Order Book & Pipeline

Jindal: "West Coast Refinery, we do not know the future of it because we have been hearing like it's always published in the paper that may not come. They might decide to go for two refineries at two different locations. So, we don't see any future at this point of time for this refinery."

Margins & Segment Profitability

Jindal: "No, this quarter margin is from the routine business of EIL. As you know, EIL coming from the implementing of the project, which is cyclic in nature. This may be some more -- this may be more in this quarter and this may be less in next quarter because it is always cyclic in nature."

IOCL Paradip & Near-Term Awards

Jindal: "The PM package 1 on has been awarded to us recently, I think last week, it has been awarded to us. And package number two is expected to be awarded in next couple of weeks."

Diversification Beyond Hydrocarbons


International Business


Revenue & Turnover Guidance

Jindal: "At this moment, we are working with our clients for some change orders. And till the time change orders are finalized, we are expecting to remain same billing turnover of the last year, around INR3,200 crores, INR2,500 crores. And in case we are able to finalize our change order, then definitely, we are going to hit the figure of INR3,500 crores."

Guidance & Commitments

CommitmentSpecificsTimeline
IOCL Paradip PMC-2 awardPackage number two awarded to EILNext couple of weeks (by end of Q4 FY25)
FY25 turnover₹3,200 crores without change orders; ₹3,500 crores if change orders finalizedFY25 (conditional on client decisions)
Consultancy order intake run rateMaintain ₹4,000–5,000 croresFY26
Order book levelSustain and increase the ₹11,000 crore order bookOngoing
Bina and Kochi refinery expansionsExpansion projects expectedWithin 1 year
Andhra Pradesh refinery major tenderFormal tender floatNext financial year or toward end of this quarter
Oil-to-chemical feasibility decisionsDecisions from 3–4 studies (1 private, 2–3 government)Next couple of months
Nigeria Phase 2 implementationImplementation phase may beginBy end of this year

Key Metrics

MetricQ3 FY25
Turnover₹750 cr, +11% QoQ from ₹676 cr in Q2 FY25
Consultancy & Engineering turnover₹407 cr
Turnkey turnover₹343 cr
Other income₹37 cr, vs ₹53 cr in Q2 FY25
Profit before tax₹118 cr, +18% QoQ from ₹100 cr in Q2 FY25
Profit after tax₹88 cr, +11% QoQ from ₹79 cr in Q2 FY25
Profit from operations₹81 cr, +72% QoQ from ₹47 cr in Q2 FY25
Operating margin11%, up from 7% in Q2 FY25
EBITDA₹128 cr, +16% QoQ from ₹110 cr in Q2 FY25
EPS₹1.57, vs ₹1.41 in Q2 FY25
Consolidated PAT₹109 cr, +9% QoQ from ₹100 cr in Q2 FY25
Order book₹11,353 cr, all-time high: Consultancy ₹5,554 cr, LSTK ₹5,799 cr
9M FY25 order inflow~₹7,000 cr, ~130% growth YoY
Consultancy segment profit margin~20%
LSTK segment profit margin~5% to 6%
Cash on books~₹1,000 cr