Solarium Green Energy Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/jgmdxnpb1mh4lyqvpbochx6u.pdf

Key Takeaways


Module Manufacturing: The Big Bet

Ankit Garg: "we have not estimated the cost advantage till now. But the supply advantage will be very big for us."

The Defense Receivables Shock

Himanshu Garg: "both the agencies were stuck from somewhere about May to almost like August because of Operation Sindoor. We experienced the India-Pakistan war there. So most of the people were not reachable during that time."

EPC & Execution: The Core Engine


Residential & Channel Expansion

Himanshu Garg: "But in actual, nobody is doing the rooftop, including Tata. So, they are only supplying the products. Nobody is there in terms of executing. There are very, very few organized players who are there doing the execution part."

Distribution & Working Capital Dynamics

Himanshu Garg: "This is not the first time the module industry is seeing such sort of volatility."

Guidance & Commitments

CommitmentSpecificsTimeline
Module plant commissioningMachines arrive mid-December; trial runs 15-20 days; fully operationalMid-January to end of January
Module plant utilization40-50% initial, ramping to 75-80%75% within Q1 FY27
Module plant standalone EBITDA margin12% to 13%At steady-state utilization
Module plant revenue potentialINR1,000 crores+At 85% utilization
Captive module consumption40-50% of output consumed in-houseFirst 6-9 months post-commissioning
B2B module sales revenueRevenue to appear in financialsQ4 FY26
Defense receivables clearanceFull clearance of delayed defense-linked receivablesBy December
Finance cost normalizationElevated finance costs to settleWithin Q3 FY26
Unexecuted order book executionMajority of backlog executedWithin this fiscal year; spillover by Q1 next year
IPO working capital deploymentIPO proceeds deployed into working capitalQ4 FY26, once plant is operational

Key Metrics

MetricQ2 FY26
Revenue43% YoY increase in H1 FY26
Gross margin65% rise in H1 FY26
EBITDA36% improvement in H1 FY26
Profit after tax22% expansion in H1 FY26
Employee cost~80% YoY increase in H1 FY26; flat from H2 FY25 to H1 FY26
Finance costDoubled YoY, driven by delayed defense-linked receivables; expected to normalize as INR20–25 cr recovered Oct–Dec
Residential segment revenue share32% of H1 FY26 revenue
Government segment revenue share36% of H1 FY26 revenue
Distribution sales revenue share~70% of revenue split
Unexecuted order bookINR229 cr as of H1 FY26
L1 ordersINR209 cr
Bidding pipelineOver INR900 cr
Residential channel partners onboarded~450 new partners via Solarium Saarthi Initiative in H1 FY26
Residential footprint expansion25 additional cities in H1 FY26
Structure manufacturing cost advantage4–5% on structure cost, adding 0.3–0.5% to EPC margins
Module manufacturing plant capacity1,000 MW automated plant in Ahmedabad, commissioning mid-Jan to end-Jan 2026
Module plant standalone EBITDA margin target12–13%
Module plant initial utilization40–50% for first couple of months, targeting 75% within Q1 FY27
Module plant revenue potential at 85% utilizationINR1,000 cr+ as a standalone unit
Gross margin improvement from captive module consumption5–7% improvement foreseen
Working capital required for manufacturing plantINR80–100 cr; Q4 FY26 requirement of INR60–70 cr
Win ratio (by number of orders)25–30%