Key Takeaways
- H1 revenue surged 55% YoY, on track for FY27: Defense grew 56% and healthcare nearly tripled, while the INR31.8 crore order book provides 1.2x coverage of the reiterated ~INR48 crore full-year target.
- Unit 2 is live but margin-dilutive for now: The new facility added 15 machines and 45+ people, but its fixed costs hit other expenses before full utilization, compressing EBITDA margin from 35.2% to 30.88%.
- Management is holding the line on 35% EBITDA margin: The commitment stands for FY27 and FY28, with the H2 ramp of Unit 2 expected to absorb the overhead that dragged H1.
- The FY32 ambition is INR300 crore, with an INR500 crore stretch: A concrete plan targets INR300 crore via Unit 3, assemblies and new plants; a separate, very early-stage prospect discussion keeps the INR500 crore aspiration alive.
- What to watch next quarter: Whether Unit 2’s H2 revenue contribution tracks toward the ~INR15 crore target, the pace of margin recovery back above 35%, and any tangible progress on the Unit 3 business plan.
Unit 2 Ramp-Up: The Near-Term Margin Story
- Operational but under-absorbed: Unit 2 was inaugurated on August 14th with 15 machines and 45+ people by September, and has started contributing revenue. However, rent, electricity, security and other fixed operating costs are running ahead of the revenue contribution, which pressured other expenses by 1.75% YoY.
- H2 revenue target set: Management expects Unit 2 to contribute approximately ~INR15 crore in H2 FY27, a figure that would absorb much of the current overhead and support the margin recovery.
- Full potential is multiples higher: At peak utilization, Unit 2 can contribute INR50-60 crore, with complex parts potentially adding another INR5-6 crore. Vertical integration of assemblies could lift revenue by at least 10-15% using the same facility.
- Capacity build-out continues: 15 of 30 planned machines have arrived; installation and commissioning are ongoing. Total CNC machines across both units reached 33 as of September 30th, with headcount at 125.
- H1 seasonality provides context: H1 typically contributes ~40% of full-year performance and H2 ~60%, so the margin dip and lower revenue base are partly structural, not purely operational.
Basavaraju .K.S: "EBITDA for next 2 years we have always committed. So yeah, I mean, we were going to achieve at least 35%, uh, you know, for next 2 years. It was committed already and we are in track with that."
Revenue Growth & Segment Mix
- Defense remains the anchor: Defense contributed 61% of H1 revenue at INR12.86 crore, growing 56% YoY. Management expects defense to remain the major contributor even after the next two years.
- Healthcare nearly tripled: Healthcare reached ~11% of revenue at INR2.24 crore, up from a small base, signaling diversification beyond the core defense-aerospace franchise.
- Aerospace holds at 27%: Aerospace contributed INR5.79 crore, and the target is to move it to 30% of revenue over time.
- New parts are the growth engine: 250 new parts were deployed last year, of which ~140 are already in production and expected to generate ~INR15 crore this year. More than 100 developed parts are expected to convert to production orders during FY27 and FY28.
- One new customer added during the half, while the largest customer’s concentration reduced from 35% to 33% even as absolute revenue from that customer increased.
Basavaraju .K.S: "we don't want-- we don't have plan to reduce the customer concentration, so we always have to increase the customer concentration. So the largest customer reduced from 35% to 33%, but the parallelly we have increased our revenue."
Margin Walk: What Compressed H1
| Margin driver (H1 FY27 vs H1 FY26) | Impact |
|---|---|
| Cost of material consumed (product mix, raw material, production costs) | –3.8 pp |
| Other expenses (Unit 2 rent, electricity, security, fixed opex) | –1.75 pp |
| Depreciation (Unit 2 fixed assets and machinery) | –1.27 pp |
| Net EBITDA margin change → 30.88% | –4.32 pp (H1 FY27 vs H1 FY26) |
- Absolute profit still grew: EBITDA rose 36% and PAT rose 21% in absolute terms despite the margin compression, because the revenue base expanded 55%.
- Material cost pass-through is structurally difficult: On ongoing projects, OEMs do not increase prices mid-project, and the same constraint flows down to Apsis. The company intimates customers during next order finalization or repeat orders to get revised prices, and absorbs the impact if it is significant.
- Working capital moved on payables, not operations: Net working capital days increased because long-outstanding payables of ~INR1.5 crore, previously held for quality issues, were paid down. Receivable days held at ~45 and inventory days stayed in the 56-78 day range. Management expects net working capital days to remain around 60 to 65 going forward.
Basavaraju .K.S: "Even my customer, once they make their budget, it's very difficult to convince them. ... generally we avoid and go back to customer and try to convince them."
The Capacity Roadmap: Unit 3, Assemblies & FY32
- FY28 plan: ~INR80 crore with both Unit 1 and Unit 2 at full capacity.
- FY32 committed plan: INR300 crore, supported by Unit 3, assembly operations, and new plants. The 5-year plan targets ~50-55% YoY growth.
- INR500 crore aspiration still alive: Management is discussing a potential project with a prospect at a very initial stage that could lift the trajectory to INR500 crore, but the committed plan remains INR300 crore.
- Unit 3 is early-stage and unfunded: Construction is planned to start by FY29 on a greenfield site near Bangalore Airport, but the business plan and budget are not yet decided. Management will decide the investment plan only after a "foolproof business plan." Unit 3 will focus on complex machined components, increasing the proportion of complex parts from ~60% to up to 80%, with maximum automation.
- Assemblies offer a nearer-term revenue lift: Apsis is moving up the value chain into assemblies with ~50 new components at the RFQ stage. Vertical integration of assemblies can increase revenue from existing facilities by up to 10%, potentially reaching ~INR90 crore.
- Sequencing is undecided: Management has not yet decided whether to pursue Unit 3 (specialized complex parts) or the medium-critical/assembly expansion first.
- B2S (Build-to-Spec) exploration: Apsis is thinking about design and testing for the submodule level, though OEMs retain authority for entire system design. Plans are at a very initial stage.
Basavaraju .K.S: "that INR500 crore aspiration still we have. We have not dropped that plan. ... the committed plan is INR300 crore as of now."
Pipeline, Orders & Scaling Discipline
- Order book supports FY27: The INR31.8 crore order book covers 1.2x of the ~INR48 crore FY27 revenue target, with H2 needing ~INR26.8 crore.
- Minimum pipeline maintained at INR100 crore, with a conversion ratio of roughly 30-35%. Management did not disclose the current specific bid pipeline value.
- Scaling is deliberately slow: Management emphasized that precision machining components cannot be scaled 1x or 2x because quality must remain constant. Medium-critical parts offer an opportunity for scaling at a bigger level, and Apsis is targeting more opportunities within existing defense and aerospace machining: engine-related components, other machining applications, and air taxis.
- Apsis remains sole supplier for the ~100 new parts added, reinforcing the moat around qualified precision manufacturing.
Basavaraju .K.S: "the reason why we are not scaling in 1x, 2x, because the way our component cannot be scaled in that manner. We have to go in proper quality by keeping the quality constant for our customers."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue | ~INR48 crore; order book covers 1.2x | FY27 full year |
| Unit 2 H2 revenue contribution | ~INR15 crore | H2 FY27 |
| EBITDA margin | At least 35% | FY27 and FY28 |
| PAT margin | Up to 25% | FY27 and FY28 |
| FY28 revenue | ~INR80 crore with both units at full capacity | FY28 |
| Unit 3 construction start | By FY29, near Bangalore Airport | FY29 |
| FY32 committed revenue | INR300 crore via Unit 3, assemblies, new plants | FY32 |
| Net working capital days | ~60 to 65 days | Going forward |
| Revenue mix target | Aerospace to reach 30% of revenue | Over next 2 years |
Key Metrics
| Metric | H1 FY27 |
|---|---|
| Revenue from operations | ₹21.17 cr, +55% YoY |
| EBITDA | ₹6.52 cr, +36% YoY |
| EBITDA margin | 30.8%, vs 35.2% in H1 FY26; material cost and Unit 2 startup costs impacted margins |
| Profit after tax | ₹3.97 cr, +21% YoY |
| PAT margin | 18.7% |
| Diluted EPS | ₹3.29, lower YoY due to additional IPO shares |
| Order book | ₹31.8 cr, 1.5x H1 revenue; covers H2 target 1.2x |
| FY27 revenue target | ~₹48 cr, reiterated; H1 achieved 44% of target |
| FY28 revenue plan | ~₹80 cr, with both units at full capacity |
| FY32 revenue aspiration | ₹300 cr, supported by Unit 3, assembly, and new plants |
| Committed EBITDA margin guidance | At least 35% for next 2 years (FY27 and FY28) |
| PAT margin guidance | ~23% for FY27 and FY28 |
| Defense segment revenue | ₹12.86 cr, +56% YoY, 61% of total revenue |
| Aerospace segment revenue | ₹5.79 cr, +27% YoY |
| Healthcare segment revenue | ₹2.24 cr, nearly tripled YoY |
| Net worth | ₹52.9 cr |
| Net cash | ~₹11.6 cr |
| Cash and bank balance | ₹15.07 cr; cash equivalents per cash flow statement ₹12.95 cr |
| Borrowings | ₹3.46 cr |
| Debt-to-equity ratio | 0.07 |
| Interest cover | 25 times |
| Capacity investment in H1 | ₹23.33 cr, funded from IPO proceeds; net block doubled to ₹24.61 cr |
| Operating cash flow | ₹2.78 cr |
| Receivable days | 45 days |
| Inventory days | 56 days |
| Payable days | 38 days |
| Net working capital cycle | 63 days; expected to remain 60–65 days going forward |
| Total CNC machines | 33 as of 30th September; 18 at Unit 1, 15 at Unit 2 |
| Employees | 125 across 28,500 sq ft |
| Unit 1 capacity utilization | 100% |
| Unit 2 capacity utilization | 30–35% as of September and October; 15 of 30 planned machines installed |
| Unit 2 H2 FY27 expected revenue contribution | ~₹15 cr |
| Unit 2 peak utilization revenue potential | ₹50–60 cr from machining; up to ₹90–95 cr combined with Unit 1 and vertical integration |
| New parts deployed last year | 250; ~140 already in production, expected to generate ~₹15 cr this year |
| Parts expected to convert to production orders | More than 100 during FY27 and FY28 |
| Revenue from most complex parts | ~40% of total revenue |
| Bid pipeline | Minimum ₹100 cr maintained; conversion ratio ~30–35% |
| Customer retention | 100% |
| Largest customer concentration | 33% of revenue, down from 35% |
| Total SKUs | 500–600; ~60% are sole-supplier components |