Key Takeaways
- Profit doubled, margins held: PAT nearly doubled YoY on strong module execution and operating leverage, with PAT margin slightly up to 9.60% despite competitive EPC pricing.
- Capacity up, utilization the real story: Module manufacturing capacity expanded to 1.1 gigawatt, now running at full tilt from November, with a target to lift utilization from 69% to 85-90% this fiscal year.
- BESS entry is EPC-first, manufacturing-later: The company is bidding for BESS tenders worth ~INR1,000 crores but will only build local manufacturing if the government imposes import duties, mirroring the solar module playbook.
- Order book deliberately short: Management keeps only a 6-7 month order book to protect margins from volatile module prices, currency swings, and duty changes, a structural choice that limits forward visibility.
- What to watch next quarter: Whether the INR200-crore Bihar Jal Jeevan Mission tender finalizes, the pace of BESS EPC revenue conversion, and any clarity on the working capital needed to fund the doubling of turnover targeted for next year.
Performance & Profitability
- Revenue driver: Strong order execution in module supply, rising demand across solar EPC segments (pumps, rooftop, streetlights), and higher utilization at the 750-megawatt facility.
- EBITDA doubled on higher operating volume and improved cost efficiency, though margin slipped from 16.27% to 14.61% on competitive EPC pricing and temporary softness in module prices.
- PAT margin inched up from 9.38% to 9.60%, helped by better working capital distribution and a controlled cost structure.
- EPS nearly doubled, reflecting the sharp profit improvement and value creation for shareholders.
- Operating cash flow turned positive at INR25.89 crores, driven by tight receivable management and disciplined inventory levels.
- Half-on-half growth was sharp, reflecting improved demand, faster project execution, and higher manufacturing capacity utilization.
- Module margin guardrail: Management expects module margin to remain in the 9-11% band; adding BESS will lift margins slightly next year.
Patel: "I can say all the shareholders are our family member. We will try to fair with everyone and be transparent, we'll share all the good thing and bad thing."
Capacity & Utilization
- Installed capacity now stands at 1.1 gigawatt after a 350-megawatt addition; management notes the line can theoretically be called 2 or 2.2 gigawatt, but actual output depends entirely on utilization.
- Utilization reality: The industry operates far below nameplate capacity: ALM registers show 120 gigawatts but actual working capacity is 32-34 gigawatts. The company's own utilization is currently 69%, with a target of 85-90% within FY26.
- Strategy is maximize first, expand later: Management will improve utilization of existing lines before committing to further capacity expansion, targeting a 16-second line speed as the next operational milestone.
- EPC mix shift: The company aims to consume 50% of its own modules in EPC projects and sell 50% in the open market, using captive supply to ensure on-time project completion and capture better margins.
Patel: "Normally, what happens is, I will explain to you that the capacity. For maximum utilization, we can also say 2 gigawatt. Normally, our line has already become 2 gigawatt. It has become up to 2.2 gigawatt. Now, what happens is, if we can say 2.2 gigawatt, but in this, we make utilization the target."
Order Book & Bidding Strategy
- Deliberately short order book: Management keeps only 6-7 months of orders, a structural choice driven by three risks: government-imposed duties (30% on module sales) that change prices overnight, dollar rate volatility (86 to 88.5), and fluctuating Chinese container and transportation costs.
- The margin math behind it: Advance booking locks in a rate; if module prices rise later, the company cannot capture the upside, so it prefers to book closer to delivery.
- Current tender participation: The company has bid for tenders worth a minimum of INR1,500-2,000 crores, including NTPC's 250-megawatt tender and a Bihar Jal Jeevan Mission water supply tender worth INR200 crores.
- Water supply margins currently run at 12-15%, down from 16-17% in Bihar two years ago as rates have risen but competition has intensified.
- The Bihar tender is held up by elections and expected to finalize in 1-2 months.
Patel: "In the order book, we don't plan much in advance. Because the rate goes up and down at any time. So, there is an effect on the margin. So, normally, we keep an order book of 6, 7 months."
BESS & New Business Lines
- EPC-first entry: The company has started participating in BESS tenders worth around INR1,000 crores and will execute EPC work for a year before considering manufacturing.
- The duty trigger: Chinese BESS containers are currently cheaper than local manufacturing. Management will only invest in domestic BESS production if the government imposes an import duty, replicating the 44% duty that made local solar module manufacturing viable.
- Revenue target: BESS is expected to contribute INR500-600 crores in revenue next year. If the company secures 1 gigawatt of BESS work, it will start manufacturing at 1.5 gigawatt capacity, scaling step-by-step.
- Cell manufacturing is planned for H1 FY28 at 2 gigawatt capacity with 30-40% headroom, contingent on government promotion and support for local manufacturing; this will require significant working capital.
- Wafer manufacturing was mentioned as a future possibility with no timeline.
- Prior experience: The company manufactured lithium batteries and battery packs under the Saubhagya Yojana scheme and has developed its own Battery Management System, giving it relevant technical capability.
- New leadership: Mr. Kothari has been onboarded as head of EPC Project and BESS, with a dedicated EPC team now in place.
Patel: "If we do manufacturing here, it will be costly. So, we are going into EPC now. We will go into EPC. Government will put duty today or tomorrow. ... So, 44% duty on the module. So, at that time, government will start supporting local. Then we will bring it into manufacturing."
Working Capital & Financing
- Current position: Operating cash flow turned positive at INR25.89 crores, with working capital improved through tight receivable management and inventory control.
- Growth will stretch the balance sheet: The target to double turnover next year (80-100% growth) will require more working capital, though management was contradictory on the quantum, first saying there would be a requirement and then saying there would be none.
- Cell manufacturing is the real call on capital: A 2-gigawatt cell manufacturing plant planned for H1 FY28 will need substantial working capital. For BESS alone, management estimated a working capital need of INR100 crores.
- Unanswered question: An analyst asked about receivables issues in the water supply business but was cut off due to a poor connection and the question was never answered.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Utilization improvement | Raise from 69% to 85-90% | Within FY26 |
| Revenue growth | Double turnover (80-100% growth) | Next year (FY27) |
| Module margin band | Maintain 9% to 11% | Ongoing |
| BESS/assembly EBITDA margin | 12% to 15% | When operational |
| BESS revenue contribution | INR500-600 crores | Next year (FY27) |
| EPC own-module consumption | 50% captive, 50% market sale | Target, no date |
| Cell manufacturing | 2 GW capacity, H1 FY28 start | Contingent on government support |
| Bihar Jal Jeevan Mission tender | INR200 crores, awaiting election outcome | Expected to finalize in 1-2 months |
Key Metrics
| Metric | H1 FY26 |
|---|---|
| Revenue | ₹342 cr, +145% YoY and +87.62% HoH |
| EBITDA | ₹50.02 cr, +120% YoY and +75.48% HoH |
| EBITDA margin | 14.61%, vs 16.27% in H1 FY25; competitive EPC pricing and soft module prices |
| PAT | ₹32.88 cr, +151.62% YoY and +91.70% HoH |
| PAT margin | 9.60%, vs 9.38% in H1 FY25 |
| EPS | ₹13.26, +92.75% YoY |
| Operating cash flow | ₹25.89 cr positive |
| Order book | ₹976 cr, providing visibility for next two quarters; 60–65% to be executed in H2 |
| Revenue mix – Solar PV module | ~65% of revenue |
| Revenue mix – EPC solar allied services | ~33% of revenue |
| Module manufacturing capacity | 1.1 GW (increased from 750 MW); installed capacity up to 2.2 GW |
| Capacity utilization | 69%, targeting 85–90% within FY26 |
| H1 revenue contribution | ~35% of annual revenue; H2 historically 1.5x–2x H1 |
| BESS revenue target (next year) | ₹500–600 cr |
| Water supply project margin | 12–15% |