Key Takeaways
- Volume-led revenue nearly doubled: Revenue hit ₹55.5 cr, up from ₹28.2 cr YoY, driven by a 33% volume surge and strong real estate demand, even as selling prices softened on lower input costs.
- Margins held at 22%+ through a soft quarter: EBITDA margin sustained at ~22% despite the seasonal Q1 slowdown; management calls this level sustainable and sees upside as demand and pricing recover post-monsoon.
- Two new plants on an aggressive clock: Wada Phase 1 is targeted for commercial production by December 2022, and the SCG JV plant in Ahmedabad by June 2023, together adding 8 lakh cbm of capacity.
- The red-brick substitution story is intact: AAC blocks hold only an 8-9% market share against red bricks at 85-87%, and management sees room for 10-15% price increases because red bricks remain more expensive on a like-for-like basis.
- What to watch next quarter: Whether the Wada plant stays on its December 2022 start timeline, the pace of post-monsoon price recovery, and any update on carbon credit monetization as year-end approaches.
Revenue & Volume Performance
- Top-line surge: Revenue nearly doubled YoY to ₹55.5 cr, with management calling it a phenomenal quarter and a tremendous jump in profitability.
- Volume engine: Volume growth of 33% was the primary driver, reflecting strong real estate demand and increasing penetration into small towns and cities quarter-over-quarter.
- Contract manufacturing tailwind: Manufacturing for Ambuja is helping push product into rural areas through the cement major's dealer-distributor networks, widening the demand base beyond Bigbloc's own sales reach.
- Sales geography concentration: Bombay remains the largest market at ~50% of sales, with Ahmedabad second at ~30%; the sales team has been expanded to cover new markets including Nashik, Roa, Raigad and Alibagh.
- Order book normal for the season: The order book runs at 7-10 days (~₹7 crore), which management considers good for the monsoon period; short order books are an industry norm because AAC blocks are bulky and construction sites lack storage space.
- Seasonal rhythm: Q1 (April-June) sees labor shortage from Holi; Q2 (July-September) slows from monsoon; October through March is the peak construction activity period when demand and pricing strengthen.
Margin Structure & Sustainability
- EBITDA margin held at ~22%: Margins were maintained despite the Q1 slowdown, which management attributes to cost discipline and the underlying demand tailwind in real estate and infrastructure.
- Input cost relief: Prices for both bricks and blocks came down in Q1 because overall costing declined: cement, aluminum powder and metals all witnessed a slowdown, and management sees no further cost reductions ahead as these inputs have stabilized.
- Post-monsoon pricing upside: Management expects an upper trend in pricing from September onward, driven by rising cement costs from infrastructure demand; the potential for 10-15% price increases exists because red bricks remain more expensive on a peer-to-peer comparison.
- PAT margin ambition: Management expects better PAT margins of 12-15% going forward, up from the historical 9-10%, as operating leverage kicks in with new capacity.
- Utilization dipped on weather: Current utilization runs at 85-90%+, with a slight dip in July due to torrential rains in the Western region affecting both Ahmedabad and Bombay operations.
Mohit Saboo: "See frankly the margins that we have announced in the last two quarters, these seem to be sustainable because in spite of the slowdown that we witnessed in Q1FY23, our margins have been maintained accordingly and going forward the real estate and overall infra and everything is supposed poised to grow."
Capacity Expansion: Wada & SCG JV
- Wada plant on track: Land acquisition of 9.5 acres is complete, bank finance is arranged, machinery orders are placed with advances given to suppliers, and commercial construction activities have begun from own sources. Phase 1 (2.5 lakh cbm) is targeted for commercial production by December 2022, with Phase 2 (another 2.5 lakh cbm) by June 2023.
- SCG JV progressing: The joint venture company with Siam Cement Group is incorporated with a 52:48 shareholding ratio (Bigbloc:SCG) and capital infusion is complete. Land identification and acquisition is in progress, intended for completion within the running quarter. The plant will have 3,00,000 cbm capacity, expandable to 5,00,000 cbm, and will be built in one shot rather than phased. Commercial production is tentatively set for June 2023.
- JV product mix strategy: The SCG JV plant will manufacture both AAC blocks and panels; panels are more advanced and expensive, targeted at organized and larger builders like L&T and Lodha, while blocks serve the conversion market from red brick users.
- Full utilization timeline: Management expects new capacities to reach full utilization by December 2023 or March 2024, implying a ramp-up period of roughly 12-18 months from commissioning.
- Pan-India ambition: Post completion of Wada and JV plants, the company intends to go pan-India by setting up plants in the North (near Delhi) and South (near Hyderabad or Bangalore), each with ~5 lakh cbm capacity, expected by FY25-FY26. Internal generations are deemed sufficient for planned expansions, though management is open to raising equity if a good long-term partner is available for these future projects.
- Depreciation and interest trajectory: These costs are expected to remain at similar levels as the current quarter until December 2022, then increase from January 2023 when new plant commercial production starts, though volumes and stability will also rise in tandem.
Raw Material Security & Alternatives
- Pond ash supply secured: Enough stock exists at sourcing ponds for at least the next 5-7 years for the Umargaon/Wada plants (sourced from Dahanu, Nashik, Ukai thermal plants) and for the Ahmedabad plant (Wanakbori, Gandhinagar thermal plants); management sees no issues for the next 10-15 years. The company has been producing from pond ash for 11-12 years and has personnel visiting ponds every 15 days to monitor stock levels.
- Sand fallback option: In the event of fly ash scarcity 5-10 years down the line, plants can shift to sand-based blocks; management notes that the majority of AAC plants in Europe already run on sand, making this a proven alternative.
- AAC panel upgrade path: Existing AAC block plants can be upgraded to manufacture AAC panels with technological modifications and additional machinery, offering a capital-efficient route to capture the emerging panels market as construction methods evolve toward faster, lower-labor solutions.
Mohit Saboo: "We have been producing from pond ash since the last 11-12 years. We have our people visiting the ponds also frequently, every 15 days or something. And there's enough stock at the pond from where we are procuring in such a way that at least for the next five, seven years, we won't face any challenges with that."
Market Structure & Competitive Position
- Red brick substitution is the core thesis: Red bricks still command an 85-87% market share against AAC blocks at just 8-9%, and red bricks remain more expensive than AAC blocks on a peer-to-peer comparison even before accounting for AAC's advantages. Management sees AAC block market share reaching at least 15% within a couple of years, driven by government push toward organized and greener construction, GST imposition on red brick manufacturers, and closures of red brick units.
- Pricing power from the substitution gap: Because red bricks remain expensive, management sees headroom for 10-15% price increases going ahead, effectively pricing up toward the red brick benchmark while still undercutting it.
- Competitive capacity additions manageable: New capacities are coming up in the Bombay-Ahmedabad region, but management does not expect significant impact on sales or pricing because the conversion from brick to block and overall construction activity are increasing at the same pace.
- Service radius economics: The most ideal service radius is 200-300 km, though plants can reach up to 400-450 km; this geographic constraint makes local capacity additions less directly competitive than they might appear.
- Industry capacity data unavailable: When asked about aggregate AAC industry capacity increases over the next 2-3 years, management noted it is not possible to know everyone's planned expansions and could only offer a 12-15 month view, leaving the supply-side picture incomplete for investors.
Mohit Saboo: "Just to address it more, we are replacing red bricks, which is happening at a much faster pace now. Red bricks are still at a share of almost 85%-87%, whereas AAC blocks are at a share of 8%-9% and red bricks today is still expensive then AAC blocks on a peer-to-peer comparison without counting the advantages of AAC blocks."
Carbon Credits & Export Optionality
- Carbon credits held in inventory: The company registered for carbon credits and completed an audit for the period through August 2021; a consultant is being appointed for the next audit, a process that takes 3-4 months. Credits generated remain in stock and were not sold because prices dropped due to the Russia-Ukraine war.
- Monetization timing: Management expects carbon credit prices to reach \$5-\$6 in the next couple of months and plans to monetize at the best possible time, likely in the last quarter of the year when prices have historically been strongest. The upward price trajectory is now resuming after the war-driven dip.
- Export samples approved, viability pending: Product samples sent earlier have been approved in UK and European markets, but exports are not currently viable due to high freight rates. The Wada plant's proximity to Navashiva port is a structural advantage, and management will explore export opportunities once the Wada unit starts and freight rates stabilize.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Wada Phase 1 commercial production | 2.5 lakh cbm capacity online | December 2022 (tentatively) |
| Wada Phase 2 commercial production | Additional 2.5 lakh cbm capacity online | June 2023 (tentatively) |
| SCG JV plant commercial production | 3,00,000 cbm capacity (expandable to 5,00,000) online | June 2023 (tentatively) |
| JV land acquisition | Land identification and acquisition completed | By September 2022 (running quarter) |
| Full utilization of new capacity | Wada + JV plants running at full tilt | December 2023 to March 2024 (tentatively) |
| Revenue target | Approximately ₹500 cr | By end of FY24 |
| PAT margin target | 12% to 15% (up from historical 9-10%) | Going forward |
| Pan-India expansion | Plants in North (near Delhi) and South (near Hyderabad/Bangalore), ~5 lakh cbm each | FY25-FY26 |
| Carbon credit monetization | Sell at best price (~\$5-\$6 expected) | Likely last quarter of the year |
Key Metrics
| Metric | Q1 FY23 |
|---|---|
| Revenue | ₹55.5 cr, up ~100% YoY from ₹28.2 cr |
| EBITDA | ₹12.2 cr, up from ₹3.3 cr in Q1 FY22 |
| EBITDA margin | 22% plus, up from 20.5% previously; management sees as sustainable at this level, could further go up |
| PAT margin expectation | 12% to 15%, better than historical 9%-10% |
| EPS | ₹1.19 per share, up from ₹0.17 per share in Q1 FY22 |
| Volume sales | 1,27,000 cbm, up 33% YoY from 96,000 cbm |
| Capacity utilization | 85%-90% plus; slightly lower in July due to torrential rains; company running at ~94%-95%; industry running at more than 80% |
| Revenue guidance FY24 | ₹500 cr (per an analyst's math, implies ~10,70,000 cbm volume at ~77% utilization; management did not confirm this figure) |
| Order book | ~₹7 cr, representing 7 to 10 days of orders (monsoon season) |
| Working capital cycle | 50 to 55 days |
| Effective tax rate | 25%-26% |
| Sales geography: Mumbai | ~50% of sales |
| Sales geography: Ahmedabad | ~30% of sales |
| Sales geography: Baroda, Vapi, Pune, other towns | ~5%-7% each |
| AAC block price premium vs unorganized players | 3% to 6% |
| Red bricks market share (pan-India) | 80%-85%; AAC blocks at 8%-10% |
| Total pan-India AAC capacity | 1.5-1.8 cr cbm |
| Expected industry capacity increase (next 12-15 months) | 15%-20%, approximately 25-30 lakh cbm |
| Wada plant phase 1 timeline | December 2022, 2.5 lakh cbm capacity |
| Wada plant phase 2 timeline | June 2023, additional 2.5 lakh cbm |
| JV plant with SCG timeline | June 2023, 3,00,000 cbm initial capacity, expandable to 5,00,000 cbm |
| Full utilization of new capacity expected | December 2023 to March 2024 |
| Carbon credits accumulated | 40,000 to 45,000 units till August 2021; generating 60,000 units per year at Umargaon; held and not yet monetized |
| Carbon credit market price | ~$4 per unit currently; management expects $5-$6 in coming months |
| CAPEX for 5,00,000 cbm plant (Chinese machinery) | ₹60-70 cr |
| Payment cycle from large builders | 70 to 75 days on average |
| Fly ash as raw material | 65% of raw material consumption |
| Ahmedabad unit sand-based block production | 20%-25% of capacity |