Key Takeaways
- H1 revenue already exceeds full FY26: Revenue grew 272% YoY to ₹153.97 crores, driven by a 73% jump in tower production and integrated supply contracts contributing 64% of revenue.
- Absolute earnings per tower doubled: EBITDA per tower rose 105% YoY to ₹32.82 lakhs, even as percentage margin moderated to 23.4% from the material-intensive mix and pre-revenue Kutch opex.
- Kutch is the unlock, but still in trial runs: The facility is not yet contributing; ISO certification and OEM approvals are expected by mid-December, with revenue contribution starting in the last two quarters.
- FY28 ambition is aggressive and specific: Management targets 500+ towers, ₹30–40 lakhs EBITDA per tower, and ~25% market share, contingent on both plants running fully and internal manufacturing coming online.
- What to watch next quarter: Whether Kutch receives OEM approvals on schedule, the pace of order book finalization for FY28 from December, and the start of internal manufacturing trials.
Volume & Revenue Drivers
- Tower production surge: H1 FY27 output reached 107 towers vs 62 in H1 FY26, a ~73% increase, with approximately 100 towers manufactured at the Kopal facility. Some hybrid-model towers generated lower revenue per unit and were not fully counted.
- Integrated supply shift: Contracts bundling raw material supply with fabrication contributed ~64% of H1 revenue, lifting absolute earnings per tower while moderating percentage margins. Management is moving toward a conversion-plus-internal-plus-raw-material model.
- Tower weight inflation: Since 2023, tower weight has increased 30–40% as the industry shifts from 2.7–3.3 MW turbines to 4–5 MW machines. Tower count per month stays similar at 20–22, but tonnage and revenue rise with weight.
- Seasonality tailwind: Historically 70–80% of annual revenue lands in H2 because monsoon conditions halt site erection. This year the split may shift to 55/45 H2/H1 because a new machine arriving mid-month will lift Karnataka productivity to 7–8 towers per month, causing some near-term delay.
- Customer stickiness: Eleven clients with zero complaints support the growth trajectory; management argues customers avoid taking chances with heavy financial exposure in machining and fabrication. JSW is the top customer, with INA Power also in the book.
Nimish Vashi: "This is why we believe absolutely EBITDA per tower is a key metric investors should track when you will it annual performance along -- along percentage margin working capital and cash-flow."
Kutch Facility: Status & Ramp-Up
- Pre-revenue phase: The Kutch facility is in trial runs and the approval stage. ISO certification is at 14,500 out of 15,000 and expected by end-November; plant approvals from OEMs including Envision and Sanvian are expected by the first week of December, with the full procedure finishing before 15 December.
- Revenue contribution timeline: Kutch is expected to begin contributing in the last two quarters, December through March, with orders already in hand. As utilization improves, better absorption of operating costs should support operating efficiency.
- Capacity context: The facility is described as the biggest manufacturing facility under one roof in India. Production started first, with certification work now underway.
- Margin drag from Kutch: The 110 bps EBITDA margin decline from 24.5% in FY26 to 23.4% in H1 FY27 is partly because the company began incurring operational expenses at Kutch while capacity is still progressing through approvals.
Margin Structure & Profitability
- Percentage margin moderated, absolute earnings improved: EBITDA margin stood at 23.4% compared with 24.5% in FY26 because material-intensive integrated supply contracts carry lower percentage margins and Kutch opex began before revenue contribution. However, EBITDA per tower rose 105% YoY to ₹32.82 lakhs, and PAT grew 539% to ₹14.39 crores.
- Interest cost eliminated: H1 FY27 carried no interest cost because IPO proceeds were used for debt repayment.
- Internal manufacturing as margin lever: Trial runs for the company's own internal manufacturing facility are expected to start in December/January/February, which management says will further increase margins. A re-rolling machine has also been ordered for Kutch to help increase productivity.
- Worker retention supports productivity: Zero worker turnover is attributed to full accommodation and canteen facilities, which management claims no other tower manufacturer in India provides. This drives productivity and quality.
Nimish Vashi: "This is the biggest manufacturing facility in one roof in India. And we are the only company in India to provide the full accommodation to our worker."
Capacity Expansion & New Equipment
- New machine for heavier plate: A machine capable of handling plate thickness up to 70 mm, versus the previous maximum of 55 mm, is arriving at Bombay on the 13th. Production is expected to start by month-end, increasing productivity, tower count, and tonnage.
- Kopal tonnage ramp: Tonnage at Kopal is expected to increase from the current 7,650 tonnes per month to 10,000 tonnes per month by December.
- Tonnage growth trajectory: Tower fabrication tonnage is expected to grow approximately 30–35% per year.
- Future expansion gated: Once the internal manufacturing facility is running and customers are satisfied, management will consider further expansion. A 5 MW machine may be introduced in India, and a Rajasthan plant would be considered only after that.
Nimish Vashi: "First of all, my focus is very clear to establish this both facility 100% utilized by and both facilities may -- internal will be in manufacturing from our company only."
FY28 Outlook & Order Book
- Volume target: 500+ towers manufactured in FY28, with both Karnataka and Kutch plants fully running. The Kutch plant alone is targeted to add 200 towers of growth.
- EBITDA per tower ambition: Management expects ₹30–40 lakhs per tower, with a floor of ₹30–33 lakhs, supported by full utilization and internal manufacturing.
- Market share goal: With both facilities fully operational, the company is targeting approximately 25% market share.
- Order book timing: FY28 order books are expected to start finalizing from December onwards. IPPs and customers are waiting on steel price movements before committing.
- Karnataka plant position: The Karnataka plant is currently fully booked, and management expects customers to begin negotiating for the next financial year.
Nimish Vashi: "So in FY28, maybe it is a very good -- we have a very good result because of almost our Karnatak plant right now it is a full book and then normally the people will start to negotiate to next year -- next financial year for the -- they want to book our facility."
Investor Relations & Governance Notes
- First earnings call: This was the company's first call since listing in August 2026. Management acknowledged issues with timely uploads and committed to better coordination with the IR advisor going forward.
- Stock price concern: An individual investor raised concern about the stock falling 10% multiple times without explanation. The IR advisor attributed it to a first-time process issue, not mismanagement. Management expressed worry but did not provide a substantive explanation for the declines.
- Share purchase clarification: Management stated they are not buying any shares from the market.
- Plant visit invitation: Management invited analysts and investors to visit the plant, with machine erection around the 18th–19th and management present for the full week.
Nimish Vashi: "frankly speaking, this is also first experience in my life. We are not going to at and I am not buying any single share from share market to... so 100% we discuss with the seller by next time you see... and I am also worried actually we are also in the same boat now."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Kutch revenue contribution | Begin contributing after OEM and ISO approvals received; orders already in hand | Last two quarters FY27 (Dec–Mar) |
| ISO certification | Certificate at 14,500/15,000 | End-November |
| OEM plant approvals | Envision, Sanvian, and others to approve Kutch plant | First week of December; full procedure by 15 December |
| New machine production start | Machine arriving 13th; production from the new machine | By end of month (November) |
| Kopal tonnage increase | From 7,650 tonnes/month to 10,000 tonnes/month | By December |
| Internal manufacturing trials | Trial runs at Karnataka plant | December/January/February |
| FY28 tower volume | 500+ towers manufactured | FY28 |
| FY28 EBITDA per tower | ₹30–40 lakhs per tower, minimum ₹30–33 lakhs | FY28 |
| FY28 market share | ~25% market share | FY28 |
| FY28 order book finalization | IPPs and customers begin committing | From December onwards |
| Tonnage growth rate | Tower fabrication tonnage growing ~30–35% per year | Annual |
Key Metrics
| Metric | H1 FY27 |
|---|---|
| Revenue from operations | ₹153.97 cr, +272% YoY, surpassing full FY26 revenue of ₹143.27 cr in six months |
| EBITDA | ₹36 cr, +256% YoY |
| EBITDA margin | 23.4%, vs 24.5% in FY26; integrated supply mix shift moderated percentage margin |
| PAT | ₹14.39 cr, +539% YoY |
| Absolute EBITDA per tower | ₹32.82 lakhs, +105% YoY from ₹16.03 lakhs |
| Towers produced | 107 towers, +73% YoY vs 62 towers in FY26 |
| Integrated supply revenue share | ~64% of H1 FY27 revenue |
| Confirmed order book | ₹395 cr, covering 320 towers as of Oct 13, 2026; executable by Q1 FY28 subject to customer schedules |
| Letters of intent | ₹44 cr for 44 towers |
| Annual manufacturing capacity | 612 towers: 420 at Kopal, Karnataka and 190 at Kutch, Gujarat |
| Kopal capacity utilization | ~70% |
| Kopal monthly tonnage output | 7,650 tonnes, expected to reach 10,000 tonnes by next December |
| H2 revenue share (historical) | 70–80% of annual revenue typically generated in H2 |
| FY28 volume target | 500+ towers |
| FY28 EBITDA per tower expectation | ₹30–40 lakhs, minimum ₹30–33 lakhs, may go higher |
| Top two customer revenue contribution | ~45–47% |
| Total depreciation | ₹22 cr |
| Workforce | 700 workers |