05-2026, with ₹1,871.64 lakhs (59.26%) of the solar allocation used as at 31.03.2026 and IPO proceeds at 39.56% utilisation as on September 30, 2026.
- "Others" segment - no significant growth going forward
On track - At the Q2 FY27 call, management said the "others" segment will not see much growth going forward as the company will purely focus on solar, with any growth there only from the US subsidiary's performance. H1 FY27 shows "Others" at 2% of revenue, down from 6% in FY26; no US subsidiary figures are disclosed in our record.
- RESCO funding structure - 25:75 debt-to-equity ratio
On track - At the Q2 FY27 call, management stated RESCO projects will be funded at a 25:75 ratio - 25% of project cost from own funds/accruals and up to 75% via bank/debt finance - with debt increasing as the RESCO portfolio grows. During H1 FY27 the company raised ₹8.50 crore through unsecured loans, enhanced its cash credit limit to ₹5 crore, and secured a ₹2.58 crore term loan for the Rashtrapati Bhavan project; debt stood at ₹18.46 crore with D/E of 0.21 as of 14 Nov 2026.
- Order book conversion - 70-80% of \~220 crore EPC order book in H2 FY27
Pending - At the Q2 FY27 call, the CFO stated management can expect conversion of up to 70-80% of the \~220 crore EPC order book in H2 FY27. The order book stood at 220.3 crore (including GST) as of October 31, 2026, with a 97.2+ MW pipeline and H1 FY27 revenue of 138.7 crore; no H2 FY27 conversion figure is yet available in our record.
- EPC execution - 23 projects / 44,088.50 KWp in FY27
On track - In the Q4 FY26 PPT, the EPC execution track record table listed FY27 with 23 projects and total capacity 44,088.50 KWp, repeated in the Q2 FY27 PPT. As of October 2026, the company reported 20+ ongoing projects, a 197+ MW solar portfolio and 97+ MW under execution; no completed FY27 projects against this target are yet disclosed in our record.
- RESCO cumulative asset portfolio - 15,525 KWp in FY27
On track - In the Q4 FY26 PPT, management projected the RESCO cumulative asset portfolio to reach 15,525 KWp in FY27 (marked "P*"), versus 840 KWp in FY25 and 3,833 KWp in FY26, including subsidiary GRE Green Assets of 2,016 KWp, repeated in the Q2 FY27 PPT. The ground-mount RESCO portfolio reached 12,532.80 KWp with Himmatnagar (9,676.80 KWp) commissioned on 27-05-2026 and Indrap (2,016 KWp) on 30-05-2026, plus 2,993 KWp of rooftop RESCO plants, with RESCO revenue of ₹33 Mn in H1 FY27.