Shri Keshav Cements & Infra Ltd Q2 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/23pj9hko6pfn1ynj03nzgxui.pdf

Key Takeaways


The Cement Problem: Why Modernization Is Non-Negotiable

Management: "In this particular quarter, out of EBITDA of around INR 8.96 crores, almost INR 8 crores is contributed by solar itself. So cement, I would say, unless we fix the operational efficiency issues given the capacity utilization also will remain a little restricted."

The Modernization Plan: Scope, Cost & Timeline

Venkatesh Katwa: "Typically, we are able to execute this project in around between \$25 to \$30 per metric ton, as compared to industry standard of around \$150. This is again mainly because of the fact that we don't have to purchase new land. There's no additional grinding equipment or raw material grinding equipment required."

Solar: The Cash Flow Engine

Management: "We have solar to back it up, which no one can take away from us. In fact, when you send up a solar plant in 2018, the cost of production was around INR 4 because of interest and O&M costs. Today, the cost of production is less than INR 2.5, and that will continue to keep going down. So I'm pretty certain that EBITDA margin only because we have a solar plant, we will not only continue, we expect to improve it further."

Demand & Market Position

Management: "Typically, what is being a prohibitive factor for us right now is being still a very small capacity, our reach is not happening beyond a certain geographical area because in the limitations of our margins on the cement, logistic cost to be heavy cost on the cement because cement is a product with a very low weight rate ratio, which means that you need to have a sufficient EBITDA margins to push it further on geographical location."

Financial Position & Fundraising


Post-Expansion Financial Picture

Management: "No, my CMI data shows it is going well above 40% to 43%. But I would not like to stick to that figure because two years done I don't see what -- I don't know what is going to be the power cost or I don't know what is going to be the fuel cost."

Guidance & Commitments

CommitmentSpecificsTimeline
Modernization groundbreakingMajor civil work to startQ4 FY23 (Jan/Feb)
Modernization completionFirst brick to first bag: 14–15 months from start; entire capacity in handBy March 2024 (FY24 end)
Cement EBITDA/ton post-expansionImprove from ~INR 300 to at least over INR 1,000On project completion
Post-expansion capacity utilization target~90%After modernization, serving larger markets
Post-expansion gross sales at 80–85% utilization~INR 550 crores gross, ~INR 450 crores netPost-expansion ramp-up
Post-expansion EBITDA at 80% utilizationINR 120+ crores, assuming current power/fuel costs holdPost-expansion ramp-up
Additional outside debt for capexINR 70–75 crores, taking total outside debt to ~INR 226 croresDuring expansion phase
Debt prepaymentNo prepayment for at least one year; per existing schedule (~INR 20 crore/year) until thenUntil expansion complete
Solar EBITDA run-rateINR 7–8 crores per quarter (~INR 28–30 crores annualized)Ongoing, no significant changes expected
Income tax cash outflowMAT only (~INR 90 lakhs/quarter); no regular income taxNext 4–5 years
Cement H2 EBITDA/tonQ2 levels expected to continue, with full coal-to-petcoke shift adding supportH2 FY23

Key Metrics

MetricQ2 FY23
Revenue₹24.84 cr, up 4.84% vs preceding-year quarter
EBITDA₹8.96 cr, up nearly 24%
EBITDA margin36.07%, higher by over 540 bps
Profit after tax₹1.16 cr, after deferred tax liability of ~₹84 cr
Finance costsdown ~15%, on continuous repayment schedule
H1 FY23 revenue₹58 cr, vs ~₹50 cr in H1 FY22
H1 FY23 PAT₹27.61 cr
H1 FY23 solar revenue₹10.44 cr, up over 300% from ₹3.54 cr in H1 FY22
Solar revenue share of H1 revenue18%, vs 7% in H1 FY22
Cement volume~46,000 tons
H1 FY23 cement volume~105,850 tons
Cement EBITDA₹1.5 cr, vs ₹92.44 lakhs in Q1
Cement EBITDA per ton₹326, vs ₹184 in Q1
Solar EBITDA₹7.46 cr, vs ₹8.44 cr in Q1
Average solar realisation₹6.92 per unit, vs ₹6.66 in Q1 and ₹6.28 in FY20
Solar generation1.12 cr units, captive consumption 46 lakh units
Outside debt₹156.9 cr as of Sep 30, 2022, down from ₹199 cr to ₹169 cr earlier
Modernisation project cost~₹121 cr, ~$26 per ton
Post-capex gross sales target~₹550 cr at 80–85% utilisation
Post-capex EBITDA expectation₹120+ cr on ~₹400 cr sales, assuming current costs and 80% utilisation