Atlanta Electricals Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/ep3yei9mqmb1i6z8ruw4p356.pdf

Key Takeaways


The EHV Prototype Gateway

Niral Patel: "These prototypes are not just engineering milestones, they are gateways to significantly larger addressable market. Once delivered and validated, they will allow us to scale our EHV order books in a meaningful way."

Vadod Ramp-Up & Capacity Expansion

Niral Patel: "Industry convention for a transformer facility of this scale and voltage class typically projects a payback period of five to seven years. Vadod alone contributed nearly INR495 crores of revenue in first seven months of operation. Based on this trajectory, we are well on the course to achieve payback in three to four years' timeline, which is the best to our knowledge is largely unheard of in the transformer manufacturing industry."

Demand Environment & Competitive Landscape

Anand Sharma: "I am sure that whatever amount of capacity Indian manufacturers are going to put up, it is going to still fall short of the requirement. The requirement is going to edge over the supply side for at least next 5 years for sure."

Supply Chain & Input Costs

Anand Sharma: "We have been telling on the last couple of calls that the situation around the supply of conductors is improving because many of the manufacturers, Indian manufacturers who had announced their plans to expand capacities, those expanded facilities came to life and we have started now taking the supplies."

Margins & Financial Position

Niral Patel: "As of today, with that margin improvement and cost coming in, taking off, I mean, setting off the margins, we would be like—we would like to share that the margins for coming times would be fairly stable in nature."

Export Strategy


Guidance & Commitments

CommitmentSpecificsTimeline
400kV short circuit testingTransformer to be sent for short circuit testingComing quarter (Q1/Q2 FY27)
765kV technology tie-upClosure of tie-up with one of multiple agencies under discussionNext couple of months
IDT facility (Unit 6) commencement~5,000 MVA capacity addition at VadodBefore end of calendar year 2026
Tank and radiator backward integrationFacility commencement with robotic automationDuring FY27; benefits in FY28
Vadod utilization ramp65% utilization in FY27, 100% in FY28FY27 / FY28
Revenue growth40% CAGRNext 3 years
Export revenue share15% of total revenueNext 3 years
Net working capital daysIncrease to 80s and 90sFY27 and FY28
Merger of Atlanta Trafo LimitedProcedure to commenceWithin a short span
All debt repayment₹340 cr fully repaid; any new term loan drawn to be fully paid offAlready achieved; coming financial year if drawn

Key Metrics

MetricQ4 FY26
Revenue from operations₹747.6 cr, +81.7% YoY and +58.5% QoQ
EBITDA₹149.6 cr, +117.9% YoY
EBITDA margin19.99%, vs 16.7% in Q4 FY25
Profit after tax₹102.2 cr, +128.9% YoY
FY26 consolidated revenue₹1,851.5 cr, +48.8% YoY, ahead of 40% growth target
FY26 EBITDA margin18.6%, expanded 300 bps from 15.6% in FY25
FY26 PAT₹201.8 cr, +70.1% YoY
220kV class revenue share~52% of FY26 revenue
Total MVA produced (FY26)22,943 MVA across all five units
Vadod facility (Unit 4) production6,960 MVA in ~7 months since July 2025
Vadod facility utilization~39% of 30,000 MVA nameplate capacity over seven months
New orders booked (FY26)₹2,507 cr
Unexecuted order book₹2,493 cr as of 31st March 2026
Term debt outstandingNil, all long-term debts fully repaid as of 31st March 2026
Operating cash flow (FY26)₹184 cr
Net working capital days (FY26)64 days
IPO proceeds deployed₹395.46 cr of ₹400 cr fresh issue deployed
Vadod facility revenue contribution~₹495 cr in first seven months of operation
Order book with price variation clause~75%
FY27 Vadod utilization target65%, with ramp-up to 100% in FY28
Export revenue target15% of total revenue in next 3 years
IDT facility additional capacity5,000 MVA, to commence operations during FY27
Tank and radiator capex₹170–180 cr, IDT capex ~₹65 cr