Key Takeaways
- Solar scale-up is the story, but FY27 is a transition year: The 600 MW Khavda solar plant is now fully operational at a 33% CUF, and the 500 MW expansion is imminent, but FY27 EBITDA is guided to ~₹940–950 crores, not the full ₹1,000 crore run-rate, because of phased commissioning and initial teething losses.
- Balance sheet is entering a peak-debt phase: Total long-term debt is expected to reach ~₹4,500 crores after the 500 MW commissioning, with peak debt later hitting around ₹6,500–7,000 crores as the 750 MW lignite expansion begins.
- Idle gas assets are being repurposed, not revived: Management sees no revival for the 310 MW gas-based station and is converting the site into a BESS hub, with a decision on the gas plant's book value expected in the next couple of months.
- A 750 MW lignite expansion anchors the post-solar growth story: In-principle approval is secured for a ₹6,000–7,000 crore, 750 MW lignite-based plant under a cost-plus PTA with GUVNL, with commissioning phased through 2031–2033.
- What to watch next quarter: The pace of 500 MW solar block commissioning as PGCIL connectivity comes online, the actual FY27 finance cost and depreciation trajectory, and the decision on the gas plant's book value.
The Khavda Solar Ramp: From Teething to Full Load
- 600 MW now at full swing: The plant achieved a 33.24% CUF in Q4 after resolving initial teething issues that had capped CUF at 23% in the prior quarter. Full load evacuation began in November 2025 after receiving a pro-rata allocation from PGCIL.
- CUF seasonality is material: Management expects CUF to dip in Q2 due to the monsoon and rise again in Q3, so quarterly generation will not be linear.
- No curtailment risk: The plant has a firm PPA with GUNL for 25 years with no upper limit on generation, and GIPCL sits at the top of Gujarat's merit order, meaning any surplus-driven curtailment would hit costlier suppliers first.
- 500 MW commissioning is phased, not a single event: Capacity will be added in 50/100/200 MW blocks as evacuation capacity becomes ready, with the first phase of 200 MW expected post-monsoon once PGCIL connectivity is available.
- Initial loss on 500 MW is expected: Management flagged that the 600 MW project booked an initial loss of ~₹220 crores in FY26 due to teething problems, and a similar hit is anticipated when the 500 MW is commissioned.
- Full-year benefit only in FY28: Full operational CUF of ~33% for the 500 MW block is expected only in the next financial year after commissioning, so the ₹1,000 crore consolidated EBITDA target is a FY28 story.
Bhatt: "Last year, it was in the teething phase, and we have solved all the teething issues, and now we are on full swing."
FY27 Financial Bridge: Revenue Up, Costs Up More
- Top line addition of ~₹450 crores: This breaks down into ₹400–425 crores from the 600 MW Khavda plant's first full year and ₹30–40 crores from the RE park O&M revenue stream.
- Solar EBITDA nearly doubles: Solar division EBITDA is expected to rise from ₹332 crores in FY26 to ~₹600 crores in FY27, driven by the full-year contribution of the 600 MW plant.
- Interest cost to double: FY27 interest is guided to ₹225–250 crores, up from a lower base in FY26 when only one quarter of interest on the 600 MW was booked. The 500 MW addition will add further pro-rata interest.
- Depreciation to nearly double: Depreciation is expected to rise from ₹187 crores to ₹345–350 crores in FY27, reflecting the full-year impact of the 600 MW asset and the phased capitalisation of the 500 MW block.
- Combined cost relief if commissioning is mid-year: If the 500 MW is commissioned around mid-year, the combined interest-plus-depreciation hit would be ~₹200 crores lower than a full-year assumption, providing some PBT cushion.
- Consolidated EBITDA guided at ₹940–950 crores: This falls short of the ₹1,000 crore aspirational run-rate because the 500 MW will not contribute a full year of operational CUF.
The Gas-to-BESS Pivot and Idle Asset Resolution
- Gas-based station is structurally uncompetitive: The 310 MW plant has been largely idle for two years because its cost of production was around ₹10/unit, making it unviable in the merit order. All capex has already been fully recovered through historical PPA tariffs.
- Site is being repurposed for BESS: GUNL has approved a 120 MW BESS at the gas plant location, leveraging the existing switchyard and evacuation infrastructure. A further 160 MW BESS is under consideration for the coming year.
- BESS revenue model is fixed-return: GUNL will pay ~₹6 per unit for storage services, with power stored during off-peak hours and dispatched as required. The capex phase will take around one year to become fully operational.
- Gas plant book-value decision is imminent: Management stated that "nothing is going to happen on the gas front" and a decision on the plant's future in the books will be taken in the next couple of months, which could trigger a write-down.
- ROE is healthier ex-gas: Management indicated that excluding the gas-based station, ROE is more than 13% to 14%, framing the gas asset as the primary drag on return metrics.
Bhatt: "Basically, we are thinking to have a very -- in the next couple of months, a decision will be taken because nothing is going to happen on the gas front. So, there is no point in continuing with the gas-based station in the books."
The 750 MW Lignite Expansion: The Next Growth Leg
- In-principle approval secured: GUNL has approved a 750 MW lignite-based power station under a Section 62 cost-flow basis, with a PTA covering the entire capacity with offtaker GUVNL.
- Capex and timeline: Total capex is estimated at ₹6,000–7,000 crores, with a minimum four-year gestation period. The order is expected to be placed by the last quarter of the current financial year, with three capacities commissioned by 2031, 2032, and 2033.
- Fuel security is assured: Management confirmed that sufficient lignite is available in the region to cater to the total 750 MW plus the existing 500 MW for the entire PTA life period.
- Equity funding is flexible: The ~₹1,200 crore equity requirement will be funded through internal accruals over five years, with promoter infusion, equity dilution, or a market raise all on the table as options.
- Peak debt trajectory: Total debt is expected to peak at ₹6,000–6,500 crores at one point during the build-out, with ₹4,500 crores of new debt added in a phased manner and some repayment of existing debt occurring simultaneously.
RE Park and Land Bank Optionality
- 2,375 MW solar park is a multi-developer play: GIPCL is developing 1,100 MW on its own, while third-party developers (Coal India, SJVN, SAEL) will develop the rest under direct PPAs with GUNL. GIPCL provides park infrastructure and evacuation, which is already in place.
- O&M revenue stream starts in FY27: Once third-party developers commission their plants, GIPCL will earn O&M revenue as the park developer. Peak O&M revenue is expected at ₹55–60 crores, with net earnings of ₹20–25 crores annually for 25 years after expenses.
- Land optimisation unlocks 200 MW upside: Out of the 4,750 hectares allocated for 2,375 MW, land optimisation has freed up pockets that can accommodate an additional 200 MW beyond the remaining 75 MW MNRE allotment, with a firm plan to develop this in the next couple of months.
- Future solar pipeline is modest and land-gated: Management is thinking about adding 200–300 MW of solar in the next couple of years, subject to land acquisition and evacuation crystallisation, but declined to provide a longer-term quantified pipeline or annual run-rate target.
Bhatt: "Vision is one thing and actual reality is another thing. So we are thinking to add certain capacity of solar in next couple of years, around 200 to 300 megawatts. We will see how we are going to get the land and where we are going to get the land."
Capital Structure and Shareholder Returns
- Thermal and legacy renewables are nearly debt-free: All thermal stations are debt-free, and the existing 262 MW and 312 MW solar plus wind assets carry only very small residual debt. Only the Khavda 600 MW currently carries material debt.
- Debt is on a step-up repayment schedule: Repayments are lower in the first five years and then step up in subsequent five-year blocks, matching the ballooning structure. Cash surplus from the 600 MW is sufficient to service its debt.
- Dividend commitment is explicit: Management committed to maintaining dividend payments at current levels, citing obligations to investors, regardless of PBT fluctuations during the transition phase as new capacity is commissioned.
- Other income spike is non-recurring: Q4 other income rose to ₹42 crores from ₹13 crores QoQ, driven by crystallised insurance claims, a ₹17 crore income tax refund, and grant amortisation. This is not a run-rate.
Bhatt: "Dividend, we are committed. We will pay what we are paying because we have certain obligations to the investors also."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| 500 MW Khavda commissioning | First phase of 200 MW, then 200 MW and 100 MW in subsequent months; full operational CUF of ~33% only in FY28 | Post-monsoon FY27 start; phased through FY27 |
| FY27 consolidated EBITDA | ~₹940–950 crores | FY27 |
| FY27 top line addition | ~₹450 crores (₹400–425 cr from 600 MW solar, ₹30–40 cr from RE park O&M) | FY27 |
| FY27 interest cost | ₹225–250 crores | FY27 |
| FY27 depreciation | ₹345–350 crores | FY27 |
| Consolidated EBITDA run-rate | ₹950–1,000 crores once 500 MW is fully operational for a full year | FY28 |
| 750 MW lignite expansion order placement | Order expected to be placed; three capacities commissioned by 2031, 2032, 2033 | Order by last quarter FY27; commissioning 2031–2033 |
| 120 MW BESS at gas plant site | Capex phase of ~1 year to become fully operational | FY28 |
| Additional 200 MW solar at Khavda | Firm plan to develop on available land pockets | "Next couple of months" |
| Gas-based station book-value decision | Decision to be taken | "Next couple of months" |
| Dividend | Maintain at current levels through transition | Ongoing |
| Quarterly earnings calls | Hold a call every three months when results are declared | Ongoing from Q4 FY26 |
| PLF data publication | Look into publishing on BSE-NSE sites | From next quarter onwards, if possible |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue | ₹1,103 cr from thermal (SLPP-1 & 2), ₹152 cr solar, ₹86 cr wind, ₹38 cr 75 MW solar, ₹111 cr other solar; total ~₹1,490 cr |
| EBITDA (FY26 full year, solar division) | ₹332 cr |
| PBT (FY26 full year) | ₹244 cr |
| PBT (FY26 full year, solar division) | ₹62 cr |
| Other income (Q4) | ₹42 cr, up from ₹13 cr QoQ; includes ₹17 cr income tax refund and insurance claims |
| Tax credit (FY26, transition to new regime) | ~₹260 cr |
| Initial loss on 600 MW Khavda solar (FY26) | ~₹220 cr |
| PLF, thermal stations SLPP-1 and SLPP-2 | SLPP-1 nearing 75%, SLPP-2 nearing 80% |
| PLF, 600 MW Khavda solar (current quarter) | 33.24% |
| PLF, 600 MW Khavda solar (Q4 FY26, March quarter) | 23% |
| Expected annual CUF, Khavda solar | 30% plus |
| Expected annual CUF, Raghanesda solar | 28–29% |
| Revenue per unit, Khavda solar | ₹2.73 per unit |
| Approximate annual revenue from 600 MW Khavda (FY27) | ~₹420 cr, may vary 5–10% |
| Approximate EBITDA from 600 MW Khavda (FY27) | ₹350–360 cr |
| FY27 EBITDA guidance (entire company) | ₹940–950 cr |
| FY27 revenue addition from 600 MW Khavda | ₹400–425 cr |
| FY27 revenue addition from RE park | ₹30–40 cr |
| FY27 total top-line addition | ~₹450 cr |
| FY27 interest cost estimate | ~₹250–260 cr |
| FY27 depreciation estimate | ~₹425–450 cr |
| FY28 interest cost estimate (post full 500 MW commissioning) | ₹400–450 cr |
| FY28 depreciation estimate (post full 500 MW commissioning) | ₹550–600 cr |
| Long-term borrowing (31 Mar 2026) | ₹3,250 cr (non-current liability) |
| Expected long-term debt after 500 MW commissioning | ~₹4,500 cr |
| Peak debt (including thermal expansion, at one point) | ~₹6,000–6,500 cr |
| Average coupon rate on borrowings | 7.8%, floating rate |
| Capital work in progress (31 Mar 2026) | ₹2,065 cr, entirely for 500 MW project |
| Moratorium on Khavda 600 MW debt | Up to June 2026; repayment starts next quarter |
| 500 MW Khavda solar commissioning timeline | Phased commissioning post-monsoon, starting with 200 MW, then 200 MW, then 100 MW |
| 750 MW lignite thermal expansion capex | ~₹6,000 cr (₹4,800 cr debt, ₹1,200 cr equity at 80:20) |
| 750 MW lignite thermal expansion commissioning target | Three capacities by 2031, 2032, and 2033 |
| BESS at Baroda gas station location | 120 MW approved by GUNL, tender in place; considering another 160 MW |
| BESS capex at Baroda gas station | ₹250–300 cr |
| BESS revenue model | ~₹6 per unit |
| Additional solar capacity at Khavda (land optimization) | 200 MW planned; estimated capex ₹800–1,000 cr |
| O&M revenue from Khavda park at peak | ₹55–60 cr gross, ₹20–25 cr net of expenditure, for 25 years |
| Revenue from 75 MW group power plant (9 months, FY26) | ₹38 cr |
| Gas-based stations (310 MW) status | Idle; all capex recovered historically; cost of production ~₹10/unit |
| Depreciation method | Straight line |