Key Takeaways
- Turnkey drag, consultancy steady: Turnkey revenue fell ~19% as large LSTK/OBE jobs completed, while consultancy grew ~3% QoQ. Management expects the shortfall to be compensated by jobs in progress and new H1 wins.
- Order book building toward a step-up: H1 order inflow reached INR1,729 crores in October alone, and the full-year target is INR8,000-8,500 crores, supporting a corporate ambition of INR5,000 crores annual turnover within 2-3 years.
- Margins under quarterly pressure but full-year steady: Consultancy margins held at 20-25% and turnkey at ~5%; management expects full-year EBITDA margins in line with last year's 8.8%, with improvement from operational efficiency and new mega jobs.
- New energy pipeline is real but early: Green hydrogen, coal gasification, biofuels, nuclear and offshore wind are all in study, tender or readiness phases, with no major implementation yet materialized.
- What to watch next quarter: Whether the IOCL Paradip L1 position converts to a signed contract, the pace of Turnkey revenue recovery, and any concrete movement on the Guyana refinery and power projects.
Revenue & Segment Performance
- Turnkey segment: Revenue declined ~19% (37% in one reference) because major LSTK/OBE jobs were completed during Q1 and Q2. Management expects the shortfall to be compensated by existing jobs in progress and new orders received in H1.
- Consultancy segment: Revenue increased about 3% QoQ, with margins maintained at 20% to 25% on a regular basis.
- RFCL profit share: Q2 contribution was INR22 crores, with H1 total around INR54-55 crores; management expects to maintain over INR100 crores annually going forward.
- Revenue recognition cycle: For long-gestation contracts, revenue is not linear: only ~10% in the first 1.5 years, then 30-35% in years 2-3, with the balance in year 4. This creates inherent quarterly volatility.
- Numaligarh expansion: The expansion to 9 MMTPA is ongoing, but revenue will come only after completion; expenditures are currently being capitalized, and profitability will flow as dividends to EIL.
Management: "We are targeting around this figure."
Order Book & Project Pipeline
- October order inflow: INR1,729 crores, with most orders toward OBE and LSTK jobs and the rest consultancies.
- Full-year intake target: Management hopes to add another INR1,000-2,000 crores, reaching around INR8,000-8,500 crores total business intake for FY25.
- IOCL Paradip Petrochemical: Tender floated and opened; EIL bid and became eligible for both consultancy packages, is L1, and is likely to get the job shortly after client internal approvals.
- BPC refinery project: All consultancy packages have been awarded and work is already ongoing.
- Biofuel refinery: EIL quoted a project on OBE basis worth around INR300 crores.
- Panipat Expansion: Already being executed, with completion expected in the next 1.5 years or so; most packages already awarded and in construction phase.
- Confidential pipeline: Other projects in the OB segment are under negotiation, some in confidential one-to-one discussions; management declined to name specific projects.
Sanjay Jindal: "In the October month, quantum is INR1,729 crores and most of the orders are towards OBE, LSTK jobs and rest are the Consultancies."
Margins & Profitability
- Segment margin targets: Consultancy segment profit targeted at 20% to 25%, turnkey (Atlantica) business margin around 5%, with management aiming to maintain these in coming years.
- Full-year margin expectation: Management expects full-year EBITDA margins to be in the same line as last year (8.8%) over the course of the financial year.
- Margin improvement drivers: Improvement expected from operational efficiency and new mega jobs secured during the current financial year.
- Big vs small order dynamics: Big-ticket orders carry lower margins compared to small orders where there is intense competition.
- Quarterly volatility: Margins will be lower in quarters with higher expenses, but over 6 months or years management gets a better handle on margins.
- Nominated order profitability: Management declined to comment on cost percentage for nominated orders, citing competitive market conditions, but reiterated the 20-25% consultancy and 5-6% OBE profitability targets.
Sanjay Jindal: "The same profitability what we receive. There's nothing specific we can highlight on what the cost percentage is there. So it's a competitive market. So we'll not comment on that. But as we are maintaining the consistency profitability of 20% that would be the - 20% to 25%, that would be the target. And the OBE percentage, 5% to 6%, that would remain the target."
International & New Business Initiatives
- Guyana PMC award: EIL was awarded project management consultant services for a natural gas liquid project and a 400 MW power plant in Guyana, won under competition.
- Guyana future prospects: Guyana is anticipating an oil refinery and fertilizer project, but progress is delayed because the government is looking for investors rather than investing itself; expansion in the existing power facility is also anticipated as Guyana intends to supply power to neighboring countries.
- Abu Dhabi office: Achieved its highest-ever order booking this year.
- New energy studies: Multiple studies and initial engineering assignments completed for green hydrogen, coal gasification and biofuels, but major implementation has not yet materialized; things are in pipeline and discussion.
- Nuclear sector: Discussions ongoing with NTPC and NPCIL at initial stages for nuclear power plant involvement; management anticipates similar balance of plant assignments in the future, but nothing concrete yet.
- Offshore wind readiness: EIL is developing skills and preparing teams for offshore wind opportunities, drawing on extensive offshore experience (248+ platforms), but has not yet won any offshore wind projects and will bid when jobs come to market.
- Major oil & gas projects (GAIL, BPCL, ONGC): All still in feasibility stage; work will start only after initial board approvals, with EIL involved in feasibility studies.
Sanjay Jindal: "But it's going to take some time. Because actually, what they want is they don't wish to invest. They are looking for the investor to invest that project. So that is the hitch right now because it's far delayed. If the government would have invested, it would have been faster."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue target FY25 | Around INR3,500 crores | FY25 |
| Order inflow target FY25 | Additional INR1,000-2,000 crores; total ~INR8,000-8,500 crores | FY25 |
| Annual turnover ambition | INR5,000 crores corporate target | Within next 2-3 years (~FY27) |
| Consultancy segment margin | Maintain at 20% to 25% | Ongoing / coming years |
| Turnkey (Atlantica) margin | Maintain at ~5% | Ongoing / coming years |
| RFCL profit share | More than INR100 crores annually | Going forward |
| Full-year EBITDA margin | In line with last year (8.8%) | FY25 |
| IOCL Paradip contract award | L1, likely to get job after client internal approvals | In short time |
| Panipat Expansion completion | Already being executed | Next 1.5 years or so |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Revenue | ₹676 cr, vs ₹611 cr in Q1 FY25 |
| Consultancy & Engineering revenue | ₹383 cr |
| Turnkey revenue | ₹293 cr |
| Other income | ₹53 cr, vs ₹38 cr in Q1 FY25 |
| Profit before tax growth | 36% increase vs Q1 FY25 |
| Profit after tax growth | 44% increase vs Q1 FY25 |
| EPS | ₹1.41 |
| Order inflow (H1 FY25) | ₹5,137 cr |
| Order inflow including October | ₹6,866 cr |
| Order book (30 Sep 2024) | ₹11,155 cr, Consultancy ₹6,496 cr, LSTK ₹4,650 cr |
| Order book including October | ~₹12,000 cr |
| Consultancy segment margin target | 20% to 25% |
| Turnkey (OBE) segment margin target | 5% to 6% |
| RFCL profit share (Q2 FY25) | ₹22 cr |
| RFCL profit share (H1 FY25) | ~₹54-55 cr, full-year expectation more than ₹100 cr |
| RFCL revenue (H1 FY25, EIL 46% share) | ₹729 cr |
| Abu Dhabi office order booking (FY25) | ₹160-180 cr, highest ever |
| Corporate turnover target | ₹5,000 cr annual, within next 2-3 years |