Key Takeaways
- Volume engine running at full throttle: Q3 DI pipe sales volume rose 18% YoY to 192,000 tonnes, with the company hitting 100% capacity utilization and recording its highest-ever quarterly production and sales.
- Margin squeeze from raw material lag: EBITDA fell 7% YoY to ₹184 crores because fixed-price contracts could not pass through higher coking coal costs, though sequential recovery from Q2’s ₹177 crores signals the trough is passing.
- The coal mine compensation wildcard: Management is “extremely hopeful” of receiving ₹1,500 crores from the auction of a previously held coking coal block, a sum that would transform the balance sheet by exceeding total long-term debt.
- ICD reversal addresses a governance overhang: Promoters have begun recalling inter-corporate deposits after shareholder feedback, with ~₹25 crores already received and the remaining ~₹200 crores expected in 1–2 months.
- What to watch next quarter: Whether the coal mine auction concludes and at what bid value, the pace of margin recovery as higher-cost inventory is consumed, and confirmation that the working capital cycle has indeed peaked.
Volume & Demand Environment
- Government schemes drive the order book: Jal Jeevan Mission and Amrut 2.0 continue to fuel DI pipe demand, with 9M revenue up 49% YoY to ₹5,227 crores and management seeing enough runway in the 42% of rural households still unconnected.
- Full-year volume on track: Q4 tonnage is expected in line with or better than Q3’s 192,000 tonnes, pushing full-year volume above 700,000 tonnes.
- New capacity entering a seller’s market: Management dismissed Welspun’s entry as a concern, arguing that robust demand leaves “enough on the table for every manufacturer” and that new supply is healthy for the industry.
Management: "Around 58% of the rural households have connectivity now and still 42% is yet to be connected. For everyone, for every manufacturer, there is enough on the table."
Margins & Raw Material Dynamics
- The coking coal lag: Raw-material-to-sales rose from ~49% in 9M last year to ~56% this year, driven by substantially higher coking coal costs versus the prior year, while fixed-price contracts prevented pass-through.
- Recovery mechanics: Management expects margins to improve as higher-cost RM inventory is consumed and current order intake reflects prevailing, lower RM prices. Iron ore prices have already cooled.
- EBITDA per tonne held steady: Despite the margin percentage decline, absolute EBITDA per tonne was maintained in 9M FY23 versus 9M FY22, and absolute EBITDA was also maintained.
- Sequential inflection: Q3 EBITDA of ₹184 crores improved from Q2’s ₹177 crores, suggesting the margin trough is behind the company.
Management: "Absolutely. We expect the same and the endeavor is to focus and get the margins trying for improvement in margins."
Balance Sheet & Working Capital
- Working capital peak called: The cycle has expanded due to capacity growth and price movements, with coking coal inventory built to ~5.5 months and iron ore to ~3–4 months. Management believes the peak is reached, assuming RM prices stay where they are, and debt should start declining.
- Debt at its zenith: Long-term debt is at peak levels; the ~₹400 crores of balance CAPEX next year will not cause a material increase because debt is already tied up. Scheduled repayments of ~₹350 crores in FY24 and ~₹250–260 crores in FY25 will gradually bring it down.
- ICD reversal underway: Following shareholder feedback, promoters have begun recalling inter-corporate deposits. ~₹25 crores has been received, the balance ~₹200 crores is expected in 1–2 months, after which the ICD balance will be zero.
V.M. Sridharan: "You can fairly assume that as of now the long-term debt is what the levels that we are at the moment is the peak level."
Coal Mine Compensation
- The ₹1,500 crore claim: A coking coal block de-allocated in 2015 has been put up for auction under the Coal Mines Act. The Delhi High Court ruled in the company’s favour on the compensation principle in 2017, and a valuer has been appointed to verify bills and vouchers related to the mine CAPEX.
- Bidders have emerged: JSW Steel and Vedanta submitted bids in January 2023. Management is not interested in bidding again and looks forward to compensation from the new allottee.
- Timeline is uncertain but process is moving: Management declined to give timelines but noted “a lot of positive movements are happening” and expects the takeover and payment to happen quickly once the tender concludes.
- Unanswered: the low-bid scenario: An analyst asked what the company would do if the auction bid came in far below the ₹1,500 crores claim (e.g., ₹500 crores). Management declined to comment, calling it hypothetical and asking the analyst to wait for clarity.
- Balance sheet transformation: If the full ₹1,500 crores is received, long-term debt of ~₹1,000 crores would be more than covered, leaving the company net cash.
V.M. Sridharan: "Once this Rs. 1,500 crores comes in, whenever it comes in, our long-term debt is only Rs. 1,000 crores. You can fairly assume where we will stand."
Capacity Expansion
- Phase 2 delayed by China supply chain: Srikalahasthi Phase 2 (additional 1.5 lakh tonnes) plus an eastern unit expansion (40,000 tonnes) are now expected to complete by end of FY24, with equipment imports from China slowed down.
- Path to 9 lakh tonnes: Total capacity will reach ~9 lakh tonnes once Phase 2 is complete, with ~₹400 crores of balance CAPEX to be spent next year.
- 0.1 crore tonnes within reach: Management confirmed it is possible to reach 0.1 crore tonnes within the existing capacity and land bank, with marginal scope for further debottlenecking in the southern unit. Larger expansions beyond that will require land and evaluation at the right time.
Subsidiaries & Other Assets
- Consolidated vs standalone gap is narrow: Consolidated EBITDA (₹593 crores) is only ~₹5–6 crores higher than standalone (₹586 crores), because subsidiaries are mainly export marketing arms with broadly similar profitability.
- Elavur plant is operational but small: The plant contributes ~₹8–10 crores in EBITDA, roughly 2–3% of turnover. A related land case is pending, and management is very confident the merits are in their favor.
- Dividend intent maintained: The company aims to maintain its dividend payout, subject to Board decision.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Full-year DI pipe volume | Close higher than 700,000 tonnes | FY23 (Q4 tonnage in line with or better than Q3’s 192,000 tonnes) |
| Capacity expansion completion | Srikalahasthi Phase 2 (1.5 lakh tonnes) + eastern unit (40,000 tonnes) online, taking total to ~9 lakh tonnes | End of FY24 |
| Balance CAPEX spend | ~₹400 crores | FY24 |
| Long-term debt repayment | ~₹350 crores scheduled | FY24 |
| Long-term debt repayment | ~₹250–260 crores scheduled | FY25 |
| ICD reversal | Full ~₹200 crores balance recalled, ICD becomes zero | 1–2 months |
| Coal mine compensation | ₹1,500 crores claim receivable from new allottee | No timeline given; process expected to move quickly once tender concludes |
Key Metrics
| Metric | Q3 FY23 |
|---|---|
| Total income | ₹1,751 cr, +24.5% YoY |
| EBITDA | ₹184 cr, -7% YoY; higher than ₹177 cr in Q2 FY23 |
| EBITDA margin | 10.50% |
| PAT | ₹65 cr, -31% YoY |
| PAT margin | 3.73% |
| 9M FY23 total income | ₹5,227 cr, +49% YoY |
| 9M FY23 EBITDA | ₹586 cr, +21% YoY |
| 9M FY23 EBITDA margin | 11.21% |
| 9M FY23 PAT | ₹234 cr, +15% YoY |
| 9M FY23 PAT margin | 4.47% |
| DI pipe sales volume | 792,000 tonnes (Q3), +18% YoY; highest production and sales in company history |
| 9M FY23 DI pipe sales volume | 517,000 tonnes, +24% YoY; full year expected to exceed 700,000 tonnes |
| Order book | ~7 months |
| Current DI pipe capacity | ~7 lakh tonnes; expansion to ~9 lakh tonnes expected by end of FY24 |
| Net debt | ~₹2,650 cr as of 31 Dec 2022; long-term debt ~₹1,050 cr, short-term debt ~₹1,600 cr |
| Cost of funds | Close to 10% |
| Coking coal inventory | ~5.5 months; iron ore inventory ~3–4 months |
| Coking coal price | ~$385/tonne (prevailing as of call date) |
| Long-term loan repayments due by FY24 | ~₹350 cr; FY25 repayments ~₹250–260 cr |
| CAPEX spent so far | ~₹150 cr; balance CAPEX ~₹400 cr to be completed next year |
| Coal mine compensation claim | ₹1,500 cr; JSW Steel and Vedanta bid for the mine in Jan 2023 under 16th tranche auction |
| ICD balance | ~₹200 cr as of 31 Dec 2022; ~₹25 cr already received, full reversal expected in 1–2 months |
| Elavur land value | ~₹300 cr; contributes ~2–3% of turnover and ~₹8–10 cr of EBITDA; plant operational |
| 9M FY23 consolidated EBITDA | ₹593 cr; standalone EBITDA ₹586 cr |
| Domestic payment cycle | ~60–90 days; exports slightly longer |