Key Takeaways
- Revenue surged 34% but EPS lagged: Consolidated revenue hit INR105.79 cr (+33.75% YoY) as the Hollywood strikes resolved, yet EPS grew only 9.38% to INR17.85, flagging a need for sustained value conversion.
- The strike hangover is clearing, not cleared: Projects that restarted in January ran only through April/May; the next wave of post-production work lands from July–September, making FY25 a heavily back-ended story.
- A material receivables overhang persists: INR15 cr of INR63 cr in receivables is >180 days old, now on an installment plan with a client facing North American market downtime.
- A financial filing error has bruised credibility: Wrong consolidated numbers were uploaded to the NSE, spotted within an hour but corrected only after the market opened, triggering a sharp sell-off and an unanswered question about regulatory scrutiny.
- What to watch next quarter: Whether the INR15 cr collection plan holds, whether the promised August/September surge materializes into billed revenue, and whether the additional internal controls restore investor confidence.
The Strike Aftermath & Revenue Phasing
- Strike resolution timeline: The writers' and actors' strikes ended around October/November 2023; projects on hold came to the floor around end-January and ran through April/early May. Projects under development started from end-March through April, with some starting by end-May. These will enter post-production around end-July, August, September, based on official release dates from studios like Marvel, Disney, Warner Brothers for June/July 2025.
- 2025 movie slate is the real catalyst: 2023 and 2024 had very few bigger movies released; the majority were pushed back to 2025 (Thunderbolts, Captain America, Passion of Christ, Batman 2). 2025 is heavily packed with releases from May through October.
- FY25 growth is back-end loaded: Management estimates ~30% revenue growth for FY25, but first-half growth will be much less than 30%; the majority of work comes from September to end-March, with the second half compensating at higher than 30% growth.
- Surge timing: From August/September onwards, the company sees a market surge based on confirmed release dates of movie projects announced by major production networks; worst-case scenario is September.
- Recruitment timed to the surge: The company plans recruitment by June/July, not August, to have capacity ready when work arrives.
Balakrishnan: "If you look into maybe 75% of what we work in India is discounted, but 25% what it comes out of these overseas locations would add to our margin. So that is where we've been balancing out this current situation."
Project Pipeline & Order Book
- No total order book disclosed: When asked for total order book size executable in FY25, management listed individual projects and offered the 30% growth estimate instead of a specific backlog figure.
- Blockbuster sequel: Anticipated to generate significant revenue of INR18 cr over the next 10 to 11 months.
- Exclusive vendor project: Scheduled for September 2024, spanning 8–10 months across 10 episodes, with a book value of INR34 cr.
- Previs for video game cinematics: Commencing in coming days, spans 10 months, from an AAA-level gaming company, expected revenue of INR2.5 cr.
- Other pipeline items: A June 2024 project with approximately 500 shots; a product modelling project for an eyewear brand expected to bring INR4.5 cr over 3–4 months.
- Diversification post-strike: The strike taught the company to look into other avenues; they have been working on short and real-time projects for corporate films, gaming cinematics, and diversified into markets like Italy, Spain, France in regional languages.
Receivables & Working Capital
- INR63 cr total receivables: Broken into INR15 cr >180 days and INR48 cr <180 days. The >180 days portion is on a declining pattern; clients are production houses of repute, with payment models arranged in parts due to industry downtime.
- INR15 cr long-pending bucket: A settlement/program has been made with that client for weekly or monthly installments; it is a temporary requirement due to market downtime in North America where these studios are located. Management declined to give a precise collection timeline, calling it "a little early," and expects to provide one by the next investor call.
- No write-off risk claimed: Other than the INR15 cr with installment arrangements, management stated there will not be any write-off on receivables; the company can collect the money well within stipulated time limits.
- Canadian subsidiary receivable: The Canadian entity owes INR10 cr to the standalone company, not adjusted in consolidation, due to collection pending from the Canadian side because of international market issues affecting their fund flow.
- Normalized working capital cycle: 60 days, including work in progress and debtors minus payables. The current INR63 cr figure looks bigger due to February/March bookings; the normal credit cycle is 60–90 days, with some already collected in April.
- Other current assets: Comprised of work in progress (roughly INR19 cr, unbilled value where expenditure is being incurred) and GST refund (INR5 cr plus).
Margins & Pricing
- Pricing strategy is a balancing act: Approximately 75% of India work is done at discounted rates; the 25% of work from overseas locations (where the company competes with smaller/mid-level overseas studios) adds to margin, balancing the overall situation.
- Cost advantage vs overseas competitors: Per-day rates of USD150 in India vs USD500–600 in the UK enable better margins on work sourced from overseas.
- Margin guidance: Management expects to maintain the EBITDA margin achieved in the previous year and looks to maintain a PAT margin of 35%, which was done last year.
- Direct production mix improving: Direct production increased from 30% to 35%; subcontracting is 65%. The target is to move to 45–50% direct by around the first half of 2025 (by March 2025), with more direct orders expected from the second half of 2024.
- Revenue split by task (approximate): 30% Roto, 20–25% Paint, and the rest Composting and other at 45% total. Management initially resisted providing this split, calling it "very intricate," and the "45% each" phrasing in the transcript appears contradictory.
The Filing Error & Credibility Question
- What happened: A set of financials was prepared one day in advance for the board meeting. During a mock run, an accounting standard treatment error was caught and corrected before the board approved the correct financials. However, the wrong set was attached while uploading to NSE on April 30, 2024. The error was identified within an hour of upload. The company emailed NSE on May 1 (a holiday) and tried to reach them before market opening on May 2 but could not get them online until 10:30–10:45 AM. NSE said they would discuss internally with their legal team.
- Market impact: An analyst noted that at 10:30 AM the circuit opened with huge buying, suggesting a leak, while the clarification timestamp was 12:21 PM. Management did not directly address whether there was a leak or whether they have asked NSE for clarification on the delay.
- SEBI inquiry status: When asked whether SEBI has approached or questioned the company, management did not directly answer.
- Remedial action: The company is adding an additional layer of internal control to prevent recurrence and intends to stay committed to regaining investor confidence.
- Shareholder loss: An analyst pressed management to consider reimbursing shareholders who lost money, stating "the entire brunt has been borne by anyone who was holding the shares those days... there is actual tangible loss." Management did not commit to any reimbursement.
Midha: "We acknowledge the investors' disappointment due to this inconvenience caused and intend to stay committed to regaining the investor confidence by adding an additional layer of internal control, which will in turn ensure stricter internal control and corporate governance working in the interest of the investor fraternity."
People, Capabilities & Strategic Moves
- Senior talent hires: Onboarded Mr. Dan Levitan as VFX Supervisor (30+ years, 85 feature films, credits at Disney, DreamWorks, Warner Brothers, Paramount/CBS) and Mr. Zameer as COO (20+ years, associations with ILM, Double Negative, MPC).
- Workforce scaled to ~500: Post-IPO, employee count expanded to approximately 500 as of March 2024.
- Upskilling at full participation: 100% participation rate in upskilling programs converting 2D digital VFX employees to 3D concept artists. Artists were also trained in real-time content creation using Unreal Engine and other tools for creating CG content quickly.
- Strategic partnerships in discussion: The company has appointed an advisor working on potential partnerships, in close discussion with a few potential partners, primarily focused on incentive-location and technology-driven companies where the company would get returns back from the government from foreign production.
- Government incentive utilization: The company plans to utilize the government's 30% minimum project expenditure rebate (max INR30 cr per project) for VFX work on foreign/international content. For VFX projects, they can apply based on a contract with a potential international client without needing an interim date. Management noted that more clarity is yet to flow in on the scheme details.
- Awards won: Best VFX TV Series International, Best VFX Shot in TV Series International, Best VFX Shot in Feature Film International at VAM Awards 2024.
Balakrishnan: "And we are not here to do any mislead or cheaper things here in this market, but rather, we wanted to focus on our business, we want to take this company to a global perspective and global trend."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | ~30% growth, fully organic | FY25 |
| Revenue phasing | First half growth much less than 30%; second half higher than 30% to compensate | FY25, surge from Aug/Sep onwards |
| EBITDA margin | Maintain previous year's level | FY25 |
| PAT margin | Maintain 35% | FY25 |
| Direct production mix | Move from 35% to 45–50% | By around first half of 2025 (March 2025) |
| Blockbuster sequel revenue | INR18 cr | Over next 10–11 months |
| Exclusive vendor project | INR34 cr book value, 8–10 months, 10 episodes | Starting September 2024 |
| Previs for video game cinematics | INR2.5 cr revenue, 10-month span | Starting in coming days |
| Recruitment | Hire ahead of surge | By June/July |
| INR15 cr receivable collection timeline | Precise timeline to be provided | By next investor call |
| Internal controls | Additional layer of internal control added | In progress |
Key Metrics
| Metric | Q4 FY24 |
|---|---|
| Total revenue (consolidated) | ₹105.79 cr, +33.75% YoY |
| Total revenue (standalone) | ₹103.19 cr, +46.34% YoY |
| EBITDA (consolidated) | ₹52.18 cr, +34.35% YoY |
| EBITDA (standalone) | ₹51.68 cr, +40.69% YoY |
| Profit before tax (consolidated) | ₹50.61 cr, +34.95% YoY |
| Profit before tax (standalone) | ₹50.18 cr, +41.64% YoY |
| Profit after tax (standalone) | ₹26.44 cr, rising by ₹36.19 cr YoY |
| EPS (consolidated) | ₹17.85, +9.38% YoY |
| EPS (standalone) | ₹17.69 |
| Revenue growth guidance (FY25) | ~30%, weighted toward H2 as project surge expected from August-September |
| EBITDA margin guidance | Maintain previous year level |
| PAT margin guidance | Maintain ~35% |
| Employee count | ~500 as of March 2024 |
| Direct production mix | 35% direct studio resources, 65% from studios; target 45-50% direct by March 2025 |
| Standalone receivables | ₹63 cr, of which ₹15 cr >180 days and ₹48 cr <180 days |
| Amount receivable from Canadian subsidiary | ₹1.83 cr (within <180 days bucket) |
| Work in progress | ~₹19 cr |
| Net working capital cycle (normalized) | 60 days |
| Revenue split: Roto | ~30% |
| Revenue split: Paint | ~20-25% |
| Revenue split: Composting and other | ~45% |
| Visible pipeline: exclusive vendor project (10 episodes) | ₹34 cr book value, starting September 2024, spanning 8-10 months |
| Visible pipeline: blockbuster sequel | ₹18 cr expected revenue over 10-11 months |
| Visible pipeline: product modelling project (eyewear brand) | ₹4.5 cr expected revenue over 3-4 months |