Gujarat Industries Power Co Ltd Q4 FY2022 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/83lk14ztr2692wv1thec6dz2.pdf

Key Takeaways


Profitability Bridge: Why New Solar Has Not Lifted PBT

K. K. Bhatt: "In the phase manner since the last four to five years gas-based stations profitability is getting depleted year by year. Earlier it was contributing a lot into the profitability bottom line because the stations are totally debt free and depreciation free. It was adding to the bottom line very well, but with the reduction in availability of gas, the machines are not running at full capacity."

Khavda Solar Park: The Multi-Year Growth Engine

K. K. Bhatt: "We are targeting at least 1500 to 1800 capacity addition in the Khavda location by our own in the next five to seven years down the line."

Near-Term Capacity: 75 MW Solar Expansion

K. K. Bhatt: "That was the tender for GUVNL 500-MW bidding, that was won by the other bidders at a very low price, however, we do not want compromise with quality and profitability and to go below certain level..."

Thermal & Legacy Assets: Stability and Life Extension

K. K. Bhatt: "Your question is valid but it is all mechanical. We cannot predict. We are doing our best to maintain the availability of the station with annual overhauling and capital overhauling as may be required, but since the machines are old 20 years it may be possible to have technical issues and we are trying our best so that availability is not affected."

Unresolved Questions from the Call


Guidance & Commitments

CommitmentSpecificsTimeline
SLPP-I beam replacementEconomizer Beam replacement at Unit I to restore fixed cost recoveryJuly FY2022-23
75 MW solar expansion finalizationPSUs/promoters modality to be finalized"In a few weeks"
75 MW solar operationalProject to be operational"Down the line in 18 months"
Khavda solar park completion50% of project completeBy December 2024
Khavda own capacity addition1,500–1,800 MW of own capacityNext five to seven years
FY2023-24 PBT₹250–300 crores under normal scenario with current capacities (Station I not in operation)FY2023-24
Gas station restart possibilityPreservation mode; possible to run againOne to two years down the line
SLPP life extension10-year extension for SLPP-I; SLPP-II also being consideredNo date (under evaluation)

Key Metrics

MetricQ4 FY22
RevenueNot stated
EBITDANearly ₹400 cr for FY2022
EBITDA – thermal₹200–215 cr for FY2022
EBITDA – wind and solar₹200–220 cr for FY2022
PBT guidance (normal scenario, current capacities)₹250–300 cr for FY2023-24
Gas-based station PBT contributionZero for FY2022, down from ~₹23 cr in FY2020-21
Under-recovery of fixed cost at SLPP-I~₹23 cr for FY2022
Additional maintenance expenditure (overhauling)~₹10 cr for FY2022
Profitability washed away vs FY2019-20~₹65 cr combined impact from Station I shutdown and SLPP-I under-recovery
Dividend per share₹2.50, down from ₹2.90 previously
Lignite production29 lakh metric tonnes in FY2022
Lignite production requirement34 lakh metric tonnes targeted for FY2023
SLPP-I availability / PLF~65%, constrained by beam issue at Unit I
SLPP-II availability / PLFAbove 75%
Khavda solar park Phase-I capex~₹300 cr for FY2022-23
75 MW solar project capex₹400–450 cr
Khavda capacity addition target (GIPCL own)1,500–1,800 MW over next 5–7 years
75 MW solar project timeline18 months to operational
No capacity addition in FY2023-24Confirmed