Key Takeaways
- Revenue nearly doubled, mix shift drove margins: H1 FY27 revenue grew 95% YoY to ₹194.5 crores, with high-value RIP bushings contributing 86% of value on just 40% of volume, lifting gross margins to 48.3% from 42.4%.
- Order book tripled, giving 15–20 month visibility: The order book swelled to ₹760 crores from ₹400 crores at the start of FY27, expected to execute over the next 15–20 months, with new orders still flowing.
- Capacity expansion is now live and invoicing: The greenfield Jarod facility has begun commercial production for assembly and testing, with localized RIP core type-testing imminent; brownfield expansion completes in Q3 FY27.
- Export groundwork laid, payoff still 12–18 months away: US representation agreements now cover ~27 states, a global agent network spans ~30 countries, and 420 kV orders are already in hand, but management expects export order booking to begin only from mid-FY28.
- What to watch next quarter: Whether localized RIP bushings pass type testing and secure customer approvals, the pace of Jarod’s assembly ramp in H2, and any margin impact from the full depreciation load now kicking in.
Demand & Order Book
- Demand is a seller’s market: Management sees demand increasing day-by-day, with no sign of data-center or renewable orders stalling; the next 2–4 years are expected to remain a seller’s market for niche component players like Yash.
- Order book nearly doubled in six months: The ₹760 crores order book spans all customer types in India and abroad, with unexecuted 420 kV orders already received and invoicing to start this year via the assembly model.
- Lead times are stretching: Yash’s own lead times are increasing day-by-day, though they remain far shorter than what US customers face locally; OIP export orders carry timelines spread between 6 and 15 months.
- Chinese competition is a non-issue: Chinese component suppliers occasionally turn aggressive on pricing for a quarter or two, but the impact on component players has been negligible compared to capital equipment manufacturers.
- End-use mix is tilting toward renewables and data centers: An increasing number of bushings are going into transformers for renewable and data-center applications, though transmission still dominates the majority.
Keyur Shah: “I only see that the demand is increasing day by day, right?”
Capacity Expansion & Localization
- Jarod greenfield is invoicing: Commercial production has started for the assembly model; assembly and testing departments are already resolving bottlenecks from the existing Halol facility, which is running three shifts at close to 90% utilization.
- Localized RIP core near type-testing: Initial results of the localized core are “very, very, very encouraging”; bushings are expected to be sent for type test and external lab validation in the next couple of weeks.
- Brownfield expansion on track for Q3: Completion is expected in Q3 FY27, with increased capacity flowing in Q4 FY27; management hopes to improve lead times once this comes online.
- Customer approvals in progress: Files have been submitted to the majority of customers for new-unit approval; Yash has already started supplying customers who had no restriction on new-unit supplies.
- Core sourcing will stay hybrid: Imports will continue for a while because Yash’s own capacity will not be sufficient to meet increasing demand; a combination of local and imported cores will be maintained for the next couple of years.
- Higher-voltage timeline set: Localized RIP bushings up to 245 kV enter commercial production from Q4 FY27; 420 kV and 550 kV localized manufacturing is targeted for Q4 FY28 or mid-FY28 at the latest.
Keyur Shah: “The initial results of our localized core have been very, very, very encouraging. And we are just keeping our fingers crossed that in next couple of weeks we should be able to send the bushings for type test with satisfactory result...”
Margins & Profitability
- Gross margin jumped 590 bps: Rose to 48.3% from 42.4% YoY, driven by product mix, operating leverage on ~40% volume growth, better price realization, and cost efficiency measures.
- EBITDA margin expanded 480 bps: Improved to 28.1% from 23.3% YoY; PAT rose 157% YoY to ₹36 crores with PAT margin improving from 13.7% to 18.6%.
- Depreciation load shifts to H2: H1 depreciation rose to ₹4.4 crores from ₹2.6 crores because the bulk of new investment was put to use only in September; the full impact will flow into H2. Management still aims to maintain PAT margin at last year’s level despite depreciation being 2.5x–3x higher.
- Localization margin upside is real but unquantified: Import duty and freight (18–20% of cost) goes away plus overhead differences; management expects profit margin to expand substantially but will not commit a number until full production is achieved.
- Pricing power is durable: Management sees no reason for excess capacity or a price bloodbath in bushings for at least 5–6 years, citing reasonable entry barriers and a seller’s market; margins can be maintained or made a bit better year-on-year.
- Philosophy is margin discipline, not maximization: Management targets 25–27% EBITDA as good business and is willing to pass some localization benefit to customers to stay competitive and maintain long-term relationships.
Keyur Shah: “At the end of the day, I should not be exploiting the customer, I should be able to maintain relations for long. And if you are able to do a good business with 25%, 26%, 27% EBITDA, its good business, right?”
Export Strategy & US Entry
- US representation agreements now cover ~27 states: Subsidiary Yash HV USA entered into agreements with Ensales Electrical Associates, Gateway Power Sales, and EHV Solutions LLC, concluded a couple of weeks back; actual results are expected after a couple of months.
- Strategy shift from opportunistic to permanent: Management acknowledged that past export business came from demand-supply gaps; the agreements are designed to secure permanent approvals with US utilities and end users, moving beyond spot business.
- Global agent network spans ~30 countries: Agents are now present in close to 30 countries to deepen Yash’s presence worldwide.
- Export order booking still 12–18 months out: RIP capacity is expected to be ready to address the export market by mid-FY28; export order booking is expected to start from mid-next year, changing the landscape from FY28–FY29.
- Export pricing is structurally better: Management confirmed that profit margins and realization are better in export markets, similar to other manufacturers; a combination of export and domestic business is beneficial.
- Seismic qualification unlocks US utilities: Yash became the first Indian OEM and one of a select group of global OEMs to complete stringent seismic qualification testing for IEEE-compliant 138 and 230 kV OIP condenser transformer bushings.
Keyur Shah: “Certain times when the business comes to you, it is because of it's a demand and there is a less supply. In that context, you get business, but if you want to bolster the position permanently, then you need to get inroads deeper into the end customer and the OEM.”
Product & Technology Milestones
- RIP bushings dominate value: RIP contributed 86% of revenue by value while volume share was close to 40%, indicating higher-voltage, higher-value bushings are driving value growth disproportionately.
- 245 kV wall-through bushing shipped: Successfully tested the first 245 kV wall-through transformer bushing in-house and supplied it to a leading PSU.
- 420 kV orders already in hand: Unexecuted orders for 420 kV bushings have been received; invoicing will start this year via the assembly model, while localized production for 420 kV and 550 kV is expected by Q4 of '28 or mid-28 max.
- Retrofit and services doubled: Contribution rose from 4% to 8% of domestic sales YoY.
- SAP S/4HANA migration completed: Successfully migrated globally while maintaining business continuity.
- Sukrut JV turned profitable: Acquired nine months ago when it was in loss; now brought to profits through active involvement of Yash and Quality Power with a professionally driven organization.
Balance Sheet & Cash Flow
- Cash conversion cycle improved sharply: Fell to 63 days from 81 days in full-year FY26, driven by focused and tighter controls on business operations.
- Receivables in line with revenue: Absolute receivables nearly doubled but collection days remained stable at 47 days (H1 FY27) vs. 47 days (H1 FY26); management is comfortable at ~45 days.
- Vendor advances rose to secure supply: Increase in non-current and other current assets from ₹11 crores to ₹40 crores was driven by advance payments to international core suppliers to secure production slots.
- Preferential allotment closed: Completed allotment of equity shares and warrants aggregating ~₹151 crores from investors including Malabar Investment, WhiteOak, Motilal Oswal, ValueQuest, and Anantroop; ₹106 crores received.
- Balance capex to deploy over 12 months: Of the ₹220 crores greenfield project, ₹106 crores has been spent; the balance will be deployed over the next 12 months.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Order book execution | ₹760 crores existing order book to be executed | Next 15–18 months |
| Brownfield expansion completion | Increased capacity available | Q3 FY27 complete; Q4 FY27 output |
| Localized RIP type testing | Bushings sent for external lab validation | Next couple of weeks |
| Localized RIP commercial production (up to 245 kV) | Commercial production should happen | Q4 FY27 |
| Localized RIP 420 kV and 550 kV | Manufacturing capability ready | Q4 of '28 or mid-28 |
| Export order booking start | RIP capacity ready for export market | Mid-FY28 |
| PAT margin | Maintain at last year’s level despite depreciation close to 2.5x–3x of last year | FY27 |
| Revenue capacity peak | ₹1,000 crores from expanded facilities | FY30–FY31 |
| Global market share | At least 5% | Next 4–5 years |
| Balance greenfield capex deployment | Remaining ~₹114 crores deployed | Next 12 months |
Key Metrics
| Metric | H1 FY27 |
|---|---|
| Revenue from operations | ₹194.5 cr, +95% YoY |
| Gross margin | 48.3%, vs 42.4% in H1 FY26 |
| EBITDA | ₹55 cr, +139% YoY |
| EBITDA margin | 28.1%, vs 23.3% in H1 FY26 |
| PAT | ₹36 cr, +157% YoY |
| PAT margin | 18.6%, vs 13.7% in H1 FY26 |
| Order book | ₹760 cr, up from ₹400 cr at start of FY27; execution over 15–18 months |
| Domestic revenue share | 95% of sales; exports 5% |
| RIP bushing revenue share | 86% of revenue; OIP and high-current 14% |
| Retrofit and services share | 8% of domestic sales, doubled from 4% YoY |
| Bushing volume sold | ~4,000 units, +40% YoY (H1 FY26: 2,950) |
| Cash conversion cycle | 63 days, improved from 81 days in FY26 |
| Net cash position | ₹95 cr as on 30 Sep 2026 |
| Greenfield capex spent | ₹106 cr of ₹220 cr planned; balance over next 12 months |
| Capacity utilization (Halol) | ~90% in H1 |
| Global market share | ~1% to 1.2%; aspiration to reach 5% in 4–5 years |
| Export order book | ₹40–50 cr, 5–7% of total order book |
| Preferential allotment proceeds received | ~₹106 cr (₹90.99 cr equity + ₹15 cr warrants upfront) |
| Depreciation | ₹4.4 cr in H1, up from ₹2.6 cr in H1 FY26; full year expected 2.5x–3x of FY26 |
| Receivable days | 47 days, vs 47 days in H1 FY26 and 45 days in FY26 |
| Import duty and freight cost | 18–20% of cost today |
| Combined revenue potential (Unit 1 + 2) | ₹900–1,000 cr, full utilization expected by 2030–31 |