Key Takeaways
- Solar scale-up drives the story: The 600 MW Khavda solar plant delivered a 33% CUF in its first full quarter, putting solar EBITDA on track to nearly double to ~₹600 crores this year.
- The next leg is already loading: 500 MW of additional Khavda solar is in advanced commissioning, waiting only on post-monsoon evacuation readiness; a further 200 MW is being planned from optimized land.
- Thermal stays solid, gas stays dead: Lignite stations ran at high PLFs with no grid congestion, while the idle gas plant is being repurposed for BESS and management is considering a hive-off.
- Profitability is back-end loaded: PBT this year may be ~₹220 crores as interest and depreciation jump; the ₹950–₹1,000 crore EBITDA run-rate only materializes once the 500 MW plant runs for a full year.
- What to watch next quarter: The pace of 500 MW commissioning post-monsoon, the start of principal repayments on Khavda debt, and any firm order on the 750 MW lignite thermal expansion.
The Khavda Solar Ramp
The 600 MW Khavda solar plant, commissioned in December 2025, achieved a 33.24% CUF in Q1 after resolving teething issues that had capped it at 23% in the March quarter. Full evacuation allocation received in November 2025 means the plant faces no curtailment, unlike other developers in the Khavda region who are waiting on KPS 2 readiness.
- Revenue contribution: ~₹420 crores expected from the 600 MW plant for FY26-27, with a 5–10% variance band.
- EBITDA contribution: ₹350–₹360 crores, driving the solar division's total EBITDA from ₹332 crores last year to ~₹600 crores.
- CUF seasonality: CUF will dip in Q2 during the monsoon, then recover in Q3; management expects a full-year CUF of 29–30%.
- PPA structure: A 25-year PPA with GUVNL is already in place; there is a benchmark CUF below which penalties apply, but no upper limit on generation, so all power pushed earns the tariff.
The 500 MW expansion is at an advanced commissioning stage, with capacity being added in phases. The first 200 MW is expected post-monsoon, followed by another 200 MW and 100 MW in subsequent months, contingent on CTUIL evacuation facility readiness. Full commissioning is targeted by end of calendar 2026.
- Land optimization: From the 4,750 hectares allocated for 2,375 MW, an additional pocket of land has been freed up to accommodate another 200 MW, with a firm plan to add it in the "next couple of months."
- Park O&M income: GIPCL will earn ₹20–₹25 crores annually for 25 years from O&M services to third-party developers (Coal India, SJVN, SAEL) in the Khavda park, starting this financial year.
Bhatt: "We have been given the full allocation in November 2025 and we are evacuating the full load from the 600 MW Khavda. That is why our CUF is 33%."
Profitability Bridge: Why EBITDA Growth Is Deferred
The 600 MW plant's full-year contribution will nearly double solar EBITDA, but consolidated profitability faces a heavy drag from financing costs that are only now hitting the P&L. The one-year moratorium on Khavda debt ended in June 2026, so principal repayment and full interest charges begin next quarter.
- Interest: Expected to double to ₹225–₹250 crores, because only one quarter of interest was booked last year post-commissioning, and the 500 MW debt will also begin accruing.
- Depreciation: Rising from ₹187 crores to ₹345–₹350 crores.
- PBT outcome: Management indicated PBT for FY26-27 may be around ₹220 crores, with initial teething losses on the 500 MW plant similar to what the 600 MW experienced.
- The ₹950–₹1,000 crore EBITDA run-rate will not appear this year; it requires the 500 MW plant to operate for a full year, which points to FY27-28.
The debt repayment schedule is structured as a step-up: lower in the first five years, then topping up in subsequent five-year blocks. Management declined to share specific repayment percentages. Peak debt across all projects is expected to reach ₹6,000–₹6,500 crores at one point.
Bhatt: "This year, you will not see the EBITDA of INR950 crores to INR1,000 crores. Once the 500 MW Khavda gets commissioned for the full operational year, hopefully, next year, you will see these figures on the paper."
Thermal & Gas: The Old Fleet
The two lignite-based thermal stations (SLPP 1 and SLPP 2) continue to perform reliably, crossing 75% and 80% PLF thresholds respectively. Both are debt-free and sit at the top of the merit order in South Gujarat, where industrial power demand remains heavy, insulating them from any curtailment risk even if a surplus were to emerge.
The 310 MW Baroda gas-based station remains idle, with a cost of production around ₹10/unit. All capex has already been recovered through PPA tariffs over the years. Management sees no revival given the current geopolitical situation and is instead repurposing the site.
- BESS conversion: GUVNL has approved a 20/120 MW BESS pilot at the gas station location; the tender is in place and the first phase will take approximately one year to become fully operational. A second phase of 30/160 MW is being planned for the coming year.
- Hive-off under consideration: Management is thinking to hive off the gas-based stations in the next couple of years since "nothing is going to happen on the gas front."
Bhatt: "See, the gas-based stations looking at the current geopolitical situation, I think it is not going to be revived now."
The Next Growth Legs: Thermal, Storage & Solar
750 MW lignite thermal expansion: GUVNL has given in-principle approval under a Section 62 cost-plus basis. The tender has been floated and is under observation by BHEL and other parties. The order is expected by the last quarter of this financial year, with three 250 MW units to be commissioned in 2031, 2032, and 2033. Capex will phase from 2027 through 2032–33.
- Fuel security: Available lignite in the region is sufficient to cater to the full 750 MW plus the existing 500 MW for the entire PPA life.
- Financing: Structured at 80:20 debt-to-equity (₹4,800 crores debt, ₹1,200 crores equity). Equity funding sources are undecided: options include internal accruals over five years, promoter infusion, equity dilution, or market raising.
- PPA: The entire capacity will be covered under a PPA with GUVNL.
Storage strategy: GIPCL's approach is reactive to GUVNL's requirements. If the off-taker requires storage for grid stability at existing renewable sites, GIPCL will implement it. Beyond the Baroda BESS, the company is also in the race to secure pump storage allocations from the Government of Gujarat and is identifying locations.
Incremental solar: Management is planning to add 200–300 MW of solar in the next couple of years, subject to land availability. When pressed on a medium-term vision for 500–1,000 MW annual additions, management pushed back, calling the gap between ambition and "actual reality" significant.
Bhatt: "That is one thing and actual reality is another thing. So we are thinking to add certain capacity of solar in the next couple of years around 200 to 300 megawatts."
Financial Position & Other Items
- Other income spike: Other income of ₹42 crores (vs ₹13 crores in the previous quarter) included ₹17 crores from an income tax refund, plus insurance claims, amortization of government grants, and liquidated damages from O&M contractors.
- Dividend commitment: Management affirmed its obligation to pay dividends to investors.
- ROE: Excluding the idle gas-based stations, ROE is more than 13–14%. When pressed on when consolidated ROE would cross 14%, management pointed to the hive-off plan rather than providing a timeline.
- Data disclosure: Management committed to holding quarterly conference calls going forward, providing a presentation with tabular figures, and looking into publishing PLF data on BSE/NSE sites from next quarter.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| 500 MW Khavda commissioning | First 200 MW post-monsoon, then 200 MW and 100 MW in subsequent months; full capacity by end of 2026 | Phased through Q3 FY27 |
| 600 MW Khavda revenue | ~₹420 crores (±5–10%) for FY26-27 | FY26-27 |
| 600 MW Khavda EBITDA | ₹350–₹360 crores | FY26-27 |
| Consolidated EBITDA run-rate | ₹950–₹1,000 crores | FY27-28 (full year of 500 MW operations) |
| 750 MW lignite thermal order | Order expected from GUVNL | By last quarter of FY27 |
| 750 MW lignite commissioning | 3 × 250 MW units | 2031, 2032, 2033 |
| Baroda BESS first phase (20/120 MW) | Fully operational | ~1 year |
| Additional Khavda solar (200 MW) | From optimized land | "Next couple of months" |
| Incremental solar capacity | 200–300 MW | "Next couple of years" |
| Gas plant hive-off decision | Decision on hiving off gas-based stations | "Next couple of years" |
| Peak consolidated debt | ₹6,000–₹6,500 crores | At one point during capex cycle |
| Quarterly disclosures | Conference calls, presentation, PLF data on exchanges | Starting next quarter |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Revenue from 600 MW Khavda solar | ₹420 crores expected for FY26-27 |
| Revenue from RE Park (O&M) | ₹55–₹60 crores at peak |
| Revenue from RE Park net of expenditure | ₹20–₹25 crores expected |
| Solar division EBITDA (FY25-26) | ₹332 crores |
| Solar division EBITDA (FY26-27 expected) | ₹600 crores |
| Solar division PBT (FY25-26) | ₹62 crores |
| Consolidated EBITDA (FY26-27 expected) | ₹950–₹1,000 crores once 500 MW fully operational |
| PBT (FY26-27 expected) | ₹220 crores |
| 600 MW Khavda CUF | 33.24% in Q1 FY27, up from 23% in Q4 FY26 |
| 600 MW Khavda expected annual CUF | 30%+ |
| SLPP 1 PLF | crossed 75% |
| SLPP 2 PLF | crossed 80% |
| Raghanesda solar CUF | 28–29% |
| Non-current borrowings (31 Mar 2026) | ₹3,250 crores |
| Projected total debt after 500 MW commissioning | ₹4,500 crores |
| Peak debt (including thermal expansion) | ₹6,000–₹6,500 crores at one point |
| Average borrowing cost | 7.8%, floating |
| Interest cost (FY26-27 expected) | ₹250–₹260 crores |
| Depreciation (FY26-27 expected) | ₹425–₹450 crores |
| Interest cost (FY27-28 expected, post 500 MW) | ₹400–₹450 crores |
| Depreciation (FY27-28 expected, post 500 MW) | ₹550–₹600 crores |
| 750 MW lignite thermal capex | ₹6,500–₹7,000 crores |
| 750 MW lignite commissioning timeline | 2031, 2032, 2033 |
| Baroda BESS capex | ₹250–₹300 crores |
| Baroda BESS revenue model | ~₹6 per unit |
| Khavda additional 200 MW project cost | ₹800–₹1,000 crores |
| Khavda additional 200 MW additional debt | ₹200–₹300 crores |
| Capital work in progress (31 Mar 2026) | ₹2,065 crores, entirely for 500 MW project |
| Revenue breakdown FY25-26: SLPP 1 & 2 | ₹1,103 crores |
| Revenue breakdown FY25-26: Solar (ex-Khavda) | ₹152 crores |
| Revenue breakdown FY25-26: Wind | ₹86 crores |
| Revenue breakdown FY25-26: 75 MW solar | ₹38 crores |
| Revenue breakdown FY25-26: Khavda | ₹111 crores |
| 75 MW group power plant revenue (9 months) | ₹38 crores |
| Khavda tariff | ₹2.73 per unit |
| PPA tenure for Khavda | 25 years |
| 145 MW gas plant original project cost | ~₹150 crores (1993) |
| 165 MW gas plant original project cost | ~₹250–₹300 crores |