Key Takeaways
- Volume up, price down: Volume grew 8.4% YoY but revenue fell 2% as cement prices declined sharply, particularly in South and Eastern markets.
- EBITDA compressed: EBITDA fell 27% YoY to INR434 crores (INR650/ton), driven by price declines and higher other expenses from plant shutdowns.
- Cost tailwinds building: Power and fuel costs fell 11.3% YoY, RE power share is rising toward 45%, and management expects INR50/ton savings this year from cost initiatives.
- Capacity expansion on track: The company is on track to reach 4.95 crore tons by FY25-end, with North East and Bihar grinding units commissioning in H2.
- What to watch next quarter: Whether H2 pricing improves as management expects, the pace of central market volume build without Jaypee tolling, and progress on the 7.5 crore ton FY28 capacity plan announcement.
Volume & Pricing Dynamics
- Volume growth despite headwinds: Volume grew 8.4% YoY even after discontinuing the Jaypee tolling arrangement, with Dalmia confident of 9% volume growth for FY25, growing at 1.5x the industry.
- Price decline concentrated: Q2 price decline of 5-5.5% QoQ was in line with the market, but South and Eastern markets showed much bigger declines, which translated into Dalmia's overall NSR decline.
- Trade mix shift: Non-trade mix increased 1% QoQ and 5% YoY, and since non-trade typically sells at a lower price than B2C, this shift impacted realizations.
- H2 pricing outlook: Prices could be marginally better in H2, depending on competitive intensity, though management cautioned that competitive intensity may not allow much gains.
- H2 demand drivers: Industry volume growth of 7-8% expected in H2, driven by pent-up housing demand, government infra spend momentum, real estate and private capex contribution.
Puneet Dalmia: "There will be times when industry prioritizes market share over margins. And there will be times when industry will prioritize margins over market share. This happens in every industry. Our industry is no exception."
Costs & Margin Levers
- Power and fuel tailwind: Power and fuel costs declined 11.3% YoY mainly due to a $26 decline in fuel consumption cost to about $101 YoY, with marginal reduction expected in coming quarters as spot levels are slightly down.
- Logistics cost pressure: Logistic costs rose 7.6% YoY because the company started servicing central markets from Eastern plants, and the quarter had only 1 month of busy season surcharge waiver versus 2 months in the same quarter last year.
- Other expenses elevated: Other expenses rose 15.7% YoY primarily due to a higher number of plant shutdowns and an increase in packing and material handling costs linked to higher sales volume; fixed expenses from shutdowns are expected to decline in Q3 and Q4.
- Cost savings roadmap: Management expects about INR50 per ton savings in the current year, another INR50 in FY26, and another INR100 or so in FY27 from cost initiatives.
- RE power build-out: Commissioned a 16 MW captive solar plant at Sattur, taking total RE capacity to 202 MW, and secured an additional 151 MW through group captive arrangements, bringing total signed RE capacity to 278 MW; expects to exit FY25 at about 45% RE share and reach 50% next year.
Capacity Expansion & Capex
- Near-term commissioning: The 0.24 crore ton North East grinding unit and 0.05 crore ton Bihar expansion should get commissioned in H2, with clinker in the North East expected around September of FY26.
- Debottlenecking: Debottlenecking projects of 0.09 crore ton on clinker are planned in H2.
- FY25 capex: Full year capex expected to be about INR3,000-3,300 crores, with maintenance capex running at INR250-300 crores per annum.
- FY26 capex: Expected to be about INR2,500 crores or so.
- Long-term capacity ambition: Building toward 10 crore tons by FY31, with a medium-term plan to build 7.5 crore tons by FY28; the plan for reaching 7.5 crore tons will be announced within the next 9 months.
- Central market strategy: The company will continue to serve the central market with the dealer network it has built, and in the medium term should have its own capacity even if Jaypee plants are not there; central region performance will gradually improve quarter-by-quarter, though limited by long distance from Eastern plants.
Puneet Dalmia: "I think at current prices, no investments can be justified. And whether you look at organic or inorganic growth, if you believe that the prices are going to remain at this level, we can't justify any investment."
Integration & Market Positioning
- Murli integration: The Murli plant has crossed the breakeven point and continues to improve its market positioning.
- Jaypee dealer retention: Most of the 1,000 Jaypee dealers who shifted to Dalmia are still continuing with operations through Eastern plants.
- Micro-market strategy: Management indicated that strategy will differ market by market, with a focus on gaining market share in markets where cost to serve is very low and market share is not very high.
- Long-term positioning: Management reiterated commitment to cost leadership, brand investment, distribution deepening, and service improvement, while noting that blended cements and increasing trade share remain long-term priorities.
Puneet Dalmia: "This business requires patience. This business requires not being disappointed when chips are down and not being too exuberant or arrogant when you are making too much money." [13-14]
Balance Sheet & Capital Allocation
- DBRL divestment complete: Received the final tranche of INR320 crores, along with interest, from the divestment of DBRL shares.
- Incentive receipt: Received an incentive of about INR46 crores in early October, with total incentive accruals and collections of INR300 crores expected for FY25.
- Interim dividend: The board declared an interim dividend of INR4 per share.
- Leverage guardrail: Net debt to EBITDA should not cross 2:1.
- Dividend policy: Capital allocation policy targets up to 10% of free cash flow distributed as dividends; the outlook has not diminished, so the trajectory remains unchanged.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capacity milestone | Reach 4.95 crore tons capacity | End of FY25 |
| Volume growth | 9% volume growth for FY25, growing at 1.5x industry | FY25 |
| EBITDA per ton | INR900-1,000/T blended, depending on demand and competitive intensity | FY25 |
| RE power share | Exit FY25 at about 45% RE share; reach about 50% | FY25 exit / next year-end |
| Incentive accruals | Total incentive accruals and collections of INR300 crores | FY25 |
| Depreciation | INR1,300-1,350 crores range | FY25 |
| Capex | About INR3,000-3,300 crores (FY25); about INR2,500 crores (FY26) | FY25 / FY26 |
| Cost savings | INR50/ton savings in current year, another INR50 in FY26, another INR100 in FY27 | FY25-FY27 |
| Capacity plan announcement | Announce plan for reaching 7.5 crore tons by FY28 | Within next 9 months |
| Long-term EBITDA per ton | INR1,100-1,200/T doable unless macro shocks or intense competition for market share | Long-term |
| Capacity expansion review | Will review 7.5 cr ton plan and pace only if massive macro shock | Conditional |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Revenue | ₹3,087 cr, -2% YoY |
| Volume | 0.67 crore tons, +8.4% YoY |
| EBITDA | ₹434 cr, -27% YoY |
| EBITDA per ton | ₹650, vs ₹782 in H1 FY25 and ₹900 in Q1 FY25 |
| Net debt to EBITDA | 0.25x |
| Trade mix | 63%, vs 64% in Q1 FY25 and 68% in Q2 FY24 |
| Blended cement share | 82.7% |
| Premium product share | 22.4% |
| Power and fuel cost per ton | ₹1,012, -11.3% YoY |
| Fuel consumption cost | $101 per ton, down $26 YoY and $5 QoQ |
| Blended fuel cost | ₹1.36 per kcal |
| Renewable energy share | 39%, up from 39% in Q1 FY25; target 45% by FY25 end |
| Logistics cost per ton | ₹1,102, +7.6% YoY |
| Lead distance | 280 km |
| Capacity utilization | 58% |
| Capex (H1 FY25) | ₹1,386 cr; full year guidance ₹3,000–₹3,300 cr |
| Incentive outstanding | ₹779 cr as of Sep 30; FY25 accruals and collections expected at ₹300 cr |
| Interim dividend | ₹4 per share |