Key Takeaways
- Order book nearly doubled QoQ: The order book jumped to ₹1,192.1 crore from ₹800.1 crore, driven by two large oil & gas wins worth ₹585 crore combined.
- Heavy fabrication turned the corner: Revenue surged 419.2% as the unit is now fully booked into H1 FY26, converting fixed costs into throughput after years of under-utilisation.
- Seamless pipe plant approved: A ₹90 crore, 7,000-ton plant targets 100% import substitution for thermal and subsea pipes, with a peak revenue ambition of ₹450 crore at 30–35% IRR.
- Margins got a forex tailwind: PAT margin expanded 891 bps QoQ to 10.6%, helped by a ~₹11 crore forex gain on the Thailand investment; operating EBITDA margin improved 196 bps QoQ on efficiency and logistics savings.
- What to watch next quarter: Commissioning of the Anjar Facility II in Q3, the first power sector RFQs in Q4, and the medium-term guidance management promised to deliver before the next call.
Order Book & Sector Pipeline
- Oil & gas dominated H1 ordering: Two large orders, ₹245 crore from Numaligarh Refinery (domestic) and ₹340 crore from Dow Chemicals (100% export), drove the sharp QoQ order book growth.
- Power sector orders are still in the engineering phase: 20 GW of thermal capacity has been ordered over two years, but piping inquiries lag because BHEL first places long-lead items and piping needs 6–9 months of engineering before the first RFQ. Major bidding is expected from Q4 FY25 or Q1 FY26.
- Power order sizing is material: Per 800 MW plant, the scope is ~1,000 MT at ₹500–₹700 per kg, implying an order value of ₹400–₹600 crore.
- Oil & gas pipeline remains deep: Management expects a large order book from oil & gas over the next 3–4 years, driven by domestic petrochemical plants, hydrogen-related technologies, and export traction on LNG contracts, supported by an MOU with Japan Gas Corporation.
- Execution cycle is 12–18 months: The average timeline for large orders means the current ₹1,192 crore book converts to revenue over that window, though customer schedules and material availability can cause initial delays.
Krishan Lalit Bansal: "I don't know what should I say on this particular case, because our competitors are either BHEL or L&T separately. And, you know, both of them are our customers also. So, ultimately, I will say that basically there is no competition."
Heavy Fabrication Turnaround
- Revenue exploded on full booking: The division grew 419.2% in Q2, with EBIT swinging to ~₹6 crore from ~₹1.8 crore, because the unit is now fully booked for the rest of FY25 and part of H1 FY26, and customer material availability finally allowed planned billing.
- Prior years were a fixed-cost drag: Management acknowledged the plant had never operated optimally or even at 50% capacity due to persistent constraints, so fixed costs were incurred without throughput.
- New customer line being added: The division is expanding its customer base beyond the current book, which de-risks the revenue concentration.
Krishan Lalit Bansal: "In earlier years, we have never been able to operate that plant optimally or even 50% capacity also because of some constraint or the other."
Capacity Expansion: Anjar & Seamless Pipe
- Anjar Facility II commissions in Q3 FY25: The new facility adds 9,000 MT, taking group capacity from 6,000 MT to 15,000 MT at Anjar and total group capacity to 1,12,500 MT. It will take 30–60 days post-commissioning to shift material from Palwal and ramp production.
- Dow order anchors the new facility: The ₹340 crore Dow Chemicals export order will be executed entirely from Anjar, providing a launch load for the expanded capacity.
- Seamless pipe plant targets import substitution: The board approved a ₹90 crore plant (₹22.5 crore from internal accruals) for fold seamless pipes up to 120 mm thickness in hydrolyzed steel and stainless steel grades, operational by Q4 FY26. No Indian manufacturer currently makes these pipes, which are used in >660 MW thermal plants and subsea projects.
- Revenue and return ambition: At peak utilisation, the plant is expected to generate ₹450 crore in annual revenue with a 30–35% IRR. Around 40–50% of output can be consumed captively; the rest will be sold to customers like BHEL and L&T, with a subsequent move into stainless steel pipes for the European subsea market.
- Demand visibility is long: 80 GW of thermal energy is on the cards, and subsea applications are increasing. The company's share of the total opportunity is very small, so management sees no diminishing factor for demand.
Krishan Lalit Bansal: "It's basically 100% import substitute only because at present nobody in India is manufacturing these pipes."
Margins & Cost Structure
- Gross margin is job-mix dependent: Gross margins range from 30% to 40%, sometimes exceeding 40%, and vary by the nature of jobs executed in a period. Management says a meaningful statement can only be made over 5–7 year averages, and the company bids on selective margins but outcomes can deviate.
- Steel price volatility is hedged: The company enters back-to-back contracts with vendors for raw material the moment orders are received, insulating margins across 4–5 cycles of steel price swings.
- Logistics savings are structural: The Gujarat facility's proximity to port is expected to add ~2% to margins from logistics alone.
- Capacity addition lowers fixed cost per unit: The additional 9,000 MT at Anjar will improve EBITDA margins by spreading fixed costs over a larger base, though management did not quantify the benefit beyond logistics.
- Job work lifts gross margin slightly: When the ratio of job work is higher relative to material-heavy jobs, gross margin increases, and this is the only change foreseen in the margin profile.
Sameer Agarwal: "I would always say that the gross margin range would be ranging from 30% to 40% and sometimes it is more than 40% and sometimes, many times it remains between 35% to 40%. So, it all depends upon the nature of jobs which you are executing in that particular period."
Working Capital & Execution
- Working capital is structurally high: Material must be procured immediately upon order receipt, tying up cash. Management expects a decent reduction in the cycle going forward, driven by a healthy order book, customer pressure to execute, and the new Anjar facility providing more capacity to process inventory faster.
- Execution is back-end loaded: The business is historically slowest in Q1, picks up in Q2 and Q3, and is most robust in Q4, driven by customer capex cycles where clients push everything to year-end.
- New orders face initial friction: Two large new orders are experiencing early execution challenges from customer timelines and material availability mismatches, but pace is expected to pick up once jobs start moving.
Competitive Position
- China is a pricing threat in fittings: Management acknowledged Chinese competitors are much more competitive in pipe fittings, partly because a lot of raw material itself comes from China, limiting DEE's ability to match on price.
- Power sector competitors are also customers: BHEL and L&T are both competitors and customers in the power piping space, creating a relationship dynamic management describes as effectively no competition.
- No entry into coating: The company has no plans to enter 3LP coating or glass flake coating, as it does not operate in cross-country pipelines.
Krishan Lalit Bansal: "Whenever they are in the product line, like the fittings which you are saying, they are definitely much more competitive. We cannot be that competitive because a lot of material comes from China itself."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Anjar Facility II commissioning | Additional 9,000 MT capacity operational | Q3 FY25 (December 2024) |
| Seamless pipe plant operational | 7,000-ton plant producing fold seamless pipes up to 120 mm thickness | Q4 FY26 |
| Seamless pipe plant peak revenue | ₹450 crore annual revenue at 30–35% IRR | At optimum utilisation (no date) |
| Medium-term guidance | Detailed medium-term guidance to be provided | On or before next earnings call |
| Revenue guidance | Company working on it; execution schedules from customers still being finalised | Possibly before next quarter |
| Power sector RFQs | Major bidding for power sector piping to begin | Q4 FY25 or Q1 FY26 |
| Target turnover | ₹1,500–₹1,700 crore with current asset base and expansion | In 2 years |
| Heavy fabrication booking | Fully booked | Remaining FY25 and part of H1 FY26 |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Operating income | ₹194 crore, +4.9% QoQ and +8.6% YoY |
| Operating income (H1 FY25) | ₹379 crore, +12.8% YoY |
| Operating EBITDA | ₹29.8 crore, +20.2% QoQ and +24.5% YoY |
| Operating EBITDA margin | 15.4%, +196 bps QoQ and +195 bps YoY |
| Operating EBITDA (H1 FY25) | ₹54.6 crore, +43.6% YoY; margin 14.4%, +309 bps YoY |
| PAT | ₹22.3 crore, +598.8% QoQ and +125.2% YoY |
| PAT margin | 10.6%, +891 bps QoQ and +529 bps YoY |
| PAT (H1 FY25) | ₹25.5 crore, +379.4% YoY |
| Revenue from heavy fabrication division | +419.2% YoY, sales contribution 6.9% of group |
| Other income | ₹16 crore, including ~₹11 crore forex gain on Thailand unit investment |
| Order book | ₹1,192.1 crore as of 30 Sep 2024, up from ₹800.1 crore as of 30 Jun 2024 |
| Order book, power sector | ₹180 crore |
| Order intake mix | More than 80% from oil and gas sector |
| Total group capacity | 1,12,500 metric tons after Anjar Facility II commissioning |
| Seamless pipe plant capacity | 7,000 tons annually, capital outlay ₹90 crore, peak revenue ₹450 crore, IRR 30–35% |