Key Takeaways
- H1 EBITDA grew 56% YoY on strong asset performance and fast commissioning, with PAT up ~6x from a low base; the quarter absorbed a ~5% EBITDA hit from Bikaner grid curtailment that is now easing.
- FY27 and FY28 guidance reaffirmed: minimum 1,500 MW new capacity this fiscal and at least ₹3,000 crores EBITDA next fiscal, backed by a trailing 12-month addition of ~1,400 MW.
- Hyperscaler demand is the defining growth narrative: all CTU-connected capacity through September 2028 is already sold out, the company holds a 35% market share of contracted hyperscaler energy deals in India, and management sees a structural shift of AI data center build-out toward India.
- Balance sheet quality improved materially: a CRISIL upgrade to AA stable, a maiden ₹2,500 crores green bond at ~8.6%, and a weighted average interest rate reduced to 8.2% position the company for a rising-rate environment.
- What to watch next quarter: Kopal phase 1 commissioning (expected December), the pace of new CTU connectivity applications converting to contracted capacity, and whether Bikaner curtailment stays at the improved ~26% level seen in October.
Hyperscaler & AI Data Center Demand
- Structural tailwind articulated: Management believes compute factories and AI data centers will increasingly move to India because building in the US (tougher after midterm elections), Europe, and the Middle East is difficult, and China is geopolitically off-limits; India's current 2.3% share of the AI data center market is expected to rise, driving contracted energy capacity.
- CTU capacity fully allocated: All CTU-connected capacity till September 2028 is already sold out, and the company has applied for an additional 2 GW of CTU connectivity, specifically to replenish stock for hyperscaler clients.
- Market position quantified: CleanMax holds approximately 35% market share of hyperscaler energy volumes contracted in India so far, with multiple deals over multiple years with each hyperscaler.
- Demand-supply imbalance: Aggregate hyperscaler requirement is a lot more than available open-access CTU capacity, meaning all suppliers, CleanMax and competitors alike, will do well given the imbalance.
- Location preference shifting: Hyperscalers are beginning to prefer CTU-connected wind-solar hybrids in South India, both to address curtailment risk in Kutch/Rajasthan and because many are setting up data centers in South India.
- Winning solution: Wind plus solar plus storage is the combination management believes is the winning combo and clients express a strong preference for, to deliver the least cost of power; storage-integrated projects with STU-connected customers have already begun, though scale is not yet large enough for a separate line item.
- Contracting flexibility: Hyperscalers seek the option to use power directly into a data center or for green attributes; CleanMax is indifferent because tariffs are identical under both models and locked in for 20 to 25 years.
- Deal cadence: Hyperscaler deals are typically big and bulky, with not more than one announcement in a year; management declined to give a precise date or MW estimate for the next one.
Kuldeep Jain: "I do see from our vantage point a lot of the compute factories or AI data centers needing to move to India because it's becoming tough to build in other parts of the world."
Curtailment & Grid Connectivity
- Bikaner curtailment trajectory: Curtailment fell from ~70% in Q1 to 26% in October because the grid worked hard on upgrading and commissioning new sections, reducing peak congestion; the ramp-up phase (30% in Q1, 50% in Q2, ~70% from October onward) is typical of major capex assets.
- EBITDA impact quantified: Bikaner curtailment cost approximately 5% of H1 EBITDA; without it, EBITDA growth would have been 61% instead of the reported 56%.
- Kopal connectivity on track: The grid is ready with no transmission bottlenecks; commissioning will start from December in phases, with bay 1 (~220 MW evacuating capacity) expected in the Oct-Dec quarter and bay 2 (300 MW) likely by January, definitely within this fiscal.
- Bikaner 2 / Beacon A2 uncertainty: No update on when the grid will finish the relevant substation; management stated it is completely outside the company's control, with delayed lines going into UP causing the holdup, making a timeline tough to forecast.
- Reported PLF methodology: Reported PLF is after taking the hit of curtailment.
Kuldeep Jain: "If our EBITDA in H1 of this year grew at 56%, without this curtailment, instead of 56%, it could have grown at 61%. Right, but it's not a very big number, and the issue is getting more in control."
Financial Performance & Capital Management
- Revenue and segment performance: H1 FY27 revenue from operations grew ~67% YoY; RE power sales revenue roughly doubled; RE power sales EBITDA rose from ₹620 crores to ~₹986 crores, while RE services EBITDA rose 20% from ₹52 crores to ~₹60 crores.
- Operating leverage visible: RE power sales segment EBITDA margin improved to 84% (from 83.5% in March 2026) with constant gross margin, driven by lower SG&A as a percentage of segment revenue; management expects operating leverage to continue as the company expands.
- Interest cost management: Weighted average interest rate reduced to 8.2% at project level and 8.3% at corporate level in H1; fixed-rate share increased to 53.7% via the ₹2,500 crores green bond at ~8.6%, helping navigate expected rate hardening.
- Rate rise resilience modeled: Even if rates rise 50 bps in the next six months, the weighted average rate would hopefully not cross where it started the year due to H1 initiatives; planning assumption factors in at least a 100 bps increase in RBI repo rate, which with 50% fixed-rate borrowings translates to a 50 bps impact, moving project finance from 8.2% to 8.7%, still within the 8.75% always underwritten.
- Operating cash flow decline explained: Operating cash flow was down ~₹200 crore in H1 because a large vendor payment for wind turbine deliveries was made, drawing down a loan; this reduced payables and increased debt, with capital creditors reflected in operating cash flows.
- Payable days normalization: Payable days dropped from ~334 days in FY26 to 134 days because the prior year's elongated payable period was a one-off from better vendor terms; the current ~135 to 140 days is more reflective of normalized levels.
- Tax paid in H1 (~₹170 crores): Explained by the structure where assets sit at SPV level with tax depreciation in different legal entities, while the holding company bears the primary cash tax liability because it has investment income plus EPC and services income; this is underwritten as a potential outflow in project economics.
- Higher depreciation: A function of the fixed asset base at the start of the quarter; approximately 500 MW of assets commissioned since last quarter were added to the fixed asset base at the start of this quarter.
Nikunj Ghodawat: "Even if it goes up, let's say, by 50 bps in next six months, hopefully our weighted average rate would just not cross what at the point at which it started the year. Because of the various initiatives taken in the first half."
Order Book & Client Dynamics
- Repeat business strength: Repeat business share in new PPAs rose to 85% in H1 FY27 from ~75% in the prior two financial years, reflecting strong existing-client growth from a base of 600-plus corporate clients.
- Order book interpretation: STU contracts have solar delivery within 9 months and wind within 15 months; a 3 to 5 year backlog would indicate delivery issues, so the current ~21 months of order book at a 1,500 MW/year run rate is healthy; if the order book starts going up beyond current levels, it indicates ability to execute at a faster pace.
- Tariff premium: Capacity under execution carries a tariff of ~₹4 (50% solar, 50% wind, no or low storage), which is industry-leading versus ~₹3.1 for comparable utility/SECI contracts, due to premium C&I positioning.
- Weighted average tariff decline drivers: Two factors: change in the mix of solar and wind in the particular quarter on an aggregate basis, and currency movement impact on the ~20% of contracts that are dollar-denominated, affecting it by a few paisas every quarter.
- State-wise volume skew: Gujarat and Karnataka volumes exceed Maharashtra and Tamil Nadu purely because of maturity of presence, not regulatory differences; first plants were commissioned in Gujarat in 2021 and Karnataka in 2018, while Maharashtra's first open-access solar and wind plant was commissioned only in fiscal 2025-26 and is still ramping up.
- Growth engines diversified: New CTU evacuation capacity at very late stages of closures will translate into growth when contracted; the STU client base is diversified across 10-plus states, providing many growth engines.
Kuldeep Jain: "I always tell my business development team that you need to work harder on getting more new clients because you're just resting on your laurels if you are selling to the existing ones. But it's fantastic to have this kind of a strong 600 plus base of corporate clients which caters to our growth."
Project Execution & Cost Discipline
- Cost discipline maintained: H1 FY27 plants were commissioned at ~95% of budgeted cost despite rising commodity prices, material costs, diesel costs, and supply chain uncertainties from the war; the last three fiscals have been within 95% to 97% of budget.
- Plant operating performance: Trailing 12 months to H1 FY27 versus trailing 12 months to H1 FY26 showed wind, solar, and hybrid plant performance all slightly better.
- DCR/ALCM module orders: The company is holding off on placing final orders for 100 to 150 MW for Q1 next calendar year until all work is done, given the possibility of some extension; decisions are typically made at the very fag end, and management stated they had always factored in those kinds of prices for volumes from next calendar year onward with no impact on IRR requirements.
- Wind IRRs: Management stated wind IRRs are seen as equal or better than solar, with tariffs for wind quite higher than solar.
Regulatory Risk & Mitigation
- Maharashtra banking regulation: The regulation not allowing daytime solar power to be used at night was clarified as prospective only; most states have said any change in regulation is prospective and not retrospective.
- Maximum theoretical EBITDA risk: Even if retrospective application of such regulation occurred across all states, the risk to EBITDA is a theoretical maximum of 2% of entire fleet EBITDA till date; even that 2% can be addressed by selling the power to someone else.
- No hypothetical regulatory risk seen in Maharashtra and Tamil Nadu either; the number difference between states is purely maturity of presence, not regulation.
Kuldeep Jain: "The risk to EBITDA was only 2%, right, of our entire fleet EBITDA till date, you apply it retrospectively. And even that 2% can be addressed because what will you end up in such a situation is that you have power plants built and certain customers who cannot take all that power, and you just end up giving it to someone else."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capacity addition | Minimum 1,500 MW new capacity addition | FY27 |
| EBITDA | At least ₹3,000 crores minimum reported EBITDA | FY28 |
| Implied net debt | ₹15,000–₹16,000 crores net debt on a 5x net debt/EBITDA basis | FY28 |
| Kopal bay 1 commissioning | ~220 MW total capacity evacuating | Oct–Dec quarter FY27 |
| Kopal bay 2 commissioning | 300 MW connecting | By January, definitely within FY27 |
| Interest rate resilience | Weighted average rate not to cross starting point of year even if rates rise 50 bps | Next six months |
| Equity IRR resilience | Same equity IRR as always modeled even under a 100 bps RBI repo rate increase | Ongoing planning assumption |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue from operations growth | ~67% YoY in H1 FY27 |
| EBITDA | ₹553 cr, up from ₹386 cr in Q2 FY26 |
| EBITDA growth | 56% YoY in H1 FY27; would have been 61% without Bikaner curtailment |
| EBITDA margin (RE power sales segment) | 84%, up from 83.5% in March 2026 |
| Profit after tax | ~₹120 cr in H1 FY27, up ~6x from ₹19 cr in H1 FY26 |
| Weighted average cost of debt | 8.3% at corporate level, down from 8.8% at start of year; project level 8.2% |
| Fixed-rate share of outstanding debt | 53.7%; floating 46% |
| Net debt | ₹13,838 cr as of 30 Sep 2026 |
| Net debt to EBITDA (balance sheet level) | Less than 5x |
| Operational RE power sales capacity | 3.6 GW, up from 1,712 MW in March 2025 |
| Capacity commissioned in H1 FY27 | ~600 MW in RE power sales segment |
| Contracted and under execution capacity | 2.6 GW, representing ~21 months of growth at 1,500 MW/year run rate |
| Aggregate portfolio size | ~13,200 MW as of 30 Sep 2026, up from ~7.8 GW 18 months ago |
| Capacity addition guidance FY27 | Minimum 1,500 MW of new operational capacity, reiterated |
| EBITDA guidance FY28 | Minimum ₹3,000 cr reported EBITDA, reiterated |
| Bikaner grid curtailment | 26% in October, down from ~70% in Q1 FY27; cost ~5% of H1 EBITDA |
| Repeat business share in new PPAs | 85% in H1 FY27, up from ~75% in last two financial years |
| Data and AI share of overall volume | ~41–42% |
| Weighted average PPA tenure | 23 years |