Key Takeaways
- Record nine-month EBITDA of INR 675 crores: Both liquid and gas divisions hit all-time highs, driven by new capacity, acquisitions, and 22% LPG throughput growth.
- Gas EBITDA dipped QoQ on distribution margin band: Q3 gas EBITDA fell to INR 146 crores from INR 152 crores in Q2, entirely due to the distribution margin fluctuating within its normal INR 2,500–3,250 per ton band; logistics EBITDA per ton was unchanged.
- Liquid margins have further room to run: Margins reached ~52% this quarter, and management sees continued improvement ahead from product mix optimization, value-added products, and new complex clients.
- INR 1,750 crores capex program on track: Cryogenic LPG projects at Pipavav and Mangalore, plus 300,000+ kiloliters of liquid tankage, are all progressing on budget and on time for completion within 18–20 months.
- What to watch next quarter: Commissioning of Kandla liquid tankage and the first phase of JNPT, the trajectory of distribution volumes after the Q3 YoY dip, and any firm announcement on the advanced ammonia projects.
Gas Division: Record Throughput, Distribution Margin Noise
- LPG throughput hit a lifetime record: Volumes handled across all four terminals rose 22% YoY for the nine-month period, with Pipavav now regularly handling VLGCs after its jetty upgrade.
- Distribution volumes grew 21% for nine months: Management cautioned against reading too much into the Q3 YoY decline (144,000 MT vs 157,000 MT), pointing to the cumulative nine-month improvement to 433,280 MT from 358,140 MT.
- QoQ EBITDA dip is a margin-band artefact: The INR 6 crore sequential decline in gas EBITDA came from distribution margin moving within its normal INR 2,500–3,250 per ton range; the logistics business saw no margin compression.
- Spare throughput capacity sits mainly at Kandla: Pipavav is performing strongly, Mumbai is at its limit, and Haldia is at 60%; Kandla carries the most distribution volume because it has the spare capacity to support it.
- LPG generator opportunity is large but stalled on engine availability: Management is "struggling a little bit" to source LPG/propane engines for larger gensets, though the economics are compelling at roughly 25% of diesel generation cost.
Murad Moledina: "When you use diesel, it is INR 30 plus the unit of energy generated. And if you start using propane, it can be 25% of that. So that's 75% savings and plus a clean fuel. So that's big. But it would take its time."
Liquid Division: Record EBITDA, Market Leadership Cemented
- Liquid EBITDA hit an all-time high of INR 243 crores: New capacities coming online and acquisitions drove the record, with the Aegis Vopak joint venture now the "unquestioned market leader" in every port it operates.
- Product mix optimization still has leverage: Margins at ~52% this quarter are not the ceiling; management sees room to improve further through value-added products, new clients, and more complex product handling.
- Technical sophistication is a widening moat: The combined expertise of Aegis and Vopak means international and domestic customers are choosing them over competitors for complex, difficult-to-handle products.
- Acquisition turnaround is fast and low-risk: Newly acquired terminals start with low-value, low-risk products, then upgrade over 3–12 months to handle more value-added products, with no operational standstill during the transition.
- Liquid ROCE appears low for structural reasons: Pre-owned land is valued at fair market value despite a lower cost basis, and CWIP is a permanent feature because something is always under construction or commissioning.
Raj Chandaria: "I think with the combination of Aegis and Vopak coming together, we have noticed that in every port that we are operating, we are now -- with our joint venture, Aegis Vopak Terminals Ltd., is essentially becoming the market leader -- unquestioned market leader with maximum market share."
Capacity Expansion: INR 1,750 Crores Program on Time and Budget
- Cryogenic LPG projects progressing: The 45,000 MT Pipavav and 85,000 MT Mangalore cryogenic LPG storage projects are on budget and on schedule, with completion within the 18–20 month capex window.
- Liquid tankage additions stacking up: Kandla will add 35,000 kiloliters in Q4; JNPT will commission ~20,000 kiloliters in Q4 with the balance by June 2024; Mangalore liquid expansion will be partially operational by end-FY24 and fully in Q1 FY25.
- Haldia expansion already completed: An additional 50,000 kiloliters of liquid tankage at Haldia is finished, and management plans another 300,000+ kiloliters across all ports next year.
- New terminals will start at 20–25% utilization: Pipavav and Mangalore cryogenic projects will follow the same ramp path as Kandla, per management guidance for analysts to model from that utilization base.
- Throughput growth of 20%+ expected next year: Even without counting the new Pipavav and Mangalore capacities, the current annualized run rate of 4.6 supports at least 20% throughput growth.
Market Development: Regulatory Tailwinds, Competitive Secrecy
- Regulatory mandates are the strongest conversion driver: The Morbi market grew exponentially after pollution authorities mandated gas-based fuels; similar mandates are now emerging in other industrial areas, forcing conversion to natural gas or propane.
- Direct heat applications are the biggest LPG use case: Automotive paint shops, ceramics, and other clean-fuel-requiring processes dominate conversions, especially where customers already use natural gas and can switch fuels easily.
- Dual-fuel flexibility is being engineered in: Most larger customers already have dual burners and flexible fuel systems; Aegis is working technically to convert those who do not, making fuel-switching seamless.
- Competitive secrecy is now standard practice: Management will secure all permits and licenses before making public announcements, having "learned the hard way" that competitors resist Aegis entering their turf.
- KGPL pipeline commissioning pushed to FY25: The NOC says December 2024; of the 0.83 crore ton pipeline capacity, NOC has reserved 0.15 crore tons for gas handling, but how much Aegis ports contribute depends on how quickly national oil companies use the capacity.
Raj Chandaria: "We've learned the hard way that it's better to get everything quietly and then make the announcement when we're ready to start work with everything because this is the way things work."
Ammonia, M&A, and the Next Leg
- Ammonia projects are advanced but unsigned: Management described an "active set of projects" that are "pretty advanced" but declined to give specifics until deals are firm, calling premature announcements unwise.
- M&A pipeline is active, discipline is firm: The company has the firepower, management bandwidth, and cash to pursue meaningful acquisitions, but will not overpay: "we can build it cheaper than what the market expectations are."
- New port entries await land acquisition: Aegis is looking to enter ports where it is not yet present and will announce once land is secured.
- No progress on industrial terminals: Management confirmed this category is "not on the plate right now."
- INR 4,500 crore capex figure not confirmed: When an analyst raised a much larger capex number, management did not endorse it, reiterating only the INR 1,750 crores announced program and noting occasional additional opportunities may or may not fall within it.
Raj Chandaria: "I don't think it's wise for us to actually start making big announcements until we have it in the bag. But I can assure you that it's pretty advanced."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Kandla liquid tankage | Commission additional 35,000 kiloliters | Q4 FY24 |
| JNPT liquid terminal | ~20,000 kiloliters in Q4, balance by June 2024 | Q4 FY24 / Q1 FY25 |
| Mangalore liquid expansion | Partially operational by end FY24, balance in Q1 FY25 | FY24 / Q1 FY25 |
| Cryogenic LPG projects (Pipavav 45k MT, Mangalore 85k MT) | On budget, on time | Within 18–20 months |
| Liquid capacity addition | Construct 300,000+ kiloliters across ports | FY25 |
| Throughput growth | 20%+ growth, excluding new Pipavav and Mangalore capacities | FY25 |
| KGPL pipeline commissioning | NOC says December 2024; Aegis volume contribution depends on NOC offtake | FY25 |
| Haldia liquid expansion | Additional 50,000 kiloliters completed; further expansion planned | Completed / FY25 |
Key Metrics
| Metric | Q3 FY24 |
|---|---|
| Group EBITDA (9M FY24) | INR 675 cr, +15% YoY |
| Liquid revenue (9M FY24) | INR 356 cr, +18% YoY |
| Liquid EBITDA (9M FY24) | INR 243 cr, +21% YoY |
| Gas EBITDA (9M FY24) | INR 431 cr, +12% YoY |
| Profit before tax (9M FY24) | INR 554 cr, +28% YoY |
| Profit after tax (9M FY24) | INR 435 cr, +24% YoY |
| Earnings per share (9M FY24) | INR 10.62, +16% YoY |
| LPG throughput volume (9M FY24) | 0.3 crore metric tons, +22% YoY |
| Distribution volume (9M FY24) | 433,280 metric tons, +21% YoY |
| Sourcing sales volume (9M FY24) | 5,78,140 metric tons, -12% YoY |
| Gas EBITDA (Q3) | INR 146 cr, down from INR 152 cr in Q2 FY24 |
| Distribution margin range | INR 2,500 to INR 3,250 per ton, varies by quarter |
| Liquid division margin (Q3) | ~52% |
| Cash on hand | INR 1,700 cr |
| Bank debt | INR 1,200 cr |
| Anticipated capex program | INR 1,750 cr, covering LPG and liquid projects |
| Total liquid storage capacity | 0.19 crore kiloliters, with further 300,000 kiloliters expected in FY25 |
| Throughput run rate (Q3) | 1.15 (implied annualized ~4.6), expected FY24 ending throughput 4.1 to 4.15 |
| Next year throughput growth expectation | 20% plus, without additional Pipavav and Mangalore capacities |
| Pipavav terminal utilization | Past 60% |
| Mumbai terminal utilization | 90% plus |
| Haldia terminal utilization | 60% |
| LNG vs LPG price differential | LNG 10% to 15% more costly than propane, on calorific value basis |