Sugs Lloyd Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/pk7q0av9q6hvjyiqfab3y4rj.pdf

Key Takeaways


The Growth Engine: RDSS Execution & Order Book Transformation

Santosh Shah: "We are building Sugs Lloyd to last for generations and every decision we take is guided by that long-term vision."

Margin & Cash Flow Mechanics

Santosh Shah: "To become cash positive, only thing we have to do is we have to reduce the growth speed. So I don't think anyone would like or anyone would suggest us to do so."

New Business Lines: Products, SCADA & Transmission


Balance Sheet & Funding Strategy

Santosh Shah: "Dilution of equity, further dilution, it is not on the right now. We do not have any plans for any further dilution as on date."

Competitive Position & Sector Tailwinds


Guidance & Commitments

CommitmentSpecificsTimeline
Full-year EBITDA marginRemain around 15%FY27
Revenue directionBuilding towards INR1,000 croresFY28
Order book targetAround INR2,000 crores after executionFY27 exit
Product revenue contributionReach ~10% of total revenueFY28
SCADA technology partnershipArrangement with a technology company expected to be finalisedBetween now and H1 FY28
Patna project completionFull execution deliveredMarch 2028
Amritsar solar plant completionScheduled for completionDecember 2026
Punjab RDSS completionDelivered over 15 monthsFrom Q2 FY27
Debt trajectoryINR230–240 crores at FY27 exit, ~INR300 crores at FY28 exit; debt-to-equity ~1.3x at FY27 exitFY27–FY28
Transmission billing startFirst billing from transmission projectsH2 FY27
VCB billing startFirst billing from vacuum circuit breakersFY28

Key Metrics

MetricQ2 FY27
Revenue₹134.91 cr, up 12% YoY and 72% QoQ
EBITDA₹19.1 cr, up 91% YoY and 59% QoQ
EBITDA margin14.1% (per an analyst's math), vs 15.3% in Q1
Profit after tax₹12.51 cr, up 108% YoY and 67% QoQ
H1 FY27 revenue₹213.31 cr, up 73% YoY; 71% of full-year FY26 revenue already delivered
H1 FY27 EBITDA₹31 cr, up 64% YoY; margin of 14.5%
H1 FY27 PAT₹20.01 cr, up 69% YoY
H1 FY27 EPS₹8.62, vs ₹6.86 a year ago
H1 interest cover5.2x, improved from 4.8x a year ago
H1 finance costs2.8% of revenue, down from 3.2% a year ago
Order book₹1,067 cr as of 30th September, ~3.5x last year's revenue
Q2 new orders7 orders worth ₹395 cr excluding GST, ₹466 cr including GST
Bihar share of order book~55%, down from ~82% at end of July
Receivable days (trailing 12-month)~150 days in September, improved from ~179 in June and ~193 in March
H1 operating cash outflow₹12 cr, vs ₹37 cr for full year FY26
DebtClose to ₹160 cr (per an analyst's math)
Debt-to-equity ratio1.2x to 1.3x maintained
Tenders at final evaluation stage₹1,260 cr (₹800 cr power T&D, ₹400 cr solar and storage, ₹60 cr products)
Tenders selected for bidding₹6,600 cr
Power T&D and smart grid revenue share~80% of H1 revenue
Collections since quarter close~₹50 cr