Key Takeaways
- Growth guide cut on Delhi pollution: FY26 revenue growth revised to 15–20% from 20–25% because government-mandated construction bans under GRAP 3/4 stole 6–8 months from NCR project timelines.
- Order book is deeply concentrated: 70–90% of the order book sits in Delhi NCR this year, a deliberate choice for margin control that now concentrates the pollution risk as well.
- IPO unlocks larger projects: The fresh equity has lifted net worth enough to bid for ₹200–300 crore single projects, up from a joint-venture past, and the pipeline already holds ₹500 crore of bids awaiting opening.
- Margins held flat despite an idle start: EBITDA margin was stable at ~15.9% QoQ even though one project could not start, absorbing the overhead; machinery ownership is meant to add incremental margin going forward.
- What to watch next quarter: Whether the Haryana Cricket Association approval actually lands this month, how many of the ₹500 crore in bids convert, and whether FY27’s 20–25% growth target survives the first quarter of execution.
The Pollution Overhang
- GRAP is the binding constraint: Under GRAP 3 (AQI >300) construction stops by government order; under GRAP 4 it is banned entirely. An 18-month NCR project realistically takes 24–28 months, and the company builds that buffer into its planning and client timelines.
- No penalties, but time is lost: Management stated that no penalty has been levied on the company for delays on any project, attributing all timeline extensions to external factors (pollution, rainy season) and noting that escalation clauses cover overhead and cost.
- The concentration trade-off: Management prefers NCR for better control, cost control and profitability, and this year 70–90% of the order book sits there. Last year 50–70% was outside Delhi, so the exposure swing is material and self-reinforcing: the very region that delivers margin control also carries the pollution stop-work risk.
- Q4 is seasonally stronger: 9M standalone revenue grew only 5–10% YoY, but Q4 is always better in the industry, and the revised 15–20% full-year guide depends on that seasonal lift materialising without fresh GRAP interruptions.
Vipul Khurana: "No, project has been delayed, but again it's mostly part of the department that has been at fault and there's no project where the penalty has been levied on us because of our delay."
Order Book & Pipeline
- Current book-to-bill is ~2x: The execution team is fully utilised, with one project (IIT Delhi) finishing in 1–2 months and those people shifting to another site. Management wants to reach a book-to-bill of 3, which needs 3–4 more projects of ₹400–500 crore each.
- Near-term conversion opportunity: Four projects totalling ₹500 crore have been bid and are expected to open in one to two months; management hopes to win three of them. Another ₹500 crore is in the process of being bid over the next two months.
- Repeat customers dominate: All orders come from repeat government departments (NBCC, TCIL, CPWD). End clients such as IITs, IIMs and NITs change, but the executing departments are the same counterparties, which reduces counterparty discovery risk.
- Deposit-works model insulates funding: Projects are chosen where funds are already available, so fund availability is never an issue, though approvals can still cause start delays.
Sports Infrastructure: The New Niche
- A deliberate strategic bet: Sports infrastructure has grown meaningfully and is now a focus area. The company has already taken a ₹222 crore (plus GST) stadium project for a cricket association and expects at least 1–2 more sports projects this year.
- The macro thesis: Management sees a 5–7 year build cycle driven by the Commonwealth Games and a potential Olympics in India, and wants to carve out a niche in sports infrastructure while the pipeline is forming.
- Fixed-cost structure on the stadium job: The cricket association project is fixed-cost with steel supplied by the department, shifting material price risk to the client and leaving execution efficiency as the margin driver.
Vipul Khurana: "In next 5 to 7 years there's lot of sports infrastructure that's going to build across the country because of the Commonwealth and or maybe Olympics also comes to India. So again our focus is to have a niche area in sports infrastructure."
Margins & Capital Efficiency
- Margins held flat despite idle overhead: EBITDA margin was 15.89% in Q3 vs 15.92% in Q2. Some overhead costs were incurred because one project did not start as expected, but the impact was contained.
- Machinery ownership as margin lever: The planned ₹14.2 crore machinery investment is primarily for scaffolding and shuttering material previously rented. Buying instead of renting will add to the EBITDA bottom line, though management cannot quantify the exact contribution.
- Working capital cycle target: The company is targeting a reduction to 75–80 days as EPC projects complete and receivables come in at the handover stage. No new borrowings are planned except non-fund based limits for bank guarantees.
- Government vs private margins are similar: Management stated margins are comparable across client types because quoting discipline is the same, and the targeted mix is 70:30 government-to-private for the next 4–5 years.
IPO Proceeds & Balance Sheet
- Working capital object nearly fully deployed: Of the ₹75 crore working capital object, almost all is utilised. The ₹14 crore capex object still has ₹10–11 crore available, and the ₹3 crore general corporate purpose object is available until December 2025. No debt reduction was in the objects.
- Net worth unlocks bid eligibility: The IPO proceeds have increased net worth, making the company eligible for ₹200–300 crore single projects. Previously it had to operate through joint ventures to access work of that scale.
Raghav Aggarwal: "Earlier we were doing projects in joint ventures also. Now we have ample net worth. With the IPO proceeds our net worth has increased. We are now eligible for more bigger projects and to grow faster."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 revenue growth | 15–20% (revised from 20–25%) | FY26 full year |
| FY27 revenue growth | 20–25% | FY27 full year |
| Medium-term annual growth | ~20–25% every year in both revenue and profitability | Year-on-year, ongoing |
| Haryana Cricket Association start | All approvals expected | This month (Q4 FY26) |
| Near-term order conversion | ₹500 crore of bids expected to open; hoping for 3 wins | 1–2 months |
| Additional order inflow | ₹200–400 crore more projects this year (beyond ₹500 crore already received) | FY26 |
| Book-to-bill ratio | Target of 3 (currently ~2) | No date; needs 3–4 more large projects |
| Working capital cycle | Reduce to 75–80 days | As EPC projects complete and receivables arrive |
| Government-private mix | 70:30 | Next 4–5 years |
| Machinery investment | ₹14.2 crore in scaffolding and shuttering (buy vs rent) | Ongoing; ₹10–11 crore of IPO capex object still available |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Total income (standalone) | ₹93.76 cr |
| Total income (consolidated) | ₹102.09 cr |
| Profit before tax (standalone) | ₹8 cr |
| Net profit (standalone) | ₹6.53 cr |
| Net profit margin (standalone) | 6.96% |
| EPS (standalone) | ₹1.10 |
| EBITDA margin | 15.89%, compared to 15.92% in Q2 FY26 |
| Revenue growth (standalone, 9M FY26 vs 9M FY25) | 5% to 10% |
| FY26 revenue growth guidance | 15% to 20%, revised from 20% to 25% due to pollution-related delays in Delhi NCR |
| FY27 revenue growth guidance | 20% to 25% |
| Outstanding order book | ~₹850 cr as of 31 Jan 2026 |
| Book-to-bill ratio | ~2x, targeting 3x |
| Order inflow (FY26 to date) | ~₹500 cr |
| Bid pipeline under evaluation | ~₹500 cr (four projects) |
| Working capital cycle | ~100 days, targeting reduction to 75–80 days |
| Receivables from government clients | ~90% of total receivables |
| IPO proceeds utilized for working capital | ~₹75 cr of ₹119 cr, nearly fully utilized |
| IPO proceeds remaining for capex | ~₹10–11 cr of ₹14 cr allocated |