Aegis Logistics Ltd Q4 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/nbp9orztgys0mhkh61dknt65.pdf

Key Takeaways


The Vopak JV & the ₹4,500 cr Capex Cycle

Chandaria: "I'm not sure that I necessarily agree with your statement that we have covered all the major ports of India. We are definitely well positioned on the West Coast of India, and we have one port where we are present on the East Coast of India."

Kandla: The New Growth Engine

Chandaria: "I think the construction is undertaken by IHB, which IndianOil, Hindustan Petroleum and Bharat Petroleum, their consortium. And given our experience with the Mumbai Chakan pipeline with other pipelines, I think these organizations do not work in the same way as the private sector works necessarily. So I would temper one's expectations about the exact commissioning date."

Gas Division: Throughput, Sourcing & the Margin Mix

Chandaria: "Sourcing is -- while definitely not the most profitable business in terms of absolute numbers, it's a part of our overall strategy of being an integrated supplier of LPG from the sourcing, shipping all the way through to distribution. And it really gives us a -- along with our joint venture partner Itochu, it gives us a tremendous window into what's happening in the business."

Liquid Division: Full Utilization & Capacity Build


Competitive Position: LPG vs Natural Gas & the Cryo Shift

Moledina: "Please understand that in this country, the transition is from dirty fuel to clean fuel. In clean fuel basket currently, natural gas and propane or LPG whatever you call it, are the clean fuel gas. And Ammonia will add to it. So there is so much of dirty fuel, like coal, furnace oil, briquette, diesel, et cetera, which needs to transit out and clean fuel to transit in."

Guidance & Commitments

CommitmentSpecificsTimeline
EPS growth CAGR22% to 27% CAGR (~25%) from FY22 to FY27, supported by the ₹4,500 cr capex planFY22–FY27
Logistics throughputAs close to 0.4 crore tons as possibleFY24
Liquid capacity commissioning230,000 KL under construction fully availableFY25
Pipavav 3,000 MT spheresCommissioning expectedQ2 FY24
Pipavav cryogenic LPG terminal48,000 MT capacity under constructionNo date (underway)
Mangalore cryogenic LPG terminal80,000 MT capacity (India's largest) commencedNo date (underway)
Kandla–Gorakhpur pipelineCommissioning delayed; management tempers expectations on exact date due to public-sector consortium executionEnd of 2024 (tempered)
Ammonia / green initiativesFormal information expected within 6 months~6 months from call date
JV capex plan₹4,500 cr over 2023–2027; ~₹1,500–1,700 cr underway2023–2027
JV gearing covenantDebt funding with 0.6% gearing target, reached over timeOver time (no date)
Infrastructure capex returnsEBITDA between 15% and 20% on current and forward capexProject lifetime

Key Metrics

MetricQ4 FY23
Consolidated revenue₹8,627 cr for FY23, up 86% YoY
Consolidated EBITDA₹804 cr for FY23, up 37% YoY, highest ever
Consolidated PAT₹511 cr for FY23, up 33% YoY
EPS₹13.19 for FY23, up 29% YoY from ₹10.19
Full-year dividend₹5.75 per share, 575% of face value of ₹1
Liquid division revenue₹417.9 cr for FY23, up 55% YoY
Liquid division EBITDA₹271.5 cr for FY23, up 39% YoY
Gas division revenue₹8,209.2 cr for FY23, up 88% YoY
Gas division EBITDA₹532.2 cr for FY23, up 36% YoY
LPG throughput volume8.77 lakh MT, up 9% YoY; FY23: 33.3 lakh MT, up 17% YoY
Distribution volume (commercial & industrial bulk)1.31 lakh MT, up 193% YoY; FY23: 4.74 lakh MT, up 243% YoY
Autogas sales volume4,888 MT in Q4; FY23: 20,228 MT vs 21,700 MT in FY22
Sourcing volume2.37 lakh MT vs 2.70 lakh MT in Q4 FY22; FY23: 8.95 lakh MT, up 61% YoY
Kandla LPG terminal exit run ratemore than 70,000 tons per month
EPS growth guidanceCAGR of 25% maintained (range 22% to 27%) from FY22 to FY27
JV capex plan with Vopak₹4,500 cr over 5 years (2023–2027), with ~40% (₹1,500–1,700 cr) already underway
Total static LPG terminal capacity under construction131,000 MT (Pipavav cryogenic 48,000 MT, Mangalore cryogenic 80,000 MT, Pipavav spheres 3,000 MT)
Liquid capacity under construction230,000 KL (Kochi 50,000 KL, Mangalore 70,000 KL, plus 110,000 KL first step), plus 50,000 KL recently commissioned