Key Takeaways
- Production hit, price held: Q3 lignite output fell 13% YoY after two land-sliding incidents at Tadkeshwar, but realization held steady at ~₹4,200/tonne and PBT year-to-date has already crossed the best-ever full-year figure in company history.
- CapEx budget jumps 4x: The board approved an ambitious ~₹2,500 crore capital budget for FY24, dominated by land acquisition at Tadkeshwar and Bhavnagar and a turnaround of the Akrimota power plant; management is asking investors for faith that this spend will take the company to "newer levels."
- A pipeline of new mines is forming: Lakhpat, Damlai, two South Gujarat projects and a coal-block auction bid are all in motion, with groundbreaking expected on 3–4 projects in the coming financial year and a medium-term lignite capacity target of 3–5 crore tonnes.
- Diversification is the stated ambition but remains early: Bauxite beneficiation and fluorspar plant refurbishment are underway, and management aspires to have half of revenues from beyond lignite in 2–3 years, though it calls opening non-lignite mines "even tougher."
- What to watch next quarter: Whether the coal-block auction bid succeeds, the pace of land-acquisition CapEx deployment, and any concrete timeline on the rare earth elements project that management repeatedly declined to discuss.
Production & Realization
- Tadkeshwar disruption: Two consecutive land-sliding incidents, one in December and one in the prior quarter, caused Tadkeshwar production to drop ~35%, pulling overall Q3 output down to 0.19 crore tonnes from 0.22 crore tonnes a year ago.
- Bhavnagar fast-tracked: The Tadkeshwar collapse forced Bhavnagar expansion to be accelerated; management now calls the ramp-up "very easy" and plans 0.33 crore tonnes from Bhavnagar alone, with the mining structure split across two contractors via two packages to improve output.
- Rajpardi winding down: The mine is "on its deathbed" and may close within a year; volumes are marginal at a few lakh tonnes, and the intention is to "squeeze the last drop of water out of the cloth."
- Price stability with a caveat: Realization has held at ~₹4,200/tonne since April, with only a very minor correction in the first fortnight of February; management says it will soften prices if imported coal prices soften but raised prices earlier to stop bleeding projects and curb black marketing.
- FY23 volume target: Management expects to match last year's production, above 0.8 crore tonnes, with full-year volume around 0.85 crore tonnes.
- Customer engagement improved: Booking amounts have picked up since January after a new customer-grading initiative launched on the website.
Roopwant Singh: "Rajpardi is the mine which is you can say it is on its deathbed you may see production for an year or we may see a closure earlier also. So we're not betting big there but the intention is to squeeze the last bit of water out the ring. The last drop of water out of the cloth layer."
CapEx & Capital Allocation
- FY24 budget: An ambitious ~₹2,500 crore capital budget was approved, roughly 4x the prior year's planned budget, with the majority directed toward land acquisition for Tadkeshwar and Bhavnagar assets and the Akrimota Thermal Power Station turnaround.
- Land acquisition is the first call on cash: Preparatory work was done in FY23, so the bulk of spending shifts to FY24; management expects the entire ~₹2,500 crore to be spent in the year as delivery work from FY23 converts to expenditure.
- Power plant turnaround: All hindrances at the power plant have been removed; management targets turning the asset around within 12 months, with RFPs expected in 2–3 months and improvements visible from February 2024.
- Governance promise: Management claims CapEx going forward will be "more sure footed and would have a better governance system than in the past," acknowledging past execution concerns.
- No formal distribution policy: When asked about adopting a shareholder distribution policy tied to a percentage of profits, management spoke about ploughing back money for expansion and IRRs but did not commit to any specific payout framework.
Roopwant Singh: "I believe the investor community should have faith in us and allow us to support us in this CapEx expenditure so that the company goes to newer levels. And the entire way the investor community sees us, that totally changes. That is what our aspiration is."
New Projects & Pipeline
- Lakhpat first to roll: Lakhpat is expected to be the first new mine to come online; one more project will break ground in Kutch, and two projects are being pursued aggressively in South Gujarat, with award of all these projects expected in the coming financial year and groundbreaking in 3–4 of them.
- Damlai adjacent to Rajpardi: An RFP has been floated for the Damlai project, with groundbreaking expected in FY24; product quality is described as comparable to Rajpardi, GMDC's best product, though the existing Rajpardi mine is nearly exhausted.
- Coal-block auction bid: GMDC is midway through bidding for coal mines in an auction, with results expected in March; if successful, management acknowledges implementation will be "the challenge" and says a marketing strategy and indicative customer list are ready.
- Medium-term lignite capacity: Management targets 1 crore tonnes of lignite in FY24 and expects capacity to reach 30 to 5 crore tonnes in 2–3 years, though it stresses it will produce only what can be sold, not expand mindlessly.
- Evacuation work in progress: Newer ways of evacuating lignite from Bhavnagar to South Gujarat are being explored, with the objective of ensuring consumption, not just production.
Roopwant Singh: "The point is if we win, it will be implementing, it will be the challenge."
Diversification Beyond Lignite
- Bauxite: A pilot beneficiation project will commence by end of February, with proof of concept targeted this financial year; disposal of stock has already begun, and management expects a "boom" in the bauxite division next financial year, targeting ~0.09 crore tonnes of disposal in FY24.
- Fluorspar: Plant refurbishing has started, with a trial run targeted by 15 August 2023 and production commencement by Q4.
- Rare earth elements: Management repeatedly declined to provide any timeline, detail on potential, consumption, pricing, or progress, citing "certain secrecy involved" around a critical mineral and promising full details only when clarification is available.
- Revenue aspiration: Management wants at least half of revenues to come from beyond lignite in the coming 2–3 years but acknowledges this is "easier said than done," calling non-lignite mining "even tougher" than opening a coal or lignite mine.
- Company scale ambition: Management states the company should be three or four times its current size in 5–6 years if it stays on the same trajectory, though it declined to give a specific timeline for reaching a billion-dollar top line.
Roopwant Singh: "Our aspiration is to have at least half our revenues coming from beyond lignite. Now this is easier said than done. Yes, it is a very difficult task to open a coal or lignite mine and to run it open and run a metal mine or a non-lignite mine is even tougher."
Operational Initiatives
- Project Shikhar (BCG): Under implementation; BCG has critically analyzed all business streams and directed efforts toward significant gains.
- ISAM (Institution for Center for Excellence in Mining): Being developed to emerge as a solution provider beyond a training institute; currently seeking a CEO, with movement expected in the coming 2–3 quarters.
- Digitization of mines: A process to be embarked upon for greater efficiency in mining operations; details to be shared in the coming year.
- Power plant regulatory progress: Permission has been received from the Gujarat Energy Regulatory Commission for a ₹300 crore CapEx pass-through, and a regulatory body has agreed to relook the PPA terms.
- Production discipline: Management explicitly states it will expand capacity but produce only what is required and can be sold, not chase volume for its own sake.
Roopwant Singh: "Yes, we are mindful we will not go mindlessly expanding. We will produce only that much what we can sell. We will expand our capacity but produce only what is required."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Bhavnagar production | 0.33 crore tonnes from Bhavnagar | FY24 |
| FY24 lignite volume | 1 crore tonnes | FY24 |
| FY24 CapEx spend | Entire ~₹2,500 crore budget to be spent | FY24 |
| Akrimota power plant turnaround | Asset turned around; RFPs in 2–3 months | 12 months from now |
| Damlai project | Groundbreaking (mobilization expenditure, minimal production) | FY24 |
| New project awards | Award of Lakhpat, Kutch, and two South Gujarat projects | Coming financial year |
| New project groundbreakings | Groundbreaking in 3–4 projects | Coming financial year |
| Fluorspar plant | Trial run by 15 August 2023; production commencement by Q4 | 15 Aug 2023 / Q4 |
| Bauxite beneficiation pilot | Pilot by end of February; proof of concept this financial year | End Feb / FY23 |
| Bauxite disposal | ~0.09 crore tonnes | FY24 |
| Medium-term lignite capacity | 3–5 crore tonnes | 2–3 years |
| Revenue diversification | At least half of revenues from beyond lignite | 2–3 years |
| Company scale | Three or four times current size, if on same trajectory | 5–6 years |
| Digitization of mines | Process to be embarked upon; details shared | Coming year |
| ISAM | Movement expected; CEO being sought | 2–3 quarters |
Key Metrics
| Metric | Q3 FY23 |
|---|---|
| Revenue | ~₹3,700–4,000 cr (FY23 estimate, per an analyst's statement) |
| PBT | Crossed best-ever full-year results in company history (9M FY23) |
| Lignite production | 19.38 lakh metric tons (0.19 cr MT), down 13% YoY from 0.22 cr MT |
| Lignite sales volume (total) | 55.78 lakh metric tons, comprising open market and own/GUVNL power plants |
| Lignite sales volume (open market) | 42.49 lakh metric tons |
| Lignite supplied to own/GUVNL power plants | 13.29 lakh metric tons |
| Realization per metric ton | ~₹4,200, broadly similar since April with minor correction in early Feb |
| Cash and cash equivalents | ~₹2,500 cr as of 31 Dec 2022, up from ~₹1,400 cr at end of FY22 |
| Cash yield | 6.5% on surplus deposited with GSFS |
| FY24 capital budget | ~₹2,500 cr, ~4x last year's planned budget; over ₹1,500 cr for land acquisition and thermal power station renovation |
| FY24 lignite volume target | 1 crore tons |
| Bhavnagar planned production | 0.33 crore tonnes in FY24, up from current run-rate of 0.13–0.14 cr tonnes |
| Bauxite disposal target (FY24) | ~0.09 crore tons |
| Surat textile cluster sales share | ~41% of total sales volume |
| Tadkeshwar production decline | ~35% due to two consecutive land-sliding incidents |