Key Takeaways
- A reset quarter, owned by management: Cost per tonne stayed at the ₹4,500 peak instead of falling, and the company explicitly admitted it has not delivered what it promised. The response is a sharp pivot to cost delivery and capital discipline.
- Cost reduction is now the central promise: Management committed to a ₹250/t reduction in FY27 (to ₹4,250 full-year average) and another ₹250/t the following year, calling it the minimum and 100% controllable.
- Acquired assets are the drag and the opportunity: Penna and Sanghi drove breakdowns, higher repairs, and heat consumption gaps; normalized EBITDA ex-acquisitions is ₹70–80/t higher. Turnaround is the primary cost lever.
- Capex is being paused and re-sequenced: FY27 capex guided at ₹6,000–7,000 crore, but new project starts are frozen until in-hand projects finish and cost delivery improves. The long-term capacity timeline is explicitly pushed out.
- What to watch next quarter: Whether Q1 cost actually holds flat at ₹4,500 as guided, any early signs of the ₹250/t reduction, and whether the April–May demand softness persists into the monsoon.
Cost Reset: The Core Story
- Peak cost, flat quarter: Total cost per tonne was ~₹4,500 in both the December and March quarters, missing the planned March exit of ~₹4,100. Management now calls ₹4,500 the peak and expects a progressive decline from here.
- Why costs stayed high: Higher freight from increased sale lead, an additional goods tax in Himachal, packing cost disruptions from the West Asia war in March, higher heat consumption especially at acquired assets, and elevated branding spend as the company pushed trade sales starting Q4.
- Acquired asset underperformance: Penna needed more maintenance capex and upkeep time than expected; Sanghi and Penna both suffered machine breakdowns that raised repairs and maintenance costs. Technical KPIs including fuel consumption deteriorated without the right fuel blend.
- Fixed cost divergence vs peers: Employee and other fixed costs rose significantly YoY, driven by branding and advertisement to promote trade and premium sales, higher R&M including breakdowns, and additional logistics and handling costs from selling more premium cement.
- The ₹250/t commitment: Management targets a ₹250/t reduction in FY27 (to a ₹4,250 full-year average) and another ₹250/t in FY28, calling this the minimum. The earlier ₹3,650/t ambition is not abandoned but deferred; only ₹500 over two years is committed now.
- Q1 FY27 cost expected flat: Cost is guided to stay at ~₹4,500 in Q1 FY27 before the reduction journey begins through the year, as headwinds including the ₹25/t cost inflation carry forward.
- Raw material savings pending: Fly ash cost improvement is available but waiting on railway infrastructure that will be completed in coming months. Green energy cost improvements are also part of the ₹150–200 savings conviction.
Karan Adani: "I think why the reset, I mean, it's quite evident our performance has not been great. We've not been able to deliver what we have promised to our shareholders."
Acquired Assets & Operational Turnaround
- Penna and Sanghi drag: EBITDA of Ambuja and ACC excluding acquired assets is higher by ₹70–80/t; normalized consolidated EBITDA would be at least ₹800/t. Acquired assets are still not performing in the desired range.
- Utilization target: Management aims to increase utilization at Penna and Sanghi (combined 1.9 crore tonnes capacity) by at least 5% to 10% in FY27.
- Breakdowns concentrated in acquisitions: Major breakdowns occurred predominantly in Penna and Sanghi. Higher R&M costs this year are partly because repairs that should have been done earlier were deferred, leading to subsequent failures.
- Sanghi ramp-up model: The base case for Sanghi utilization does not depend on the Naliya railway line; it relies on marine infrastructure (7 vessels ordered, delivery starting next year) and road movement. The railway line is an add-on, not a prerequisite.
- Sanghi strategic shift: Over the next 3 years, Sanghi will move predominantly into clinker production, with new capacities coming up on the coastal region of Gujarat.
- SLA-based contracts: The company is deploying SLA-based partners at some plants to resolve legacy union issues and improve cost and efficiency, citing competent partners in India who can run plants at target efficiency levels.
- Recalibration of capacity locations: Integrated units have high logistics costs because distance traveled is too high. The company is shutting down grinding units in some places and relocating them closer to markets, particularly in North UP, Bihar, Southern Gujarat, and Maharashtra.
Demand, Pricing & Volume
- Volume growth muted: Q4 volumes grew ~10% YoY but were flattish adjusting for the Orient Cement acquisition. FY27 consolidated volume growth is guided at ~8% to ~8 crore tonnes, with a focus on value over volume through trade sales and premium cement.
- Pricing under pressure: Realization was sustained at ₹254/bag, up only ~₹1 QoQ, while peers improved 1.5% to 2%. Industry is unable to pass on cost increases despite cost escalation of at least ₹25/t.
- Demand softening: April and May demand is subdued and soft. Management would be happy even if the industry captures half of any attempted price hike. Industry growth expectation is ~5% for FY27.
- Premiumization as margin defense: Premium cement reached 36% of trade sales in Q4. The gap between base and premium cement is ₹20–25/t for premium and ₹50–55/t for super-premium. Management sees this journey as just beginning, with differentiated benefits expected in subsequent quarters.
- Utilization expectation: 70–75% ballpark utilization for FY27; if positive demand surprises materialize, the number will look better.
Vinod Bahety: "Despite the circumstances of costs gone up, unfortunately, industry is still under the relentless pressure and not able to pass on the price."
Capital Allocation & Capex Discipline
- Capex paused and corrected: Management admitted capex execution has not been up to mark, citing wrong contractor selection, starting projects without a fully built team post-acquisition, and beginning projects before completing full engineering. New project starts are frozen until in-hand projects finish.
- FY27 capex envelope: ₹6,000–6,500 crore guided, with a possible range up to ₹7,000 crore annually for the next two years. First priority is commissioning the ongoing 1 crore tonnes of grinding units (Salai Banwa, Warisaliganj, etc.).
- Long-term capacity timeline pushed out: The capacity target is not abandoned, but the timeline is explicitly moved out, possibly to FY30 from FY28. Primary focus remains organic growth.
- New clinker projects: A 0.2 crore tonne clinker line at Mundra and another 0.2 crore tonne clinker plant in Assam (linked to a newly won limestone block) are in the pipeline, targeting 24–28 months for completion.
- Capital discipline logic: Until cost delivery improves, further capital investment does not make sense because returns on capital invested are not being achieved. 80% of the improvement plan is tied to cost reduction.
- Inorganic opportunities: The company keeps evaluating but the number one priority right now is organic development and greenfield expansion.
Karan Adani: "Until the time we are not able to deliver on what we are promising, I don't think so it makes sense to make more capital investment because you don't get the returns on those capital invested as well."
Structural & Strategic Updates
- One Cement platform launched: A strategic initiative to bring sharper focus on operational performance, business synergies, and higher compliance across the group's cement entities.
- Amalgamation progress: Sanghi Industries and Penna Cement amalgamation with Ambuja Cements is complete; ACC and Orient Cement are under process. Purchase price allocation for Orient and Penna is now finalized, with marginal balance sheet and P&L changes.
- Working capital: Ambuja's working capital improved in the March quarter vs December, with higher inventory and receivables under good control due to higher trade sales. ACC has a receivable from Ambuja under an MSA; shareholder approval is taken for an ICD that will knock off the receivable, resolving the negative operating cash flow appearance.
- Government incentives: Lower government incentives booked due to GST rates coming down, some plants exhausting incentives, and a shift to accruing only on a virtual visibility or certainty basis to avoid pending long-term accruals. Non-core working capital will be managed by booking certain incentives only on actual receipt.
- Debottlenecking: 1.5 crore tonnes of debottlenecking exercises continue across assets, but timing will differ based on where maximum return on investment is achieved.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Cost reduction | ₹250/t reduction from ₹4,500 peak to ₹4,250 full-year average | FY27 |
| Cost reduction | Additional ₹250/t reduction (cumulative ₹500/t over 2 years) | FY28 |
| Q1 FY27 cost | Flattish at ~₹4,500/t before reduction journey begins | Q1 FY27 |
| Volume growth | ~8% consolidated volume growth to ~8 crore tonnes | FY27 |
| Acquired asset utilization | Increase Penna and Sanghi utilization by 5–10% | FY27 |
| Capex | ₹6,000–7,000 crore annual capex | FY27 and FY28 |
| Capacity | 11.9 crore tonnes total capacity (including ongoing 1 crore tonnes GU additions) | End of FY27 |
| New clinker projects | Mundra and Assam clinker plants (0.2 crore tonnes each) | 24–28 months from start |
| Sanghi vessels | 7 vessels delivered progressively for marine infrastructure | Starting next year |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Consolidated sales volume (full year) | 7.37 crore tonnes, highest ever, up 16% YoY |
| Normalized EBITDA (full year) | ₹6,539 cr, up 31% YoY |
| Normalized EBITDA per tonne (full year) | ₹887, up 12% YoY |
| PAT (full year) | ₹2,647 cr, up 17% YoY |
| Revenue per bag | ₹254, up ₹1 QoQ; ₹255 in Q4 FY25 |
| Full year cost per tonne | ₹4,400, 10% above target of ₹4,000 |
| Q4 cost per tonne | ₹4,500, includes ~₹250 of cost escalation; management considers this the peak |
| March exit cost per tonne | ₹4,100 on a normalized basis, excluding ~₹250 war-related escalation |
| FY27 cost reduction target | ₹250 per tonne reduction from the ₹4,500 peak, targeting ₹4,250 average for FY27 |
| FY27 volume guidance | ~8 crore tonnes, growth of ~8% YoY |
| Industry volume growth expectation for FY27 | 5% to 5.5% |
| Cement capacity | 10.9 crore tonnes, with target of 11.9 crore tonnes by end of FY27 |
| Clinker capacity | 6.9 crore tonnes, with 0.4 crore tonnes addition at Maratha to reach 7.3 crore tonnes |
| Trade sales share | 74% in Q4, up from 68% in Q3 FY26 |
| Premium cement share of trade sales | 36% in Q4; 35% for full year |
| Clinker factor | 65%, improved from 67% in Q3 FY26 |
| Green power share | 32% in Q4, up from 26% prior |
| Sanghi cement capacity utilization | 57% |
| Penna cement capacity utilization | 46% |
| Blended utilization expectation for FY27 | 70% to 75% for Ambuja consolidated |
| FY26 capex | ~₹7,500 cr |
| FY27 capex estimate | ₹6,000 cr to ₹6,500 cr |
| Branding and advertisement cost (full year) | ~₹70 per tonne |
| Full year RMX EBITDA | ~₹300 cr |
| Q4 RMX EBITDA | ₹102 cr |
| Project IRR target | 18% (all equity) |
| Cost escalation in March | ~₹25 per bag; ₹400 to ₹500 per tonne on a full-blown basis |
| Industry pricing improvement in March quarter | ~₹10 per bag on average; ₹15 to ₹20 in selected geographies |
| Price gap: base to super premium cement | ₹50 to ₹55 per bag; premium cement gap ₹20 to ₹25 |
| Core working capital days | 20 days, down from 30 days YoY |