Shree Refrigerations Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/vh2672vyd00msexcy1ux2v7j.pdf

Key Takeaways


The H1-to-H2 Swing: Why the Year Looked Lopsided

CMDE Sunil Kaushik: "In our line of business, it might indicate incorrect conclusions to you. So for somebody in our line of business, in the defence ecosystem, a half yearly or actually even an annual reporting is more accurate than a quarterly reporting."

The Defence Moat: Certification, Capacity and Market Share

Abhijit Saoji: "Once you test that product, as per the naval or defence grade, when the order gets repeated for that product for any other ship, we don't have to do the type testing again."

Data Centre Cooling: Capability Build Before Revenue

CMDE. Sunil Kaushik: "Whatever the technology for data centre cooling is... you always need a chiller to chill either the air or the secondary coolant. So you are always going to have an opportunity in the chiller market."

Margins: Operating Leverage, Mix and Inflation

Abhijit Saoji: "Metal inflation is affecting everyone. There is no question about it. Whether it is copper, every single metal inflation. And it will also impact us, but not as badly as it is probably impacting others."

The INR1,000 Crore Target and the CAGR Question

Abhijit Saoji: "If you grow it by exactly 40%, you will end up in doing INR833 crore. But that doesn't work in business, sir. So, as a management of this company, we definitely are standing by our word. INR1,000 crore is the ladder which we are here in next 5 years and it will happen, sir."

Guidance & Commitments

CommitmentSpecificsTimeline
Revenue CAGR40% CAGR, excluding data centre contribution3–5 years
Revenue targetINR1,000 crores revenue, INR120–130 crores PATFY30–31
EBITDA margin20–24% range, commodity inflation consideredOngoing
Spares and service mixLift to 15–20% of total revenue to structurally improve marginsNo date; "continuously working"
Data centre revenueReference installation only in FY27; major revenue from FY28FY28 onward
New facility50,000 sq ft expansion begins commercial production; leased unit closesJune FY27
Project completions4 of 8 ongoing defence projects completedFY27
Working capitalImprovement to continue from 370 daysNo target given
Main board listingMove to BSE/NSE main board when regulatory window opensAt least 2 years

Key Metrics

MetricFY26
Revenue₹153 cr, +50%+ YoY
H2 revenue₹100 cr, +100% YoY and HoH
EBITDA margin21% (blended FY26), vs 27% in FY25; H2 at 26.3%
PAT₹21 cr, +64% YoY
PAT margin14% (blended FY26), vs 13% in FY25
EPS₹6.47, +28% YoY
Revenue CAGR (4-year)45%
PAT CAGR (4-year)85%
Order book₹270 cr, 1.8x FY26 revenue
Market share (defence marine HVAC)64%
Spares & service revenue share7% of total revenue, vs 30% in FY25
Net working capital cycle370 days, improved from 570 days
Receivable days250 days, improved from 350 days
Inventory days230 days, improved from 250 days
Net worth₹219 cr, up from ₹118 cr
Employee cost₹21 cr, up from ₹7 cr four years ago
Revenue growth guidance40% CAGR for next 3–5 years
EBITDA margin guidance20%–24% going forward
Peak revenue from existing infrastructureUp to ₹400 cr
Defence marine TAM (next 2–2.5 years)₹2,500 cr (defence) + ₹500 cr (non-defence marine)
Data centre cooling market (India)₹299 cr currently, expected to reach ~₹900 cr in 3 years, growing at 25%–30% CAGR
CapEx (Hanbarwadi Phase 1)₹25 cr, plant operational from June 2026
Manufacturing facility70,000 sq ft (80,000 sq ft after lease closure), expandable by another 50,000 sq ft