Key Takeaways
- Revenue surged 45.7% YoY, but cash turned negative: Total income hit INR365 crores, yet operations consumed INR70 crores of cash as growth tied up working capital in inventory and EPC project funding.
- Margins compressed in H2, and the reset is the new baseline: EBITDA margin fell from ~15% in H1 to ~12% in H2 on bulk supplies and EPC start-up costs; management expects the 12–13% range to persist.
- A new facility doubles the growth runway: The Dankuni unit (1.18 lakh sq ft) is commissioning now, with management targeting 70–80% utilization by September and a capacity that can 3x–4x within two years.
- EPC entry is a strategic bet, not just a project: The company won a six-laning National Highway contract and is bidding transmission and distribution tenders, leveraging its own cable and conductor manufacturing as a forward-integration advantage.
- What to watch next quarter: Whether the conductor division starts production once power is connected this month, the pace of BIS license approvals for new products, and any improvement in the working capital cycle as EPC bills come due.
Revenue Growth & Order Book
- Broad-based demand drove the top line: Growth came from power transmission, distribution, infrastructure, and industrial sectors, with capacity utilization running at 82.4% (Unit I) and 84.6% (Unit II).
- Order book stands at ~INR500 crores: The typical execution timeline is one and a half years, and management expects the book to reach INR700–800 crores by FY27-end on a conservative basis.
- Large tenders in play with no track record to model: The company has participated in transmission and distribution tenders worth INR1,000+ crores and expects favorable results, but management cautioned that without prior experience in this category, a conversion ratio is impossible to estimate.
- Revenue from order book vs. spot business is not tracked: When asked for the split, management acknowledged the data has not been segregated and offered to task the team with producing it.
Garodia: "Since like if you will see like, transmission and distribution, we have participated in several transmission distribution tenders. So, we didn't have prior experience in participating in this sort of tenders. So, it's quite difficult to tell like conversion ratio."
Capacity Expansion & New Facility
- Dankuni unit adds 1.18 lakh sq ft of industrial space: The acquired facility will house both a conductor division and a cable division, with further land procurement underway beside the site.
- Conductor production is imminent: The conductor facility is already installed and waiting for an electricity connection, expected within this month; the cable division will start in the next two months.
- Phase 1 doubles capacity by September 2026: Management expects the new unit to run at 70–80% utilization by September-end, with revenue potential that can 3x or 4x within two years depending on the order book.
- Capex is modest and flexible: The company plans INR20–30 crores of capex, scaling with order levels, and notes that installing machines is straightforward given the available space.
- New products await BIS licenses: HTLS, AL-59, MVCC, and HT cables have been added to the portfolio, and management will pursue BIS approvals shortly to unlock full-capacity production.
Garodia: "The revenue potential is almost double. And as you can see, we can even 3x, 4x within next two years. It's got a lot of potential."
EPC Segment Entry
- Forward integration into infrastructure EPC: The company branched into civil and electrical work, starting with a six-laning National Highway project under NHDP Phase 5 on the Bihar-Jharkhand border.
- The strategic logic is captive demand: All electrical works require cables and conductors, which JD Cables manufactures, so the EPC arm creates a pull-through channel while bidding transmission and distribution tenders.
- A dedicated team is in place: The EPC division is led by Mr. Rajesh Jhunjhunwala, who brings extensive segment experience.
- Revenue contribution is material and recurring: Management expects a minimum of INR200 crores from EPC in FY27 (conservative) and intends to participate in several other projects, making the segment recurring in nature.
- EPC margins are lower but additive at the PAT line: The segment is expected to deliver around 8% PAT margin, and combined EBITDA margin for the company should remain double-digit in FY27.
- Working capital is the near-term cost: Funding EPC projects over the last 2–3 months tied up cash, with revenues and bills to be deducted at once upon completion; this drove the INR70 crores operating cash deficit in FY26.
Garodia: "EPC is a forward integration for us and it will be quite beneficial in the longer term because all the electrical works require electrification works require cables and conductors. So as you know, we are manufacturing cables and conductors and as I said that we have already participated in several other EPC tenders like transmission and distribution sector. So going forward, it will be a huge advantage for us considering that we ourselves is manufacturing cables and conductors."
Margins & Cash Flow
- H2 margin compression was structural, not seasonal: EBITDA margin fell from ~15% in H1 to ~12% in H2, driven by bulk quantity supplies at thinner pricing and a surge in other expenses from INR4 crores to INR24 crores as the EPC segment incurred start-up costs with bills still pending.
- Management expects the 12–13% range to hold: The margin outlook for FY27 is for similar levels, with combined EBITDA staying double-digit.
- New products promise better unit economics: Management expects double-digit margins from newer products like HTLS and MVCC, and says they will be better than existing product margins, though exact figures will only be known once execution begins.
- Cash flow turned negative on growth: A company growing 50–60% will see debtor and inventory days rise, and with payables already stretched, there was no lever to offset the working capital build.
- Debt funding is lined up but not yet drawn: The company has applied to banks and they are ready to lend for working capital and new orders; management says current cash and bank balances remain sufficient.
- Management did not commit to cash flow improvement in FY27: When asked directly whether the ~INR70 crores cash deficit would reverse, the response pivoted to debt availability rather than addressing the working capital cycle.
Regional & Policy Tailwinds
- West Bengal is seen as a coming opportunity: Management cited the recent change in state government, a pipeline of infrastructure projects, and regular contact with government officers as reasons to expect good business and investment in the state.
- Cabinet expansion is a near-term catalyst: A Power Minister is expected to be appointed next week, and the government has already sanctioned numerous projects.
Garodia: "As you know, the government has been changed and we are expecting good business and good investment in West Bengal. Already like there are lots of, we have heard lots of investments and lots of infrastructure development will be happening in West Bengal, and lots of projects are in pipeline as we are in regular context with the officers. And yes, West Bengal will definitely be a good opportunity for us."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 50–60% overall revenue growth in FY27 | FY27 |
| Cables & conductor growth | 30–40% increment in cables and conductor segment | FY27 |
| EPC revenue | Minimum INR200 crores from EPC (conservative) | FY27 |
| Order book | INR700–800 crores (conservative) | FY27-end |
| New facility utilization | 70–80% capacity utilization at Dankuni unit | By September-end |
| Conductor division start | Electricity connection expected, production begins | Within this month |
| Cable division start | Production begins at new unit | Within two months |
| Capacity expansion | Double capacity in Phase 1; 3x–4x potential | Phase 1 by September 2026; 3x–4x within two years |
| Combined EBITDA margin | Double-digit | FY27 |
| EPC PAT margin | Around 8% | FY27 |
| Capex | INR20–30 crores, order-book dependent | FY27 |
| BIS licenses for new products | Approvals sought for HTLS, AL59, MVCC, HT cables | "Very shortly" |
Key Metrics
| Metric | FY26 |
|---|---|
| Total income | ₹365 cr, +45.67% YoY |
| EBITDA | ₹48.11 cr, +40% YoY |
| PAT | ₹31.72 cr, +44% YoY |
| H2 FY26 total income | ₹243 cr, +70% vs H2 FY25 |
| H2 FY26 EBITDA | ₹28 cr, +52% vs H2 FY25 |
| H2 FY26 PAT | ₹19 cr, +69% vs H2 FY25 |
| EBITDA margin | ~12–13%, similar to FY25; management expects similar levels going forward |
| Revenue growth guidance (FY27) | 50–60%, minimum expected |
| Order book | ~₹515 cr as of Mar 31, 2026; ~₹300 cr EPC, ~₹200 cr cables and conductors |
| Order book target (Mar 31, 2027) | ₹700–800 cr, conservative estimate |
| Tenders participated | >₹1,000 cr, comprising EPC and cable tenders |
| Installed capacity | 28,000 km per annum; Unit I 6,000 km, Unit II 22,000 km |
| Capacity utilization | 82.4% at Unit I, 84.6% at Unit II |
| FY26 EPC revenue | ₹30 cr |
| FY27 EPC revenue expectation | ≥₹200 cr, conservative |
| EPC PAT margin | ~8% |
| Capex plan (FY27) | ₹20–30 cr |
| New Jamshedpur facility | 1.18 lakh sq ft |
| FY26 operating cash flow | -₹74 cr |
| Current debt | ~₹55 cr |