Key Takeaways
- Pricing, not volume, drove the quarter: Almost the entire sales increase came from higher ex-factory selling prices (INR149.97 vs INR104.54 YoY), while volume gains were a modest ~6%.
- German subsidiary resolved via insolvency: Geosphere filed for insolvency after a bank demanded repayment of a EUR 4.81 million capital subsidy; both entities are deconsolidated and management sees no likely positive recovery.
- Capacity expansion pulled forward to Dec '26: Both new furnaces are being built side-by-side, with the first fire expected by December 2026, ahead of the original March '27 target, though the monsoon may cause delays.
- India-EU trade deal opens a large, open-ended export path: Europe installed ~70 GW of modules in 2024; management sees a scenario where India supplies half that volume, calling the agreement "a big deal."
- What to watch next quarter: Whether the December '26 furnace timeline holds through the monsoon, any final findings from the CVD sunset review, and concrete progress on module sourcing under the new Indo-EU trade framework.
Pricing & Margin Dynamics
- Price-led revenue: Higher average ex-factory selling price, up ~43% YoY, accounted for almost the entire sales value increase for the quarter.
- Margins followed price up: The significant margin rise was driven directly by that higher selling price; the company is comfortable at current levels and sees prices as stable going forward.
- Import-parity pricing: Domestic industry prices are based on Chinese landed cost, with Malaysian and Vietnamese supply sitting 3-4% below that benchmark; the company positions as an import substitute at Chinese prices.
- Rupee depreciation offered only marginal help: Some advantage was gained from the weaker rupee, but management characterized the benefit as marginal, not significant.
- Input cost offsets in place: A few key inputs saw price increases, but plant operations offset the impact through efficiency improvements, batch mix changes, and other operational adjustments; natural gas costs have risen modestly on Henry Hub-linked contracts but the impact is not expected to be significant because of consumption savings.
Pradeep Kheruka: "We don't foresee a significant change going forward."
Capacity Expansion & Volume Growth
- Timeline accelerated: Both furnaces are being built side by side and are expected to complete within a couple of weeks of each other; the first furnace fire is targeted for December 2026, ahead of the originally announced March 2027 date.
- Monsoon risk flagged: Management cautioned that the monsoon this year may cause delays to the December timeline.
- Stabilization budgeted at 3 months: A trial period of up to 3 months is planned after the first furnace fire to stabilize production, though it could take as little as 1 month depending on process adjustment and equipment synchronization.
- Revenue step-up in Q4 FY27: Revenue is expected to stay at similar levels until new furnace production begins in Q4 FY27, after which revenue will increase by ~60% as capacity rises by the same proportion.
- Existing capacity still has headroom: Operational volume gains of ~6% have been achieved year-to-date; management expects this to continue in the current quarter, with a further 2-3 percentage points of marginal improvement possible from existing capacity.
- Further expansion ready but on hold: All utilities, the batch house, and infrastructure are already in place at Bharuch for another furnace; the only constraint is management caution, driven by the challenge of poaching of expert personnel and the need to absorb the current 60% production increase first.
Pradeep Kheruka: "We are cautious. We don't want to move in a hurry and not be able to manage the situation."
Trade Policy & Import Substitution
- CVD extended, sunset review underway: The countervailing duty on imports from Malaysia was extended by 3 months to 8 June 2026 while DGTR considers the sunset review; final findings are expected in the next couple of months.
- Import mix shifting: Before the anti-dumping duty on China and Vietnam took effect in December 2024, Malaysian imports were almost nil; they now account for ~25% of total imports, with Vietnam at ~10% and China at 65%.
- Malaysian supply not a constraint: Malaysian domestic players have commissioned more capacity, and availability for export to India is not an issue.
- ALMM-II and ALMM-III locked in: The government introduced ALMM-II effective June 2026 mandating domestically produced solar cells, with ALMM-III to follow from June 2028 mandating locally produced ingots and wafers.
- Import substitution runway is large: Imports still occupy about 70% of domestic consumption, leaving substantial scope for capacity addition even as new domestic capacity, much of it for captive use, takes the total to ~51 GW by March 2027, still short of real demand.
- Government flexibility expected on cells: If domestic cell capacity cannot ramp up to meet module manufacturing and demand levels, management expects the government to offer deferments or leeways rather than forcing module production to stop.
Pradeep Kheruka: "I can add one thing about the government that I'm seeing a level of interaction with industry and with customers by the government, which I have not seen before. They are very frequent. They know exactly what they're doing."
Export Markets & the Indo-EU Trade Deal
- Export demand remains weak: Major markets including the EU, Turkey, and the USA continue to face challenges due to low demand.
- India-EU free trade agreement is now a reality: Management described the landmark agreement as a potential game-changer for the solar module manufacturing industry if handled correctly within the agreement terms.
- The math is open-ended: Europe installed about 70 GW of modules in 2024; if even half of that is sourced from India under the trade deal, that represents 35 GW of potential demand. Management emphasized that "everything is open-ended."
- Overseas subsidiaries turned positive: Overseas subsidiaries moved from a negative EBITDA of INR5.08 crores in the previous quarter to a positive EBITDA of INR1.9 crores in Q3 FY26.
Pradeep Kheruka: "Europe has installed about 70 gigawatts of modules in the year '24... So if they take, say, even half of that, there will be 35 gigawatts they can buy from India. So, I mean, everything is open-ended. This trade deal is a big deal in my opinion."
German Subsidiary: Insolvency & Deconsolidation
- Trigger was a subsidy clawback: German bank ILB demanded repayment of a EUR 4.81 million capital subsidy; Geosphere denied the obligation citing force majeure due to inaction by the EU and German government to support domestic solar glass manufacturing.
- Both entities deconsolidated: GMB, the operating step-down subsidiary, and Geosphere, its holding company, have both been deconsolidated from the balance sheet; assets and investments have been removed.
- Court and administrator now in control: The German subsidiary and its manufacturing company are under the control of a court and a court-appointed administrator, who will decide whether to sell the company, find a buyer, or sell the assets.
- No positive recovery expected: When asked about the possibility of a positive outcome such as selling the subsidiary to recover losses, management responded, "frankly, I think that is unlikely."
- Legal advice suggests finality: Management stated that, per legal advice, there is nothing more that can be stuck with from the German subsidiary, though this is a qualified rather than definitive answer.
Domestic Demand & Policy Tailwinds
- Demand steady but had temporary friction: Domestic demand remained steady, but anticipated GST changes and a prolonged monsoon challenged solar module manufacturers with postponed deliveries, causing cash flow blockages and a decline in module selling prices that affected margins; the delivery situation started improving toward mid-December and is now normalizing.
- Module manufacturing set to surge: India is expected to become an international manufacturing hub with 200 GW of module capacity by 2027, while solar cell capacity is expected to rise to 75 GW.
- Battery storage adoption rising: Management sees increasing adoption of battery energy storage systems driven by challenges in grid stability and power evacuation.
- GST reduction already helping: The recent reduction in GST from 18% to 5% on many items is making a big impact on sales; management suggested that increasing the limit on renewable energy projects beyond the current 100% of contract demand could "set the market on fire."
- No equity dilution planned: The company is fully funded for current expansions; any further expansion would be supported by cash accruals, with no plan to raise further equity.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capacity expansion completion | Both furnaces built side by side; first furnace fire | December 2026 (monsoon may cause delays) |
| New line stabilization | Trial period to stabilize production after furnace fire | Up to 3 months post-December 2026 fire |
| Revenue step-up from new capacity | Revenue to increase by ~60% as capacity rises 60% | Q4 FY27 onwards |
| Volume growth from existing capacity | At least 6% volume growth for full year vs last year; further 2-3 pp improvement possible | FY26 full year |
| CVD sunset review findings | DGTR to issue final findings | Next couple of months |
| ALMM-II enforcement | Mandatory use of domestically produced solar cells | June 2026 |
| ALMM-III enforcement | Mandatory locally produced ingot and wafer | June 2028 |
| Targeted ROCE post-expansion | ROCE upwards of 25% | After 4,600 TPD expansion completion |
| No further equity dilution | Fully funded; cash accruals to support any further expansion | Ongoing |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Standalone revenue | ₹386.5 cr, all-time high, +40% YoY and +2% QoQ |
| Standalone EBITDA | ₹129.04 cr (33.4% margin), +518% YoY from ₹20.89 cr (7.6% margin); flat QoQ vs ₹125.5 cr (33.2% margin) |
| Consolidated revenue | ₹390.46 cr, vs ₹378.88 cr in Q2 FY26 |
| Consolidated EBITDA | ₹130.94 cr, vs ₹120.42 cr in Q2 FY26 |
| Average ex-factory selling price | ₹149.97/mm, vs ₹104.54/mm YoY and ₹147.5/mm QoQ |
| Exports | ₹20.74 cr (5.4% of turnover), vs ₹16 cr (5.8% of turnover) YoY |
| 9M FY26 standalone revenue | ₹1,097 cr, +40% over 9M FY25 |
| 9M FY26 standalone EBITDA | ₹347 cr, +235% over 9M FY25 |
| Volume growth (9M FY26) | ~6% YoY, with 2–3 ppt further improvement expected from existing capacity |
| Solar glass capacity | 2,600 TPD (~18 GW); expansion to add 60% capacity, commissioning expected from Dec '26 |
| Domestic solar glass demand | ~55 GW (DC basis) for FY26 installations; imports hold ~70% share |
| Domestic module manufacturing capacity | 145 GW, expected to rise to 200 GW by 2027 |
| Solar installations (FY26E) | ~40 GW (30 GW in 9M, ~10 GW expected in Q4), vs 24 GW in FY25 |
| Malaysian import share | ~25% of total imports, vs near nil before ADD on China/Vietnam started Dec '24; Vietnam ~10%, China ~65% |
| CVD on Malaysian imports | Extended by 3 months to 8 June 2026; sunset review underway |
| Power and fuel cost | ~32% of cost of production; renewable energy deployment to save ~₹1.25 cr/month |
| Targeted ROCE post-expansion | >25% (per management) |