Godrej Properties Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/6ygl1qq6emh5uex13q934320.pdf

Key Takeaways


Guidance & Bookings Trajectory

Gaurav Pandey: "If we hit even 70%-80% of that, we should be able to achieve our guidance and if we are able to hit, many of it and at better pace performance than our initial conservative estimate, we could surprise."

Execution Ramp-Up & Construction Scale

Gaurav Pandey: "Our labour strength has reached an all-time high, we were give or take 20,000, 21,000 odd laborers at the start of the year. And by the time we wrapped up H1, we reached 32,000 laborers. This has never happened in terms of ramp up of our execution ever."

Profitability & Accounting Distortions

Pirojsha Godrej: "Net profit, I think honestly, we can -- the reported numbers are 58%, but I would agree that a lot of that is accounting related. And it's not something that I would pay much attention to in the short-term, because there are several dislocations for a company that's following the project completion accounting method, which not all of our peers are."

Market-by-Market Positioning

MarketTrendCommentary
Bangalore▲ Best performerAll micro-markets firing for 6-9 months; constrained by high-quality land supply limiting abstract supply; very strong end-user demand.
Mumbai▲ Consistent favouriteEnd-user centric, product-conscious, developer-conscious market; South Bombay, Western Suburb and Panvel are the most favoured micro-markets.
Hyderabad▲ Strong reboundRebounded in 2024 after 2023 stagnancy; ₹2,600 crores sales in two launches in first calendar year; management believes it could "surprise everyone in the long-term" due to best-in-India quality infrastructure.
NCR▬ Lagging H1, catching upSeemed to lag in first half; management confident of catching up to a ₹10,000 crores run rate with exciting launches planned; phase activation of Golf Course Road inventory in Q3 and Q4.
Pune▼ UnderdogPrices flattish despite Godrej being #1 player; Bangalore and Pune prices were similar 3-4 years ago but Bangalore has moved to a different league while Pune has not picked up.
Gurgaon▲ Healthier marketManagement intentionally avoided sold-out launches, focusing on quality of sales: no multiple units per customer, detailed KYC checks, rejecting speculative bookings.
Gaurav Pandey: "Our idea was not to do consciously sold out projects, but to do extreme strong quality of sales. When I say quality of sales meaning that unlike many of our peers, we do not allow multiple units to be bought by a customer. If we do see that there is a speculative tendency, we do not log in that booking, we have detailed KYC checks."

Key Project Updates

Gaurav Pandey: "Some of the area share that we've changed is largely to benefit our interest and get higher economic interest, because we're also trying to control specific units, specific floors, specific inventory, which is always easier to do when you do a sort of area share structure."

Capital Position & Equity

Pirojsha Godrej: "I think as of now, we certainly don't have any plans and I think it's highly unlikely that there would be any equity raise between now and then."

Guidance & Commitments

CommitmentSpecificsTimeline
Booking valueBeat guidance of ₹32,500 croresFY26
CollectionsAchieve ₹21,000 crores guidanceFY26
Business developmentSecond-half BD roughly in line with salesFY26
ROEDeliver 20% ROEFY'28
NCR deliveries~4,000 homes delivered in NCRNext 6-9 months
Bandra launchLaunch the projectCalendar year 2026
Kharghar launchThree auction parcels hit the marketLikely Q4 FY26
Equity raiseNo equity raise plannedBetween now and FY'28

Key Metrics

MetricQ2 FY26
Booking value₹8,505 cr, +64% YoY and +20% QoQ
H1 FY26 booking value₹15,587 cr, +13% YoY, highest ever H1
Booking value guidance achieved48% of ₹32,500 cr annual guidance
Collections₹4,066 cr, +2% YoY and +11% QoQ
H1 FY26 collections₹7,736 cr, +10% YoY
Collections guidance achieved37% of ₹21,000 cr annual guidance
Total income₹1,867 cr, +39% YoY
EBITDA₹614 cr, +118% YoY
Net profit₹405 cr, +21% YoY
H1 FY26 net profit₹1,005 cr, +18% YoY
Business development — projects added4 new projects, estimated saleable area 0.58 cr sq ft, expected booking value just under ₹5,000 cr
H1 FY26 business development9 projects, 1.5 cr sq ft, expected booking value ₹16,250 cr, 81% of annual guidance
Construction spend growth+82% YoY in Q2
Labour strength32,000 at end of H1, up from ~21,000 at start of year
Share of sales (own projects)87%
National residential market share4.3% of total sales (last year)
Deliveries (last year)1.8 cr sq ft
Operating cash flow (H1 FY26)~₹2,100 cr
Operating cash flow (full year FY25)₹7,500 cr
ROE target20% by FY28, implying ₹4,000–₹4,500 cr PAT (per an analyst's math)