Key Takeaways
- PAT surges 71% YoY, but transmission revenue flat: Newly commissioned assets added INR 66 crores, fully offset by a depreciation factor on older cost-plus projects. Management says this drag will not repeat because most projects are now tariff-based.
- Smart meter execution is the near-term growth engine: 24 lakh installations this quarter, on track to surpass 1 crore by FY26-end, with a stated ambition to scale the order book to 6 crore meters over 2-3 years.
- C&I and cooling are new, early-stage vectors: The C&I business booked its first ~INR 18 crores of revenue from 14 industrial customers, while the district cooling facility at Mundra broke ground. Both are framed as multi-year build-outs.
- Parallel license in Navi Mumbai is at the final gate: MERC held a public hearing last week; an order is the last step. For other states, applications are pending with no timeline visibility.
- What to watch next quarter: Whether the MERC order on the Navi Mumbai parallel license arrives, the pace of smart meter installations through the monsoon, and any movement on the INR 90,000 crore transmission bidding pipeline, including the Khavda HVDC reverse auction.
Transmission: Flat Revenue, Strong Pipeline
- Revenue drag is a one-time accounting artifact: INR 66 crores of revenue from newly commissioned projects was neutralized by INR 58 crores of depreciation impact because 12 years were completed on older cost-plus assets. This affects EBITDA and revenue but not PAT, and management stated it will not repeat since most projects now operate under a fixed-tariff regime.
- Three projects commissioned ahead of schedule: Khavda Phase 2 Part-A, Khavda Pooling Station, and Sangod Transmission Project all went live during the quarter. The Khavda projects were commissioned prior to their scheduled date.
- Two projects face known delays: NKTL has disclosed reasons for delay; WRSR is on the verge of commissioning. Sector-wide renewable evacuation projects are also delayed, primarily due to equipment availability.
- Capex phasing is back-end loaded but guidance stands: Q1 transmission capex was INR 1,025 crores, only 9% of the INR 12,000-13,000 crore FY26 target. Management attributed the slow start partly to an unexpected monsoon in May but remains confident of meeting the full-year number, noting that Q1 additions are always much lower than Q4 at the country level.
- Bidding pipeline is large but temporarily paused: INR 90,000 crores of transmission bidding is expected, including two large HVDC projects. Bidding slowed this quarter due to regulatory deliberations at CEA and CTU on transmission system planning and design; after the review, bidding is expected to resume as before.
- Khavda HVDC bid is under technical evaluation: The initial bid has been submitted and a reverse auction is expected in about a month. A separate discussion on whether HVDC technology choice (VSC vs LCC) should be left to developers remains unresolved.
- State transmission opportunities are opening: Maharashtra has started with two projects under auction in the last month; Karnataka has come out with a few TBCB projects; Rajasthan has approved a significant amount of transmission projects under TBCB. A couple more projects are expected in Maharashtra in about a month.
Kandarp Patel: "Even HVDC, we are going to commission in this year itself. That will be a landmark for Mumbai region. No project has got commissioned in such a short time frame in Mumbai region."
Smart Meters: Execution at Scale, Order Book Ambition
- Installation run rate held despite weather disruption: 24 lakh meters were installed in the quarter, maintaining a daily average of 27,000 meters even as unexpected rain in May affected progress. The company is focused on executing its existing order book rather than waiting for new orders.
- FY26 target is to surpass 1 crore installed meters: Management is confident of completing at least 70 lakh meters this year and reaching beyond 1 crore cumulative installations by FY26-end. Next year, the plan is to complete the balance of the current order book.
- Order book scaling ambition is explicit: The target is to scale the order book from the current 2.28 crore meters to around 6 crore meters over the next 2-3 years. Management expects that within 1.5 years, states that are pending bidding will move ahead.
- Key state opportunities are still ahead: Madhya Pradesh, Telangana, Karnataka, and Tamil Nadu are large states that still have smart metering opportunities. The Tamil Nadu bid has been extended and revised a couple of times but has not yet been finalized.
- Market share target is 22%: The company wants to maintain approximately 22% market share in future smart meter opportunities.
- Segment reporting will change: Smart meters currently sit in "others" because the business is still nascent; going forward, it will be shown as a separate segment.
Kandarp Patel: "With this execution run rate, we are fully confident that we will be going beyond 1 crore smart meter installation by the time we complete this financial year."
Distribution: AEML Stagnation, Parallel License Catalyst
- AEML demand was flat due to early monsoon: Distribution demand in the AEML license area remained stagnant, while Mundra distribution grew 22% YoY on increased industrial demand.
- Distribution loss improved but does not lift profit: AEML distribution loss improved to 4.24% from 5.18% in Q1 FY25, making AESL one of the most efficient in T&D losses globally. However, the improvement does not contribute to profitability because the advantage passes to the customer.
- AEML EBITDA declined 7.6% YoY: One reason cited was the absence of the Dahanu power plant, which was present in the base quarter.
- Navi Mumbai parallel license is at the final regulatory step: MERC held a public hearing last week; the order is the last step in the license grant process. A decision is expected very soon. As a second licensee, AESL must set up its own network and has submitted a detailed 5-year rollout plan to MERC for the Navi Mumbai area, progressing area by area.
- Other state applications are stalled with no timeline: Applications for parallel licenses in UP and for expansion of the AEML license area in Gujarat are pending. From a legal standpoint, management believes there is no issue and that someday the applications will have to be cleared, but no timeline can be given.
- UP DISCOM privatization is still in discussion: The RFP has not yet come out; discussions are ongoing between UPRC and the government of UP on certain issues relating to privatization.
Kandarp Patel: "In last week, MERC held a public hearing. Now the order is risen which is the last step in license grant. So, we see that there should be a decision from MERC very soon. As far as other states are concerned, we are not sure about timeline because it is pending with them since long time."
New Businesses: C&I and District Cooling
- C&I business generated its first revenue: This was the first quarter the company earned from the C&I business, with revenue of around INR 18 crores from 14 large industrial and commercial customers representing 717 MW of total load.
- The model is aggregation, not back-to-back trading: AESL aggregates capacity and offers customized solutions to customers, which management distinguishes from standard trading models. The bouquet of services will increase as energy storage capacity is contracted out, improving the ability to serve round-the-clock load and enabling faster scale-up.
- Scale-up target is 7,000 MW in 5 years: Management stated a target to reach about 7,000 MW over the next five years and promised "a lot of action on the C&I front in AESL in the times ahead."
- District cooling facility is under construction at Mundra: The company is building what it calls India's largest district cooling facility, with 45,000 tons of refrigeration at Mundra and total implementing capacity of 52,000 tons. The concept is gaining traction, and the company is in discussions with developers in Pune, Hyderabad, and Chennai where cluster development is happening.
- Management sees a very large addressable market: The view is that theoretically all AC requirements can be converted into district cooling, representing a "humongous opportunity."
Kandarp Patel: "There is one fundamental difference. Normally, when you talk of trading, usually, you must have seen through back-to-back contracts. What we will be doing is aggregation of the capacity. And from aggregate capacity, we'll be offering a customized solution."
Project Execution and Competitive Position
- AESL is structuring projects to reduce manpower dependency: In response to sector-wide equipment and labor challenges, the company has set up project implementation to avoid these bottlenecks and is optimizing operations to reduce manpower dependency, including training programs to create a new manpower pool.
- Competition intensity is expected to ease: Management believes the competitive landscape will not change much during the year and that intensity should reduce because the project tender pipeline is good and all players have sufficient implementation capacity.
- Three more projects to be capitalized this fiscal year: Apart from Mumbai HVDC, three other projects should be commissioned in the later part of January or February, but before the fiscal year-end for sure.
Kandarp Patel: "So, we have set up our project implementation in such a way that we don't face these challenges. We are also trying various ways of optimising these operations. So, your dependability on manpower reduces there."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Smart meter installations | Surpass 1 crore cumulative installations | By end of FY26 |
| Smart meter order book | Scale to ~6 crore meters | Over next 2-3 years |
| Transmission capex | INR 12,000-13,000 crores | FY26 |
| Mumbai HVDC Phase 1 | Commission the project | During FY26 |
| Three other transmission projects | Commission (later part of Jan or Feb) | Before FY26 year-end |
| C&I business scale | Achieve ~7,000 MW load | In ~5 years |
| Navi Mumbai parallel license | MERC order (final step in license grant) | Expected "very soon" |
| Khavda HVDC bid | Reverse auction | In about a month |
| Smart meter market share | Maintain ~22% share | In future opportunities |
Key Metrics
| Metric | Q1 FY26 |
|---|---|
| Total income | 28% YoY increase |
| EBITDA | ₹2,017 cr, +14% YoY vs ₹1,762 cr in Q1 FY25 |
| PAT | ₹539 cr, +71% YoY |
| Cash profit | Crossed ₹1,000 cr, vs ~₹900 cr in Q4 FY25 |
| Consolidated capex | ₹2,224 cr, 1.7x vs ₹1,313 cr in Q1 FY25 |
| Transmission capex | ₹1,025 cr, ~9% of FY26 guidance of ₹12,000–13,000 cr |
| Transmission capitalization target (FY26) | ~₹15,000 cr, including Mumbai HVDC of ₹7,000 cr |
| Under-construction order book | ₹59,300 cr |
| Transmission network | 26,696 circuit kilometers |
| Line availability | 99.8%, earned incentive of ₹29 cr |
| AEML distribution loss | 4.24%, improved from 5.18% in Q1 FY25 |
| Mundra distribution sales growth | 22% YoY |
| Smart meters installed in Q1 | 24 lakh, cumulative 55.44 lakh; 51 lakh commissioned and revenue-generating |
| Smart meter daily installation run rate | ~27,000 meters |
| Smart meter revenue in Q1 | ~₹115 cr, from 106 meter months at ~₹100 per meter per month |
| Smart meter order book | ~2.28 cr meters |
| C&I business contracted load | 717 MW across 14 industrial customers |
| C&I business revenue in Q1 | ~₹18 cr |
| SCA income | ₹178 cr (₹133 cr transmission, ₹45 cr smart meters) |
| Transmission bidding pipeline | ₹90,000 cr expected over ~1 year, ~90% interstate; includes two HVDC projects: Rajasthan ~₹25,000 cr, Khavda-Olpad ~₹20,000 cr |
| Mumbai HVDC Phase 2 estimated cost | ~₹10,000 cr |