Key Takeaways
- Capex engine firing at 2.5x: Q2 capex hit ₹3,000 crore, pulling H1 to ₹4,400 crore (1.7x YoY), and management expects to close FY25 at ₹10,000 crore at least.
- Profitability locked in by deployment: EBITDA rose 31% to ₹1,891 crore and PAT surged to ₹773 crore, driven by all three existing businesses; the ₹50,000 crore capex under execution is expected to drive >20% EBITDA growth as it commissions.
- Smart meter ramp finally unblocked: Daily deployment tripled to 7,000 meters in October after integration with all six discoms completed, and the company targets 16,000-20,000 meters/day from next quarter.
- New C&I business incubated, revenue imminent: The power solutions vertical is in active discussions with Google and Microsoft for complex energy contracts beyond plain PPAs, with contribution expected from next quarter.
- What to watch next quarter: Whether smart meter deployment actually hits the 16,000-20,000/day run-rate, the first revenue contribution from the C&I business, and any resolution timeline on the SEBI show cause notice.
Capex-Led Growth Model
- Capex locks profitability: Every rupee of capex deployed locks in future regulated returns; the ₹50,000 crore under execution will conclude in the next couple of years, driving EBITDA growth in excess of 20%.
- H2 acceleration expected: H1 capex of ₹4,400 crore was constrained by the extended monsoon; the clear season post-monsoon supports a sharp H2 ramp-up toward the ₹10,000 crore full-year target.
- Transmission project pipeline: Four new transmission projects were secured during the quarter, lifting under-construction projects to ~₹31,000 crore from ₹17,000 crore; these are expected to commission within two years (current year, FY26, early FY27).
- Funding fully in place: The ₹8,300 crore QIP equity raise means the company is fully funded; all projects under construction have debt funding tied up, and future projects will continue at a 70:30 debt-to-equity structure.
- Mumbai distribution project: One delayed project is now on track and expected to commission next quarter, adding ~₹1,000 crore to the regulated asset base.
Kandarp Patel: "In our business, it is important to understand that whenever we deploy capex, we to that extent lock-in the profitability."
Smart Meter Rollout
- Integration bottleneck cleared: Integration with all six distribution companies (Assam, Bihar, Maharashtra, Andhra Pradesh, Uttarakhand, BEST Mumbai) is now complete and systems are stable, after resolving contractor and manpower availability issues.
- Deployment rate trajectory: Daily installations rose from 4,000 meters in Q2 to 7,000 in October, with 10,000 people trained; the company expects to operate between 16,000-20,000 meters/day from next quarter now that the monsoon season is over.
- FY25 target: Add 30-35 lakh meters in the next six months, closing the year with 40-45 lakh meters installed; next year, around 70 lakh meters from the awarded contract plus another 30 lakh from new contracts.
- Revenue recognition lag: The ₹900 per-meter subsidy accrues with a 2-2.5 month lag after deployment because meters must be demonstrated working to the discom before billing starts; full revenue from 40-45 lakh meters will be visible next financial year.
- Margin profile: Overall project margin is 80-85%, though initial years may see 75% due to ramp-up costs.
- Ground-level resistance: Deployment faces resistance from motivated factors on the ground, not mainly from customers, which management treats as part of the business to be navigated.
Kandarp Patel: "There is resistance, not mainly from a customer, but all those motivated factors on the ground, but that's a part of business. We have to deal with that and find your way in implementing it."
C&I Power Solutions: The New Business
- Incubation underway: The new C&I Power Solutions business is being incubated and contribution is expected from next quarter onwards; management targets year-end volume of about 500 crore units with an annualized EBITDA contribution of ~₹150 crore.
- Beyond plain PPAs: Discussions with Google, Microsoft and other tech players involve designing energy solutions that go beyond power supply contracts to include managing entire power supply management, last-mile connectivity, and transmission infrastructure.
- Google contract context: Google signed a long-term power purchase contract with Adani Green for part requirement of their existing or under-construction data center at Noida, but that is only a power supply PPA meeting a part requirement; AESL's opportunity is in the broader energy solution stack.
- Margin structure varies widely: Simple back-to-back service contracts yield around ₹10 paisa; complex contracts with stitching and position-taking yield higher margins up to ₹1, with EBITDA margin roughly 98% given minimal costs.
- Capex returns threshold: Management will look for more than 15% return whenever deploying capex in C&I projects, though specific return metrics or cash profiles were not provided, as investment amounts depend on contract-to-contract specifics and consumer facility locations.
- Medium-term ambition: Targeting about 700 crore to 1,000 crore units in a couple of years, with major activity expected in the next financial year.
Kandarp Patel: "This is a very exciting thing, especially personally for me, because I started my career with a power trading job. That's my first love, in fact, this is what C&I business will be."
Transmission: Bidding Pipeline & Returns
- IRR environment improving: IRRs have increased in recent bids as the level of aggression has reduced; a huge pipeline of ₹85,000 crore notified for bidding and another ₹1 lakh crore expected next year supports better returns.
- Market share ambition: Management expects to maintain market share with opportunity to increase it, hoping to secure ₹15,000-₹20,000 crore worth of projects in the next six months.
- HVDC opportunities: The Rajasthan HVDC rebid is expected very soon, and another Khavda HVDC is expected in the second half.
- Execution risk managed upfront: Detailed analysis is done before bidding, with potential delays factored into cost models and preparative work completed before bidding and execution begins.
- Mumbai HVDC line: Expected capex of about ₹7,000 crore; the project is progressing well and remains on track for commissioning within the August 2025 timeline.
Kandarp Patel: "We expect that if not, it will further allow us to increase IRR, but at least we do not see any condition where there will be a lot of aggressive bidding forcing you to reduce your IRR."
Regulatory & Governance Items
- SEBI show cause notice: A show cause notice was sent by SEBI to shareholders and AESL regarding shareholding not being public; management clarified it pertains to shareholders, not the company per se, and the company will respond in due course without providing a timeline or additional details on the percentage shareholding alleged not to be public.
- Peer review certificate resolved: The show cause notice regarding the peer review certificate that statutory auditors had to provide in 2015-16 has been resolved; the auditors have subsequently provided it and complete peer review is now available.
- Regulatory deferral account liquidation: The ₹1,600 crore regulatory deferral account is being liquidated faster than committed; ₹700 crore was liquidated in the last six months, with ₹900 crore remaining by end of September, and full liquidation is expected by end of March per the MERC order.
- Dahanu power plant carve-out: The 500 MW coal-based thermal power plant under Adani Electricity Mumbai Limited was carved out for ESG considerations, a book entry of ₹2,300 crore; AEML/AESL now owns no coal-based generating power plant.
- Effective tax rate: Expected effective tax rate of around 20% going forward for the second half and beyond.
Anupam Misra: "At this stage, I also have to clarify that it has nothing to do with the company per se. It is because it is the company which is listed and hence the show-cause notice has been sent to it, but it is more pertaining to the shareholders rather than the company."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY25 capex | Close year at about ₹10,000 crore at least | FY25 end |
| Transmission project commissioning | ₹31,000 crore capex projects commissioned | Current year, FY26, early FY27 |
| EBITDA growth | More than 15%; in excess of 20% corresponding to ₹50,000 crore capex | As projects commission |
| Smart meter deployment | Add 30-35 lakh meters; close year with 40-45 lakh installed | Next 6 months (H2 FY25) |
| Smart meter daily run-rate | Operate between 16,000-20,000 meters/day | From next quarter onwards |
| Smart meter FY26 | Add around 70 lakh meters from awarded contract plus ~30 lakh from new contracts | FY26 |
| C&I business volume | Year-end volume of about 500 crore units; annualized EBITDA ~₹150 crore | FY25 end |
| C&I medium-term volume | About 700 crore to 1,000 crore units | In a couple of years |
| Regulatory deferral account | Full liquidation of ₹1,600 crore through tariff | By end of March |
| Mumbai HVDC line | Commission within timeline | August 2025 |
| Effective tax rate | Around 20% | H2 FY25 and beyond |
| Transmission project wins | ₹15,000-₹20,000 crore worth of projects | Next 6 months |
| Bond refinancing | Refinance existing bond maturing August 2026 | At the right time before maturity |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Operational revenue | ₹4,200 cr, +23% YoY |
| EBITDA | ₹1,891 cr, +31% YoY |
| PAT | ₹773 cr |
| Cash profit | ₹1,026 cr |
| Net debt to EBITDA | 3.1x |
| EBITDA growth outlook | In excess of 20%, corresponding to ~₹50,000 cr capex under execution |
| Effective tax rate | ~20% going forward, one-time MAT credit reversal in Q2 |
| Capex deployed in Q2 | ~₹3,000 cr, 2.5x of Q2 last year |
| H1 FY25 capex | ₹4,400 cr, 1.7x of H1 last year |
| FY25 capex guidance | ~₹10,000 cr at least |
| Under-construction transmission projects | ~₹31,000 cr, expected to contribute ~₹4,200 cr EBITDA once completed |
| Transmission bidding opportunity (next 6–7 months) | ~₹85,000 cr |
| Expected project wins (next 6 months) | ₹15,000–₹20,000 cr at current market share |
| IRR on new transmission projects | ~15% |
| Distribution RAB | ₹8,405 cr, growing 12–13% annually |
| Electricity sale growth (distribution) | 7% YoY |
| Distribution losses | 4.85% |
| Network reliability | 99.7%, earning ₹35 cr incentive |
| Smart meters deployed in Q2 | ~4 lakh meters at 4,200 meters/day |
| Total smart meters deployed to date | 6.73 lakh meters |
| Smart meter installation target (H2 FY25) | 30–35 lakh meters, reaching 40–45 lakh by year-end |
| Smart meter rollout expected next year | ~70 lakh meters from awarded contracts, plus ~30 lakh from new contracts |
| Smart meter margin | 80–85%, may be ~75% in initial ramp-up years |
| C&I business annualized EBITDA target | ~₹150 cr from ~500 crore units by year-end |
| C&I business long-term volume target | 700–1,000 crore units in a couple of years |
| Mumbai HVDC line expected capex | ~₹7,000 cr, commissioning by August 2025 |
| Regulatory deferral account asset (AEML) | ₹900 cr remaining as of September-end, fully liquidated by March 2025 |