AXISCADES Technologies Ltd Q1 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/pejr42b0znddlj0yoqlw4mk0.pdf

Key Takeaways


Core Business Performance

Dr. S Ravinarayanan: "Even if I get the product ready today, it will probably take about three months for us to get the final approval. So, this is where everything is getting pushed to a little this thing, and also manpower."

Order Book & Program Wins

Dr. S Ravinarayanan: "We have set up a target of over 40% year-on-year growth and we are all set for that. We have an order book of Rs.1,260 crores for this financial year FY26 and Rs.1,827 crores for the next financial year, that is FY27, the forecast visibility plus order book totaling to Rs.3,087 crores."

Hyperscaler & ESAI Expansion


Infrastructure Investment & Power 930 Ambition

Dr. S Ravinarayanan: "This year and next year, we are working investing about \$200 million, about Rs.1,500 crores in infrastructure before the beginning of '27."

Execution Risks & H2 Dependency


Margin & Profitability Outlook


Guidance & Commitments

CommitmentSpecificsTimeline
Core revenue growth40%+ YoY growth in defense, aerospace, ESAI (revenue, EBITDA, PAT)FY26
Overall revenue growth~25% growth including core and non-coreFY26
EBITDA margin improvement300 bps improvement over previous yearFY26
Core EBITDA margin19.2% to 19.8%FY26
Core revenue CAGR40% CAGR in core verticalsFY26-FY28
Core EBITDA margin target~19.5%By FY28
Power 930 revenue targetRs.9,000 crores (\$1 billion)By 2030
Infrastructure investment\$200 million (~Rs.1,500 crores) deployedBefore beginning of 2027
Facility Phase 1A (DAC)ReadyBy March
Acoustic lab for AmazonReadyBy October/November
BrahMos wiring harnessPart of BrahMos programBeginning of FY27
EHWT homing receiverFirst production unit deliveryNovember/December of this year
KUSHA DBF units (5 nos.)Delivery completedBy March this financial year
Non-core resolutionAnswer on restructuringBy beginning of next year
ESOP costRs.40-50 croresFY26

Key Metrics

MetricQ1 FY26
Consolidated revenue₹244 cr, up ~9% YoY
Reported EBITDA₹34 cr, up 9% YoY; margin at 14%
Normalized EBITDA₹34 cr, up 86% YoY from ₹18 cr (adjusted for one-time ESOP write-back of ₹12.9 cr in Q1 FY25)
Normalized EBITDA margin14%, expanded from 8.2% in Q1 FY25
Consolidated PAT₹21 cr, up 25% YoY from ₹17 cr
Core segment revenue₹182 cr, up 17% YoY from ₹156 cr
Core segment normalized EBITDA₹34 cr, up 61% YoY from ₹21 cr; margin improved to 18.6% from 13.5%
ESAI revenue growth34% YoY
Defense revenue growth23% YoY
Aerospace revenue growth8% YoY
Non-core verticals revenue growth-9% YoY, due to macro pressures in automotive and timing-related order shift in energy
FY26 revenue growth guidance~25% (consolidated, including core and non-core)
FY26 EBITDA margin improvement guidance300 bps improvement over previous year, after factoring ESOP cost
Core segment 3-year CAGR target40% (FY26–FY28)
Core segment EBITDA margin target (FY28)~19.5%
Order book (FY26)₹1,260 cr
Order book (FY27)₹1,827 cr
Order book and forecast visibility (total)₹3,087 cr
Defense order book (FY26 deliverable)~₹540 cr (could reach ₹600 cr depending on delivery)
Defense order book (FY26 + FY27)~₹1,500 cr
ESAI order book and forecast visibility~₹210 cr
Aerospace order book~₹450 cr
Tank trailer order₹200 cr
Attrition19%
ESOP cost (Q1 FY26)~₹3 cr
ESOP cost (FY26 full-year target)₹40–50 cr range
Weighted average interest rate on working capital debt~9.5% (debt of ~₹48 cr)
Long-term debt~₹101 cr with an alternate investment fund
Average finance cost~8–8.5%
Revenue from US27% of total revenues
Infrastructure investment before FY27~$200 million (~₹1,500 cr)
Per LCA (Tejas) revenue₹12–13 cr per aircraft
EHWT homing receiver value~₹1.5 cr per torpedo; ~20 units per year, ~100 units over five years