Anant Raj Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/mx5lj9mkqr9in0ljsm7rk1yn.pdf

Key Takeaways


The 63A Engine: Plot Sales, Pricing Power & the Group Housing Catalyst

Sarin: "the land is already paid for as you know, and the land is definitely more than 10 years, 8 to 10 years old. So, that's already done. The construction cost outer limit for 0.1 crore square foot will not be more than 500, sir. And the selling cost today is about 18,000 per square feet... we feel that the margins from here when the group housing comes, starts contributing, which is going to be from next year, is going to be further will further improve, sir."

Data Center: First Revenue, First Delay, and a 300 MW Bet

Sarin: "we don't have that kind of money, and as you know, at Anant Raj, we are very clear that we are not going to be taking on debt."

Margin Trajectory & the Land Bank Advantage


Balance Sheet: Debt Reduction as a Stated Priority

Sarin: "The Company is not taking on any debt for data center at all. It's all from our internal accrual. So, just have a look, sir. We have spent 200 from our internal accrual. So, these 770 figures which actually if you reduce 200 more, this would have actually gone down to 570, sir."

Demand Environment & the Cycle Call

Sarin: "10 years back when we used to have booms and all, of course, for 10 years, nobody talks about a boom, especially in our sector. That time you would see investors and all those things, but this time this is real demand, sir, because almost 75% of our sale is now to end users."

Guidance & Commitments

CommitmentSpecificsTimeline
21 MW data center operationalFull 21 MW at Manesar commissioned and revenue-generatingMid-2024 ("maybe a quarter plus" from original FY24 target)
300 MW data center targetTotal data center capacity across all sites3-4 years
Data center cost reduction₹15 lakhs per MW per month cost reduced by 15%4-5 months
Luxury group housing launch0.11 crore sq ft project in Sector 63A launched with RERA approvalQ3 FY24
Tirupati affordable housing launchProject with ₹340 cr top line, ≥30% margin launchedQ3 FY24
Anant Raj Centre launch (Delhi)Hospitality, service apartment, and commercial complex launchedQ3 FY24 (all formalities complete)
Debt reductionNet debt reduced "substantially" from ₹770 cr, funded by internal accrualsFY25
100-acre Delhi land monetizationMonetization of Delhi land parcel begins~2 years
Balance 50% Anant Raj Estate inventory launchRemaining inventory released in phases1-2 years

Key Metrics

MetricQ2 FY24
Revenue from operations₹341 cr, up 28% YoY
H1 FY24 revenue from operations₹667 cr, almost 1.5x YoY
EBITDA₹88 cr, EBITDA margin at 26%
PAT₹59 cr, grew 80% YoY
H1 FY24 PAT₹107 cr, almost doubled YoY
Operating cash flow growth25.33% YoY, up from 19.35%
Net debt₹770 cr, down from ₹1,650 cr in January 2021
Ashok Estate inventory sold80% sold, 60-70% of money collected; total monetization expected more than ₹1,000 cr
Sector 63A remaining inventory top line~₹10,000 cr of further top line to be monetized
Data center operational capacity3 MW operational, revenue started ~2-2.5 months back
Data center rental rate₹90 lakhs per MW per month
Data center operational cost~₹15 lakhs per MW per month
Data center cost per MW₹25-26 cr per MW additional cost, land and building already invested
Tirupati affordable housing project top line~₹340 cr, margin at least 30%
Anant Raj Center office space expected cash flow₹250 cr plus from 1.2 lakh sq ft office sale