Key Takeaways
- Earnings surge on margin recovery: PAT jumped 106% YoY as EBITDA margin crossed 10% in Q2, with management committing to double-digit margins for the full year.
- Order book and revenue guidance held firm: FY26 revenue growth guidance of 15–20% was reaffirmed, backed by a ~₹8,000 cr order inflow target and a clear runway in residential real estate.
- Labor is the binding constraint, not demand: A severe skills shortage, amplified by festivals and Bihar elections, drove a spike in employee costs; management is mitigating through mechanization and client-backed labor retention.
- The capex cycle is peaking: FY26 capex was revised down to ₹400 cr from ₹500 cr, with a further 20% drop guided for FY27, signaling a shift from capacity build-out to cash generation.
- What to watch next quarter: Whether the NCR construction ban materially disrupts H2 billing, the pace of ramp-up at Dahlias and Downtown, and any concrete diversification moves beyond the core.
Margin & Profitability
- PAT more than doubled: PAT grew 106.07% YoY, with PAT margin improving to 5.88% in 1HFY26 from 3.53% a year ago, driven by operating leverage and better project mix.
- EBITDA margin crossed the double-digit threshold: EBITDA margin reached nearly 11% in Q2 and nearly 10% for H1, up from 6.93% in 1HFY25, putting the full-year double-digit commitment within reach.
- Employee cost spike was a one-off: Employee cost jumped to ₹121 cr in Q2 from ₹91 cr in Q1 because delayed increments and arrears were paid in the quarter; this will taper off in H2 as high-volume projects ramp up.
- Working capital tightened further: Working capital days improved to ~87 from ~95, with ~₹70 cr stuck in Maharashtra and Assam on account of GST revisions, but management expects that statutory money to come in time.
- Cash strategy favors cost avoidance over yield: The company avoids interest-bearing advances on government projects and uses cash to reduce procurement costs and get better supplier bargains, sacrificing some interest income for margin.
Uppal: "Shravan, I am sticking my neck out and saying that we will maintain what I had projected last time. And we have done that. For this quarter, we have crossed 10%, we are nearly at 11%, and we are nearly at 10% for H1. So, I think overall, it will be more than double-digit. Let me just say that for the entire year."
Order Book & Revenue Visibility
- Revenue growth guidance reaffirmed: Management maintained the 15–20% top-line growth projection for FY26, with H2 traditionally more remunerative in both revenue and earnings.
- Order inflow target on track: The company is confident of achieving the ~₹8,000 cr new order target for FY26, with Whiteland alone seeing a scope increase from ₹821 cr to ₹1,065 cr.
- Next-year growth already telegraphed: Management sees no challenge in maintaining 15–20% growth even next year, with a similar ~₹8,000 cr order inflow and 15%+ revenue growth expected.
- Private-sector work is being turned away: The company is actively refusing work every month to avoid skewing the private-to-government ratio too far from the long-run 60:40 target, signaling strong demand but deliberate capital discipline.
- Smaller legacy projects are winding down: Lower-value projects from earlier cycles should be completed by FY27 or mid-FY28, removing a drag on margins and management attention.
Uppal: "At the moment, actually, to sort of give you the correct picture on the private sector side, we are actually refusing work every month because we don't want the ratio to be skewed too much."
Project Execution & Key Assets
- Dahlias ramp-up delayed by weather: DLF handed over two of eight towers, but heavy September rains delayed further handovers; FY26 revenue is pegged at ₹100–125 cr, with FY27 jumping to ₹300–350 cr once all towers are in play.
- DLF Downtown gaining momentum: Billing is logging ₹15–20 cr and is expected to ramp 20–30% as execution accelerates.
- Airport projects running at full throttle: Varanasi and Darbhanga airports are each billing ₹25–30 cr and are on track to cross 30% of order value in FY26; Darbhanga completion is set for October 2026, while Varanasi faces client pressure to finish by March 2027 ahead of UP elections.
- CSMT station redevelopment finally unlocked: Design closure has enabled the first above-track work and greenfield buildings are out of the ground; structural steel fabrication capacity is being doubled in the next 2–3 months as clearances have come.
- Gems and jewelry project starting soon: Environmental clearance is in hand, engineering design is underway, and ground work is expected to begin in two months, with FY27 revenue potential at 30–35% of order value.
- Old flat inventory being liquidated patiently: The company is selling legacy inventory only when good prices are obtained, with some stuck in Noida due to changing laws and others in projects where the client entered NCLT.
Labor & Capacity Constraints
- Labor shortage is the single biggest challenge: A skills shortage is compounded by festival-driven outmigration (Diwali, Chhath) and the Bihar elections, which drew skilled workers back en masse due to FIR implementation.
- NCR construction ban is being mitigated: Laborers are being retained on site with client agreement to pay them even when no work is happening; post-Bihar elections, labor has started returning, and management expects the impact to be less severe than prior bans.
- Mechanization is the structural answer: The company is importing heavy-duty cranes, using larger electronic batching plants for higher-grade concrete (up to M80), investing in system shuttering, and deploying CNC machines for bar cutting and reinforcement steel fabrication to reduce labor dependency.
- Campus hiring sustains the talent pipeline: The company recruits 50–60 fresh engineers every year (barring COVID years) and trains them, building a captive skilled workforce.
Uppal: "Yes, labor is a continuous challenge. It is the biggest challenge that we are facing. In addition to the labor, there being a skills shortage, there is also an impact on account of events such as, or festivals such as Diwali, Chhath, and then elections now, which just got over in Bihar. En masse, a lot of skilled workforce has gone to Bihar, especially this year, because of the implementation of the FIR."
Capex & Balance Sheet
- Capex cycle is peaking and rolling over: FY26 capex was revised down to ~₹400 cr from the earlier ₹500 cr guidance, and FY27 is guided at ~₹300 cr, 20% lower, as the heavy machinery and shuttering investment phase winds down.
- Capex composition is machinery-heavy: Spending is concentrated on plant and machinery (cranes, batching plants) and shuttering material, with aluminum shuttering having a useful life longer than the standard depreciation formula.
- Okhla land purchase consolidates offices: A 1,300 sq yard plot was procured to build an owned office, consolidating operations currently spread across two buildings; planning is underway with details expected next quarter.
- West Bengal land awaiting approvals: The company is working actively to secure necessary approvals to make the Kolkata land ready to build; a decision on whether to develop or sell outright will come later.
- Depreciation to rise with capex: Depreciation is currently running at ~₹20-odd cr per quarter and will move up as capex is deployed, though the exact trajectory for FY27 was not quantified on the call.
Strategy & Diversification
- Residential real estate runway looks clear: Management sees no downturn on the horizon, with a clear runway over the next three to four years, supported by a client pedigree that includes DLF, Signature Global, and Brigade.
- Private-sector risk is being actively de-risked: For newer clients like Whiteland, contracts have been negotiated to reduce financial liabilities, including no bank guarantees; DLF funds the company's capex interest-free.
- Diversification is being studied, not executed: The company is studying adjacent sectors, new technologies, foreign partnerships, and potential acquisitions to maintain growth rates, but management clarified that acquisitions are not on the anvil in the near future.
- Digitization is at an early but functional stage: SAP has gone live with PwC, Power BI dashboards are in use at different hierarchy levels, and management now reviews data monthly; on a journey of 1 to 10, the company rates itself at 4.
Uppal: "What I am trying to say is that we have negotiated the contract in such a fashion that our financial liabilities are considerably reduced, we have de-risked ourselves, so to speak."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 15% to 20% top-line growth | FY26 |
| Revenue growth | 15%+ growth, similar ~₹8,000 cr order inflow | FY27 onwards |
| EBITDA margin | More than double-digit for the full year | FY26 |
| Order inflow | ~₹8,000 cr new orders | FY26 |
| Capex | ~₹400 cr (revised from ₹500 cr) | FY26 |
| Capex | ~₹300 cr (20% less than FY26) | FY27 |
| Dahlias project revenue | ₹100–125 cr | FY26 |
| Dahlias project revenue | ₹300–350 cr | FY27 |
| CSMT station revenue | ~₹400 cr (balance ~₹250 cr in H2) | FY26 |
| CSMT station revenue | ~40% of order value | FY27 |
| Gems & jewelry project revenue | 30–35% of order value | FY27 |
| Airport projects revenue | Cross 30% of order value at both Varanasi and Darbhanga | FY26 |
| Darbhanga Airport completion | Project completion | October 2026 |
| Varanasi Airport completion | Stipulated completion (client pressing for March 2027) | June/July 2027 |
| Smaller-value legacy projects | Completion | FY27 to mid-FY28 |
| Structural steel fabrication capacity | Doubling capacity | Next 2–3 months |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue | ₹1,177.30 cr, +16.39% YoY |
| PAT | ₹79.45 cr, +106.07% YoY |
| EBITDA margin | 9.85% in 1HFY26, vs 6.93% in 1HFY25 |
| PAT margin | 5.88% in 1HFY26, vs 3.53% in 1HFY25 |
| Net order book | ₹18,057.60 cr as on 30 Sep 2025 |
| Order inflow (H1 FY26) | ₹4,374 cr |
| FY26 revenue growth guidance | 15% to 20%, maintained |
| FY26 EBITDA margin guidance | Double-digit, maintained; Q2 crossed 10%, nearly 11% |
| FY26 new order inflow target | ~₹8,000 cr |
| L1 orders outstanding | ~₹1,620 cr (OUTR Bhubaneswar ~₹1,000 cr, RML Hospital Delhi ~₹570 cr) |
| Bid pipeline | ~₹6,500 cr |
| Working capital days | 87 days as on 30 Sep 2025, improved from 95 days as on 30 Jun 2025 |
| Mobilization advances | ₹708 cr as on 30 Sep 2025, 33% interest-bearing |
| Retention money | ₹418 cr (including non-current) as on 30 Sep 2025 |
| Unbilled revenue | ₹552 cr as on 30 Sep 2025 |
| Cash and equivalents | ~₹1,000 cr, of which restricted cash ~₹419 cr and free cash ₹615 cr |
| FY26 CAPEX target | ~₹400 cr, revised from earlier guidance of ₹500 cr; H1 CAPEX ₹137 cr |
| FY27 CAPEX target | ~₹300 cr, about 20% less than FY26 |
| Employee cost | ₹121 cr in Q2, vs ₹91 cr in Q1; includes arrears for increments effective 1 Jan |
| GST stuck (Maharashtra & Assam) | ~₹70 cr |
| CST station redevelopment FY26 revenue | ~₹400 cr for full year, ~₹250 cr balance in H2 |
| Dahlias project FY26 revenue | ₹100 cr to ₹125 cr |
| Dahlias project FY27 revenue | ₹300 cr to ₹350 cr |
| Gems & jewelry project FY27 revenue | 30% to 35% of order value |
| Interest rate on mobilization advances | 7% to 8% |
| Old flats inventory | ₹35 cr |