Engineers India Ltd Q1 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/jf5baraeljxq30llabg3vpse.pdf

Key Takeaways


Revenue: The Turnkey Timing Gap

Sanjay Jindal: "A decline in turnover is due to Turnkey segment, whose major ongoing contracts are on the verge of progress. However, in the current financial year or late in the preceding financial year, we have received a number of Turnkey jobs, whose turnover will be reflected in the coming quarters."

Order Book & Pipeline


Margins: Cyclical Pressure, Structural Confidence

Vivek Midha: "As you know, in this project kind of industry, margins are always cyclic in nature. And definitely, since we have a strong order book, and that order book will be reflected in turnover in the coming quarters. And we are sure that margin will -- all margins in the Consultancy segment will be intact."

Green & New Energy: Early Innings


International: The Long March to 50%

Vivek Midha: "The ultimate target is at least to bring it to the 50% of our revenue should come from the international, and that's a long-term target. Right now we are working, we are moving towards this around 20%, 30%, we should be able to get it."

Guidance & Commitments

CommitmentSpecificsTimeline
RevenueINR3,500 croresFY25
Net profitIntact on a yearly basisFY25
Order inflowAt least match last year's level (already at INR4,800 crores)FY25
Numaligarh Refinery commissioningClose to commissioningBy end of FY25
Revenue mixConsultancy 50–60%, Turnkey/LSTK 40–45%FY25
LSTK sustainable margin5% average, with quarterly upside from change ordersOngoing
International revenueMoving towards 20–30% shareMedium term
International revenueUltimate target of 50% shareLong term

Key Metrics

MetricQ1 FY25
Revenue₹611 cr, vs ₹808 cr in Q1 FY24
Consultancy & Engineering segment revenue₹347 cr
Turnkey segment revenue₹264 cr
Other income₹38 cr, vs ₹93 cr in Q1 FY24 (which included ₹56 cr interest from a client settlement)
PBT₹74 cr, vs ₹153 cr in Q1 FY24
PAT₹55 cr, vs ₹114 cr in Q1 FY24
Executed order book₹9,658 cr as on 30 Jun 2024; Consultancy ₹5,522 cr, LSTK ₹4,136 cr
Order book as on date~₹11,000 cr (as of mid-August 2024)
Order intake FY25 to date₹4,800 cr (as of 12 Aug 2024)
FY25 revenue guidance₹3,500 cr
Sustainable Consultancy segment margin~20%
Sustainable LSTK segment margin~5% (average); Q1 LSTK margin was almost 8% due to change orders
Green business contribution8% to 12% of order pipeline
Ramagundam plant capacity utilization90%; expected to reach 100% in the coming year
Ramagundam PAT share₹32 cr (EIL's 26% share of overall ~₹130 cr PAT)