Gujarat Industries Power Co Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/as-848088047003520398c01ef0.pdf

Key Takeaways


The Khavda Solar Ramp: From Teething to Full Load

Bhatt: "Last year, it was in the teething phase, and we have solved all the teething issues, and now we are on full swing."

FY27 Financial Bridge: Revenue Up, Costs Up More


The Gas-to-BESS Pivot and Idle Asset Resolution

Bhatt: "Basically, we are thinking to have a very -- in the next couple of months, a decision will be taken because nothing is going to happen on the gas front. So, there is no point in continuing with the gas-based station in the books."

The 750 MW Lignite Expansion: The Next Growth Leg


RE Park and Land Bank Optionality

Bhatt: "Vision is one thing and actual reality is another thing. So we are thinking to add certain capacity of solar in next couple of years, around 200 to 300 megawatts. We will see how we are going to get the land and where we are going to get the land."

Capital Structure and Shareholder Returns

Bhatt: "Dividend, we are committed. We will pay what we are paying because we have certain obligations to the investors also."

Guidance & Commitments

CommitmentSpecificsTimeline
500 MW Khavda commissioningFirst phase of 200 MW, then 200 MW and 100 MW in subsequent months; full operational CUF of ~33% only in FY28Post-monsoon FY27 start; phased through FY27
FY27 consolidated EBITDA~₹940–950 croresFY27
FY27 top line addition~₹450 crores (₹400–425 cr from 600 MW solar, ₹30–40 cr from RE park O&M)FY27
FY27 interest cost₹225–250 croresFY27
FY27 depreciation₹345–350 croresFY27
Consolidated EBITDA run-rate₹950–1,000 crores once 500 MW is fully operational for a full yearFY28
750 MW lignite expansion order placementOrder expected to be placed; three capacities commissioned by 2031, 2032, 2033Order by last quarter FY27; commissioning 2031–2033
120 MW BESS at gas plant siteCapex phase of ~1 year to become fully operationalFY28
Additional 200 MW solar at KhavdaFirm plan to develop on available land pockets"Next couple of months"
Gas-based station book-value decisionDecision to be taken"Next couple of months"
DividendMaintain at current levels through transitionOngoing
Quarterly earnings callsHold a call every three months when results are declaredOngoing from Q4 FY26
PLF data publicationLook into publishing on BSE-NSE sitesFrom next quarter onwards, if possible

Key Metrics

MetricQ4 FY26
Revenue₹1,103 cr from thermal (SLPP-1 & 2), ₹152 cr solar, ₹86 cr wind, ₹38 cr 75 MW solar, ₹111 cr other solar; total ~₹1,490 cr
EBITDA (FY26 full year, solar division)₹332 cr
PBT (FY26 full year)₹244 cr
PBT (FY26 full year, solar division)₹62 cr
Other income (Q4)₹42 cr, up from ₹13 cr QoQ; includes ₹17 cr income tax refund and insurance claims
Tax credit (FY26, transition to new regime)~₹260 cr
Initial loss on 600 MW Khavda solar (FY26)~₹220 cr
PLF, thermal stations SLPP-1 and SLPP-2SLPP-1 nearing 75%, SLPP-2 nearing 80%
PLF, 600 MW Khavda solar (current quarter)33.24%
PLF, 600 MW Khavda solar (Q4 FY26, March quarter)23%
Expected annual CUF, Khavda solar30% plus
Expected annual CUF, Raghanesda solar28–29%
Revenue per unit, Khavda solar₹2.73 per unit
Approximate annual revenue from 600 MW Khavda (FY27)~₹420 cr, may vary 5–10%
Approximate EBITDA from 600 MW Khavda (FY27)₹350–360 cr
FY27 EBITDA guidance (entire company)₹940–950 cr
FY27 revenue addition from 600 MW Khavda₹400–425 cr
FY27 revenue addition from RE park₹30–40 cr
FY27 total top-line addition~₹450 cr
FY27 interest cost estimate~₹250–260 cr
FY27 depreciation estimate~₹425–450 cr
FY28 interest cost estimate (post full 500 MW commissioning)₹400–450 cr
FY28 depreciation estimate (post full 500 MW commissioning)₹550–600 cr
Long-term borrowing (31 Mar 2026)₹3,250 cr (non-current liability)
Expected long-term debt after 500 MW commissioning~₹4,500 cr
Peak debt (including thermal expansion, at one point)~₹6,000–6,500 cr
Average coupon rate on borrowings7.8%, floating rate
Capital work in progress (31 Mar 2026)₹2,065 cr, entirely for 500 MW project
Moratorium on Khavda 600 MW debtUp to June 2026; repayment starts next quarter
500 MW Khavda solar commissioning timelinePhased commissioning post-monsoon, starting with 200 MW, then 200 MW, then 100 MW
750 MW lignite thermal expansion capex~₹6,000 cr (₹4,800 cr debt, ₹1,200 cr equity at 80:20)
750 MW lignite thermal expansion commissioning targetThree capacities by 2031, 2032, and 2033
BESS at Baroda gas station location120 MW approved by GUNL, tender in place; considering another 160 MW
BESS capex at Baroda gas station₹250–300 cr
BESS revenue model~₹6 per unit
Additional solar capacity at Khavda (land optimization)200 MW planned; estimated capex ₹800–1,000 cr
O&M revenue from Khavda park at peak₹55–60 cr gross, ₹20–25 cr net of expenditure, for 25 years
Revenue from 75 MW group power plant (9 months, FY26)₹38 cr
Gas-based stations (310 MW) statusIdle; all capex recovered historically; cost of production ~₹10/unit
Depreciation methodStraight line