Bharat Heavy Electricals Ltd Q4 FY2022 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/p67z6m6p1ztk45424r6uhgn4.pdf

Key Takeaways


The Turnaround: Profitability Restored, but Quality Check Needed

Subodh Gupta: "If you see the financials of BHEL (prior financials), it was always in the range of 60%. So that really further impacted us. Otherwise, things are well under control and whatever we have already factored into this material cost into our current financials also."

The Margin Story: Material Costs Are the Villain

Subodh Gupta: "Those will be coming but after some time because we cannot show under investment in the company. So those are also reflected as contract asset. Otherwise, it's indirectly a funding for the projects from BHEL."

Thermal Power: A Pipeline That Must Convert

Dr. Nalin Shinghal: "So, as I already said, we are seeing a pipeline of almost 7,700 Megawatt, you know because Talcher, Talabira, Adani, Bhandora then Singrauli, Lara, all these are there, so we are expecting these ordering to happen in the very near future with you know the crunch on the power-supply side, this is going to be speeded up."

Diversification: Planting Flags Beyond Thermal

Dr. Nalin Shinghal: "We have explored that, but at this point I think the call is not to get into this."

Balance Sheet & Cash Flow: Quietly Strengthening


Guidance & Commitments

CommitmentSpecificsTimeline
Thermal order inflow7,700 MW visible pipeline (Talcher, Talabira, Adani, Bhandora, Singrauli, Lara) to convert to orders"Very near future," most by FY24
Defence order growthOrder booking to increase further from FY22 record of ₹1,500 CrFY23
FGD ordering pickupState and private sector ordering to begin, given country's commitmentsNo specific timeline; visibility not yet there
Asset monetizationProcedural clarity expected on identified properties"Quite soon"
PVC benefit from COVID extensionsAdditional PVC benefit to accrue once time extension requests are approved by customersUpon customer approval
CapEx₹231 Cr plannedFY23

Key Metrics

MetricQ4 FY22
Revenue from operations₹7,600 cr, up 13% YoY
EBITDA₹1,280 cr
Profit before tax₹1,098 cr, vs loss of ₹1,385 cr in Q4 FY21
Profit after tax₹909 cr, vs loss of ₹1,033 cr in Q4 FY21
Manufacturing, admin, selling & distribution expenses5.5% of turnover, vs 7% in Q4 FY21
Other expenses₹(385) cr, including provisions of ₹(842) cr, ERV gain of ₹91 cr
FY22 total order booking₹23,693 cr
Total outstanding order book₹1,02,542 cr (Power: ₹85,664 cr, Industry: ₹11,836 cr, Exports: ₹5,042 cr)
FY22 material cost72% of revenue, all-time high vs historical ~60%
FY22 defence order booking₹1,500 cr, highest ever
Thermal power project pipeline~7,700 MW total, with ~4,000 MW in advanced bidding
Nuclear order (6x700 MWe TGs)₹10,800 cr
FY22 commissioning/synchronization4,119 MW of power plants plus 1,460 MW of steam generators
Cash and bank balances, net of borrowings₹2,409 cr, vs ₹1,868 cr at end of FY21
Trade receivables₹6,229 cr, lowest in 10 years; total receivables including contract assets ₹33,169 cr