Waaree Renewable Technologies Ltd Q3 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/lyiklhc12zxdbuhhdtfi6jf9.pdf

Key Takeaways


Margin Philosophy & Q3 Outperformance

Panjwani: "We better surprise ourselves rather than be not cautious. So we have always maintained that we should be under 15%. We are better than 15% is good for us."

Order Book & Execution Dynamics

Panjwani: "All EPC companies will continue to guide according to their, and it will always be a moving goal post because new orders keeps entering."

Data Center EPC: The New Adjacency

Panjwani: "There are synergies. Data centers, you build EPC solar-generating power projects, now we will build data centers also, another EPC model. And also coupled with data centers have a lot of energy consumption."

Pipeline & Adjacent Bets


Guidance & Commitments

CommitmentSpecificsTimeline
Q4 FY25 execution volume500 to 600 MWJanuary to March 2025
Q4 FY25 revenueAround INR500–600 crores (at ~INR1 crore per MW)Q4 FY25
Medium-term marginMaintain 15% levelMedium term
Annual execution capacity3 to 3.5 GWAnnual run-rate
O&M base growth2x to 3x from current 587 MWFrom April onwards
Jindal 2 GW order executionRoughly 8 or 9 monthsFrom order start
DebtNo funded debt unless capex is monetizedOngoing
Green hydrogen EPC biddingWill bid as use cases come upUndated

Key Metrics

MetricQ3 FY25
Revenue₹360.35 cr, vs ₹324.19 cr in Q3 FY24
9M FY25 revenue₹1,121.17 cr, +85.87% YoY
EBITDA₹71.92 cr
EBITDA margin19.96%, vs 16.50% for 9M FY25; management maintains medium-term guidance of ~15%
PAT₹53.48 cr
9M FY25 PAT₹135.16 cr, +43.94% YoY
EPC execution319 MWp in Q3; 488 MWp in Q2 FY25; 1 GWp in 9M FY25
Unexecuted order book3.4 GWp as of 9M FY25
Q4 FY25 execution expectation500–600 MWp (management's internal goalpost)
Annual execution capacity3–3.5 GWp
Cash position₹200–220 cr
Debt outstanding~₹28 cr (one loan)
Non-fund-based limits~₹1,400 cr from banks, with 75–80% utilization; plus ~₹300 cr from insurance companies
O&M portfolio587 MWp currently; expected to grow 2x–3x from April 2025 as projects go live in March
Pipeline24 GWp